Skip to content

Building-1 · Sai Nilay

Harigram · RERA PR1270002602134

IDBLD_0870649 floorsNot yet due
9Sanctioned habitable floorsregistration certificate
31 Dec 2030Revised completionpromised 31 Dec 2030

Floors

9 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
PR1270002602134 · registered 5 Oct 2026
Promised completion
31 Dec 2030
Revised completion
31 Dec 2030
Sanctioned habitable floors
9
ProjectId
66,522
ProjectName
Sai Nilay
TotalUnitCount
96
ProjectBuildingId
2,01,319
BuildingNameNumber
Building-1
FsiWithSanctionSqmts
Ground Floor + 1st to 8th Floor
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
86
ProjectRegistartionNo
PR1270002602134
ProjectBuildingWingsId
2,10,491
BuildingWingsNameNumber
NA
NonResidentialUnitCount
10
AdvertisedBuildingNameNumber
Sai Nilay
NoOfBuildingWingFloorProposed
9
NoOfBuildingWingFloorHabitable
9
NoOfBuildingWingFloorSanctioned
9

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
——96not published
Total96
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology