Skip to content

Ews-4 Floors-8 Phase-I · Sector 21 Taloja

Pendhar · RERA P52000017439

IDBLD_0141268 floorsExtended 18 mo
8Sanctioned habitable floorsregistration certificate
30 Sep 2022Revised completionpromised 31 Mar 2021
27 of 48Units bookedMahaRERA project page

Floors

8 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52000017439 · registered 13 Aug 2018
Promised completion
31 Mar 2021
Revised completion
30 Sep 2022
Sanctioned habitable floors
8
ProjectId
19,340
ProjectName
SECTOR 21 TALOJA
TotalUnitCount
0
ProjectBuildingId
19,615
BuildingNameNumber
EWS-4 FLOORS-8 PHASE-I
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52000017439
ProjectBuildingWingsId
19,615
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
EWS-4 FLOORS-8 PHASE-I
NoOfBuildingWingFloorProposed
8
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
8

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
EWS RESIDENTIAL25.8 m² (278 sq.ft)4827
Total4827
Data through12 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology