Building No- 10 · Sai Prasad Garden- Phase 2
Nevali · RERA P52000019248
IDBLD_0152675 floorsExtended 12 mo
5Sanctioned habitable floorsregistration certificate
29 Dec 2024Revised completionpromised 30 Dec 2023
16 of 16Units bookedMahaRERA project page
Floors
5 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52000019248 · registered 14 Jan 2019
- Promised completion
- 30 Dec 2023
- Revised completion
- 29 Dec 2024
- Sanctioned habitable floors
- 5
- ProjectId
- 20,140
- ProjectName
- SAI PRASAD GARDEN- PHASE 2
- TotalUnitCount
- 0
- ProjectBuildingId
- 20,986
- BuildingNameNumber
- BUILDING NO- 10
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52000019248
- ProjectBuildingWingsId
- 20,986
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- BUILDING NO- 10
- NoOfBuildingWingFloorProposed
- 5
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 5
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 34.4 m² (370 sq.ft) | 4 | 4 |
| 1BHK | 34.4 m² (370 sq.ft) | 4 | 4 |
| 1BHK | 34.4 m² (370 sq.ft) | 4 | 4 |
| 1BHK | 34.4 m² (370 sq.ft) | 4 | 4 |
| Total | 16 | 16 |
Data through12 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology