Gulab Shilp

Certificate Signed

Warje, Pune 411058 |Promoter: Buttepatil Properties

Residential / Group HousingRERAP52100032862
2 Feb 2022Registered with MahaRERA
31 Mar 2027Promised completion
31 Jul 2027Revised completionPushed back 4 months
1Building
50Units registered50 booked (100%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK50 units in all
Address
80/2/1, Dodke Park Road, AtulnagarPIN 411058
Designated bank account
154
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.48521, 73.79405
Gulab Shilp is at latitude 18.48521, longitude 73.79405.

Registered transactions

12 registered documents matched to this project. Consideration is the value declared in the document; the Index II opens inside Deedo.

Registered transactions in this project
RegisteredUnitTypeConsideration₹ / sq.ftDocument
13 Oct 2026
Primary sale≈ ₹54 L≈ ₹9,075
13 Oct 2026
Cancellation≈ ₹10,000—
27 Aug 2026
Primary sale≈ ₹70 L≈ ₹10,574
11 Aug 2026
Primary sale≈ ₹52 L≈ ₹11,791
31 Jul 2026
Bldg Name · Unit 202
Rental≈ ₹60,000—
10 Jul 2026
Primary sale≈ ₹65 L≈ ₹10,449
5 May 2026
Bldg Name · Unit 201
Rental≈ ₹60,000—
7 Jan 2026
Bldg Name · Unit 404
Rental≈ ₹60,000—
2 Sep 2025
Bldg Name · Unit 202
Rental≈ ₹60,000—
25 Jul 2025
Bldg Name · Unit 201
Rental≈ ₹60,000—
25 Jun 2025
Bldg Name · Unit 201
Rental≈ ₹1 L—
4 Jun 2025
Bldg Name · Unit 202
Rental≈ ₹50,000—

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
2 Feb 2022
Promised
31 Mar 2027
Revised
31 Jul 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000328622 Feb 202231 Mar 202731 Jul 2027Buttepatil PropertiesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Gulab Shilp1150

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

50 of 50 units booked (100%), as the promoter reported to MahaRERA

1BHK · 10 units2BHK · 40 units
TypeCarpet areaUnitsBooked
1BHK45.43 sq m · 489 sq ft1010
2BHK57.04 sq m · 614 sq ft1010
2BHK60.2 sq m · 648 sq ft1010
2BHK65.4 sq m · 704 sq ft1010
2BHK66.33 sq m · 714 sq ft1010

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 123 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardPROP.pdf · uploaded 18 Jan 2022Source

Legal

  • Legal Title reportWarje Rera Legal Title Report.pdf · uploaded 25 Dec 2021Source
  • Declaration Form Bform B.pdf · uploaded 19 Jan 2022Source
  • Declaration Form BAffidavit Cum Declaration Form B EXTENSION.pdf · uploaded 15 Mar 2024Source
  • Declaration Form BFORM B rera warje 19225.pdf · uploaded 19 Feb 2025Source
  • Declaration Form BFORM B Warje Delaration 110425.pdf · uploaded 11 Apr 2025Source
Show all 125 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportWarje Rera Legal Title Report.pdf · uploaded 25 Dec 2021Source
  • 1 Copy of Layout Approval (in case of layout)Declaration Layout.pdf · uploaded 25 Dec 2021Source
  • 1 Declaration about Commencement CertificateDeclaration C C.pdf · uploaded 25 Dec 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTI WARJE.pdf · uploaded 25 Dec 2021Source
  • 1 Proforma of Allotment letterAGREEMENT FOR SALE-Warje-Buttepatil.pdf · uploaded 25 Dec 2021Source
  • 2 Proforma of Allotment letterAllotment Letter.pdf · uploaded 25 Dec 2021Source
  • 1 CERSAI detailsCERSAI-WARJE GULAB SHILP-.pdf · uploaded 27 Dec 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentWARAJE PLAN.pdf · uploaded 3 Jan 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentWARAJE CC.pdf · uploaded 3 Jan 2022Source
  • 1 PAN CardPROP.pdf · uploaded 18 Jan 2022Source
  • 1 Declaration in FORM Bform B.pdf · uploaded 19 Jan 2022Source
  • 1 Details of encumbrancesENCUMBRANCE WARJE.pdf · uploaded 27 Jan 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentWARJE PLAN 1.pdf · uploaded 12 Jan 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentWARJE PLAN 2.pdf · uploaded 12 Jan 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentWarje CC.pdf · uploaded 12 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)GULAB SHILP FORM 5 MAR-2022.pdf · uploaded 8 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Gulab Shilp EC March 2022.pdf · uploaded 19 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Gulab Shilp EC June 2022.pdf · uploaded 19 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Gulab Shilp EC Sept 2022.pdf · uploaded 19 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Gulab Shilp EC Dec 2022.pdf · uploaded 19 Jan 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Gulab Shilp EC March 2023.pdf · uploaded 19 Jan 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Gulab Shilp EC June 2023.pdf · uploaded 19 Jan 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Gulab Shilp EC Sept 2023.pdf · uploaded 19 Jan 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Gulab Shilp EC Dec 2023.pdf · uploaded 19 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A QUALITY ASSU MAR 22.pdf · uploaded 19 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A QUALITY ASSU MAR 23.pdf · uploaded 19 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Gulab Shilp Dec 2022 (1).pdf · uploaded 19 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Gulab Shilp March 2023 (1).pdf · uploaded 19 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Gulab Shilp June 2023 (1).pdf · uploaded 19 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Gulab Shilp Sept 2023 (1).pdf · uploaded 19 Jan 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Gulab Shilp Dec 2023 (1).pdf · uploaded 19 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 MAR 23 GULAB SHILP.pdf · uploaded 23 Jan 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)AC DEC 2022 GULAB SHILP.pdf · uploaded 25 Jan 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)AC MAR 2023 GULAB SHILP.pdf · uploaded 25 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)AC JUNE 2023 GULAB SHILP.pdf · uploaded 25 Jan 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)AC SEP 2023 GULAB SHILP.pdf · uploaded 25 Jan 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)AC DEC 2023 GULAB SHILP.pdf · uploaded 25 Jan 2024Source
  • 2 Declaration in FORM BAffidavit Cum Declaration Form B EXTENSION.pdf · uploaded 15 Mar 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 STAMP WARJE.pdf · uploaded 18 Mar 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A WARJE STAMP.pdf · uploaded 18 Mar 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A WARJE STAMP.pdf · uploaded 18 Mar 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure Of Sold Unsold WARJE.pdf · uploaded 18 Mar 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 WARJE STAMP.pdf · uploaded 18 Mar 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGIN FORM 2.pdf · uploaded 19 Mar 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA G SHILP mar 24 C.pdf · uploaded 21 Jul 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA G SHILP june 24 C.pdf · uploaded 21 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 GULAB SHILP mar 24.pdf · uploaded 21 Jul 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR CERTI Gulab Shilp MAR 24.pdf · uploaded 22 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Gulab Shilp ArC Sept 2024.pdf · uploaded 7 Nov 2024Source
  • 1 Declaration in FORM BFORM B rera warje 19225.pdf · uploaded 19 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC SHILP DEC 24.pdf · uploaded 21 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 Q2 Gulab Shilp.pdf · uploaded 21 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 Q2 gulab shilp.pdf · uploaded 22 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q3 GULAB SHILP.pdf · uploaded 22 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2 Form 2 Gulab Shilp 300624.pdf · uploaded 22 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4 form 2 310324.pdf · uploaded 22 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 Q3 Gulab Shilp.pdf · uploaded 22 Feb 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest.pdf · uploaded 22 Feb 2025Source
  • 1 Declaration in FORM BFORM B Warje Delaration 110425.pdf · uploaded 11 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure Of Sold Unsold WARJE 17225.pdf · uploaded 11 Apr 2025Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentWarje Part Completion Certificate_compressed.pdf · uploaded 15 Apr 2025Source
  • Form 1Gulab Shilp Form 1 Arch Mar 25 Q4.pdf · uploaded 27 May 2025Source
  • Form 2Gulab Shilp Form 2 Eng Mar 25 Q4.pdf · uploaded 27 May 2025Source
  • Form 3GULAB SHILP Form 3 CA Mar 25 Q4.pdf · uploaded 27 May 2025Source
  • Withdrawal Update Form 1form 1 warje 151025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 1form 1 warje 151025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 1form 1 warje 151025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 1form 1 warje 150725.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 2warje form 2 151025 1.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 2warje form 2 151025 1.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 2warje form 2 151025 1.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 2form 2 warje 050725.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 3WARJE FORM 3 151025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 3WARJE FORM 3 151025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 3WARJE FORM 3 151025.pdf · uploaded 18 Oct 2025Source
  • Withdrawal Update Form 3form3 warje q1 25.pdf · uploaded 18 Oct 2025Source
  • Form 5 (FY 2024-2025)FORM-5 GULAB SHILP.pdf · uploaded 7 Nov 2025Source
  • Form 2A (FY 2024-2025)Gulab Shilp 2A.pdf · uploaded 10 Nov 2025Source
  • Withdrawal Update Form 1Gulab Shilp Down Arc.pdf · uploaded 30 Mar 2026Source
  • Withdrawal Update Form 2Gulab Shilp Eng cer Form 2 Q3.pdf · uploaded 30 Mar 2026Source
  • Withdrawal Update Form 3Gulab Shilp Form 3.pdf · uploaded 30 Mar 2026Source
  • Withdrawal Update Form 1ARC SHILP Q4.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 2EC SHILP Q4.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 3CA SHILP Q4.pdf · uploaded 7 May 2026Source
  • Form 2A (FY 2021-2022)Form 2A Gulab Shilp 23 24.pdf · uploaded 30 Jul 2026Source
  • Form 2A (FY 2022-2023)Form 2A Gulab Shilp 23 24.pdf · uploaded 30 Jul 2026Source
  • Form 2A (FY 2023-2024)Form 2A Gulab Shilp 23 24.pdf · uploaded 30 Jul 2026Source
  • Form 2A (FY 2025-2026)Form 2A Gulab Shilp 24 25.pdf · uploaded 30 Jul 2026Source
  • Form 2A (FY 2026-2027)Form 2A Serenity Springs 25 26.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1ARC SHILP Q4.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 2EC SHILP Q4.pdf · uploaded 4 Aug 2026Source
  • Withdrawal Update Form 3CA SHILP Q4.pdf · uploaded 4 Aug 2026Source
  • Occupational CertificateGULAB SHILP Completion Cer - 1.pdf · uploaded 21 Sep 2026Source
  • Occupational CertificateGULAB SHILP 1st Sanation Plan.pdf · uploaded 21 Sep 2026Source
  • Occupational CertificateGULAB SHILP Completion Cer - 2.pdf · uploaded 21 Sep 2026Source
  • Occupational CertificateGulab Shilp 2nd Sancation Plan.pdf · uploaded 21 Sep 2026Source
  • Occupational CertificateGulab Shilp Completion Cer - 3.pdf · uploaded 21 Sep 2026Source
  • Occupational CertificateWarje 3rd Sanction Plan_260626_115454 - new.pdf · uploaded 21 Sep 2026Source
  • Occupational Certificateemail.pdf · uploaded 21 Sep 2026Source

Technical

  • DocumentDeclaration Layout.pdf · uploaded 25 Dec 2021Source
  • DocumentWARAJE PLAN.pdf · uploaded 3 Jan 2022Source
  • DocumentWARJE PLAN 1.pdf · uploaded 12 Jan 2023Source
  • DocumentWARJE PLAN 2.pdf · uploaded 12 Jan 2023Source
  • DocumentWarje 3rd Sanction PLAN 1.pdf · uploaded 1 Apr 2026Source
  • DocumentWarje 3rd Sanction PLAN 2.pdf · uploaded 1 Apr 2026Source
  • DocumentWarje 3rd Sanction PLAN 3.pdf · uploaded 1 Apr 2026Source
  • DocumentWarje 3rd Sanction PLAN 1.pdf · uploaded 1 Apr 2026Source
  • DocumentWarje 3rd Sanction PLAN 2.pdf · uploaded 1 Apr 2026Source
  • DocumentWarje 3rd Sanction PLAN 3.pdf · uploaded 1 Apr 2026Source

Technical (Architect)

  • DocumentGulab Shilp ArC Sept 2024.pdf · uploaded 7 Nov 2024Source
  • DocumentARC SHILP DEC 24.pdf · uploaded 21 Feb 2025Source
  • DocumentARC SHILP Q4.pdf · uploaded 3 Aug 2026Source

Technical (Engineer)

  • Documentform 2 Q2 Gulab Shilp.pdf · uploaded 21 Feb 2025Source
  • DocumentQ2 Form 2 Gulab Shilp 300624.pdf · uploaded 22 Feb 2025Source
  • DocumentQ4 form 2 310324.pdf · uploaded 22 Feb 2025Source
  • Documentform 2 Q3 Gulab Shilp.pdf · uploaded 22 Feb 2025Source
  • DocumentEC SHILP Q4.pdf · uploaded 7 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Warje, Haveli taluka

Survey, CTS, gat or plot numbers

80/2/1

Boundaries

North
Road
South
Atulnagar
East
Barate Property
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSiddhart Harishchandrakar—
Chartered accountantAmbar Naik—
EngineerKalpesh Manani—
EngineerParag Chopda—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology