RGS Forte

Certificate Signed

Wakad, Pune 411057 |Promoter: RGS Realty LLP

5 Apr 2022Registered with MahaRERA
31 Mar 2027Promised completion
31 Jul 2027Revised completionPushed back 4 months
2Buildings
185Units registered140 booked (76%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
2BHK, 3BHK, Mahada.1BHK, Mahada.2BHK, Shop185 units in all
Address
S No. 113/1/1, Bhumkardas Gugre Road, Bhumkar Nagar, WakadPIN 411057
Designated bank account
76
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.60494, 73.74533
RGS Forte is at latitude 18.60494, longitude 73.74533.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
5 Apr 2022
Promised
31 Mar 2027
Revised
31 Jul 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000344435 Apr 202231 Mar 202731 Jul 2027RGS Realty LLPProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Tower-A2196
Tower-B2189

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

140 of 185 units booked (76%), as the promoter reported to MahaRERA

2BHK · 8 units3BHK · 152 unitsMahada.1BHK · 11 unitsMahada.2BHK · 5 unitsShop · 9 units
BuildingTypeCarpet areaUnitsBooked
Tower-A2BHK68.85 sq m · 741 sq ft42
Tower-A3BHK77.68 sq m · 836 sq ft119
Tower-A3BHK77.86 sq m · 838 sq ft96
Tower-A3BHK82.39 sq m · 887 sq ft3622
Tower-A3BHK86.45 sq m · 931 sq ft123
Tower-A3BHK86.82 sq m · 935 sq ft83
Tower-AMahada.1BHK31.76 sq m · 342 sq ft11
Tower-AMahada.1BHK35.21 sq m · 379 sq ft11
Show all 29 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Tower-AMahada.1BHK37.96 sq m · 409 sq ft10
Tower-AMahada.1BHK39.79 sq m · 428 sq ft21
Tower-AMahada.1BHK40.7 sq m · 438 sq ft44
Tower-AMahada.1BHK41.03 sq m · 442 sq ft10
Tower-AMahada.1BHK41.05 sq m · 442 sq ft11
Tower-AMahada.2BHK41.53 sq m · 447 sq ft42
Tower-AMahada.2BHK42.68 sq m · 459 sq ft11
Tower-B2BHK67.21 sq m · 723 sq ft44
Tower-B3BHK82.39 sq m · 887 sq ft1615
Tower-B3BHK85.24 sq m · 918 sq ft2019
Tower-B3BHK86.45 sq m · 931 sq ft2322
Tower-B3BHK86.82 sq m · 935 sq ft1716
Tower-BShop31.55 sq m · 340 sq ft11
Tower-BShop42.11 sq m · 453 sq ft11
Tower-BShop47.85 sq m · 515 sq ft11
Tower-BShop49.64 sq m · 534 sq ft11
Tower-BShop55.03 sq m · 592 sq ft11
Tower-BShop60.89 sq m · 655 sq ft11
Tower-BShop66.36 sq m · 714 sq ft11
Tower-BShop72.74 sq m · 783 sq ft10
Tower-BShop86.15 sq m · 927 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 211 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardRGS REALTY LLP PAN.PDF · uploaded 24 Mar 2022Source

Legal

  • Declaration Form BFORM - B_compressed.pdf · uploaded 24 Mar 2022Source
  • OtherEC.pdf · uploaded 25 Mar 2022Source
  • Legal Title reportLegal Title As Per RERA_compressed.pdf · uploaded 29 Mar 2022Source

Migrated

  • 1 Details of encumbrancesENCUMBRANCE LETTER.PDF · uploaded 15 Mar 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentffssfyu002_compressed.pdf · uploaded 15 Mar 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentffssfyu003_compressed.pdf · uploaded 15 Mar 2022Source
Show all 212 documentsShow fewer documents

Migrated

  • 3 Building Plan Approval / NA Order for plotted developmentffssfyu004_compressed.pdf · uploaded 15 Mar 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentffssfyu005_compressed.pdf · uploaded 15 Mar 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentffssfyu006_compressed.pdf · uploaded 15 Mar 2022Source
  • 6 Building Plan Approval / NA Order for plotted developmentffssfyu007_compressed.pdf · uploaded 15 Mar 2022Source
  • 7 Building Plan Approval / NA Order for plotted developmentffssfyu008_compressed.pdf · uploaded 15 Mar 2022Source
  • 8 Building Plan Approval / NA Order for plotted developmentffssfyu009_compressed.pdf · uploaded 15 Mar 2022Source
  • 9 Building Plan Approval / NA Order for plotted developmentffssfyu010_compressed_compressed.pdf · uploaded 15 Mar 2022Source
  • 10 Building Plan Approval / NA Order for plotted developmentffssfyu011_compressed.pdf · uploaded 15 Mar 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 15 Mar 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200232508197_For_Asset_Based_Search_15_03_2022_17_11_16_375.pdf · uploaded 15 Mar 2022Source
  • 1 Proforma of Allotment letterAgreement Draft - RGS Forte.pdf · uploaded 16 Mar 2022Source
  • 2 Proforma of Allotment letterAllotment Letter - RGS FORTE.pdf · uploaded 16 Mar 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Signed-1.pdf · uploaded 17 Mar 2022Source
  • 1 PAN CardRGS REALTY LLP PAN.PDF · uploaded 24 Mar 2022Source
  • 1 Declaration in FORM BFORM - B_compressed.pdf · uploaded 24 Mar 2022Source
  • 1 Copy of Layout Approval (in case of layout)Building Plan IOD_compressed.pdf · uploaded 25 Mar 2022Source
  • 1 OtherEC.pdf · uploaded 25 Mar 2022Source
  • 1 Copy of the legal title reportLegal Title As Per RERA_compressed.pdf · uploaded 29 Mar 2022Source
  • 1 Declaration about Commencement CertificateFORM - D.PDF · uploaded 29 Mar 2022Source
  • 11 Building Plan Approval / NA Order for plotted developmentvggf004_compressed.pdf · uploaded 30 Apr 2022Source
  • 12 Building Plan Approval / NA Order for plotted developmentvggf005_compressed.pdf · uploaded 30 Apr 2022Source
  • 13 Building Plan Approval / NA Order for plotted developmentvggf006_compressed.pdf · uploaded 30 Apr 2022Source
  • 14 Building Plan Approval / NA Order for plotted developmentvggf007_compressed.pdf · uploaded 30 Apr 2022Source
  • 15 Building Plan Approval / NA Order for plotted developmentvggf008 (1)_compressed.pdf · uploaded 30 Apr 2022Source
  • 16 Building Plan Approval / NA Order for plotted developmentvggf009_compressed.pdf · uploaded 30 Apr 2022Source
  • 17 Building Plan Approval / NA Order for plotted developmentvggf010_compressed.pdf · uploaded 30 Apr 2022Source
  • 18 Building Plan Approval / NA Order for plotted developmentvggf011_compressed.pdf · uploaded 30 Apr 2022Source
  • 19 Building Plan Approval / NA Order for plotted developmentvggf012_compressed.pdf · uploaded 30 Apr 2022Source
  • 2 Details of encumbrancesENCUMBARANCE CERTIFICATE.PDF · uploaded 6 Sep 2022Source
  • 2 Copy of Layout Approval (in case of layout)n1vhyg035.pdf · uploaded 7 Feb 2023Source
  • 20 Building Plan Approval / NA Order for plotted developmentn1vhyg036.pdf · uploaded 7 Feb 2023Source
  • 21 Building Plan Approval / NA Order for plotted developmentn1vhyg037.pdf · uploaded 7 Feb 2023Source
  • 22 Building Plan Approval / NA Order for plotted developmentn1vhyg038.pdf · uploaded 7 Feb 2023Source
  • 23 Building Plan Approval / NA Order for plotted developmentn1vhyg039.pdf · uploaded 7 Feb 2023Source
  • 24 Building Plan Approval / NA Order for plotted developmentn1vhyg041.pdf · uploaded 7 Feb 2023Source
  • 25 Building Plan Approval / NA Order for plotted developmentn1vhyg042.pdf · uploaded 7 Feb 2023Source
  • 26 Building Plan Approval / NA Order for plotted developmentn1vhyg043.pdf · uploaded 7 Feb 2023Source
  • 27 Building Plan Approval / NA Order for plotted developmentn1vhyg044.pdf · uploaded 7 Feb 2023Source
  • 28 Building Plan Approval / NA Order for plotted developmentn1vhyg045.pdf · uploaded 7 Feb 2023Source
  • 29 Building Plan Approval / NA Order for plotted developmentn1vhyg046.pdf · uploaded 7 Feb 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentn1vhyg040.pdf · uploaded 7 Feb 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameRGS RERA AC.PDF · uploaded 20 Mar 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)RGS Realty - Form 1_compressed.pdf · uploaded 22 May 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_compressed.pdf · uploaded 22 May 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate New Format - RGS.pdf · uploaded 22 May 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Inventory Q4.pdf · uploaded 5 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A RGS Forte.pdf · uploaded 6 Jul 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A RGS Forte.pdf · uploaded 6 Jul 2023Source
  • 3 Copy of Layout Approval (in case of layout)Layout Apporval_Compressed.pdf · uploaded 11 Jul 2023Source
  • 30 Building Plan Approval / NA Order for plotted developmentBuilding Plan 1_Compressed.pdf · uploaded 11 Jul 2023Source
  • 31 Building Plan Approval / NA Order for plotted developmentBuilding Plan 2_Compressed.pdf · uploaded 11 Jul 2023Source
  • 32 Building Plan Approval / NA Order for plotted developmentBuilding Plan 3_Compressed.pdf · uploaded 11 Jul 2023Source
  • 33 Building Plan Approval / NA Order for plotted developmentBuilding Plan 4_Compressed.pdf · uploaded 11 Jul 2023Source
  • 34 Building Plan Approval / NA Order for plotted developmentBuilding Plan 5_Compressed.pdf · uploaded 11 Jul 2023Source
  • 35 Building Plan Approval / NA Order for plotted developmentBuilding Plan 6_Compressed.pdf · uploaded 11 Jul 2023Source
  • 36 Building Plan Approval / NA Order for plotted developmentBuilding Plan 7_Compressed.pdf · uploaded 11 Jul 2023Source
  • 37 Building Plan Approval / NA Order for plotted developmentBuilding Plan 8_Compressed.pdf · uploaded 11 Jul 2023Source
  • 38 Building Plan Approval / NA Order for plotted developmentBuilding Plan 9_Compressed.pdf · uploaded 11 Jul 2023Source
  • 39 Building Plan Approval / NA Order for plotted developmentBuilding Plan 10_Compressed.pdf · uploaded 11 Jul 2023Source
  • 40 Building Plan Approval / NA Order for plotted developmentBuilding Plan 11_Compressed.pdf · uploaded 11 Jul 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate New Format.PDF · uploaded 4 Aug 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate New Format - RGS Signed_11zon.pdf · uploaded 9 Feb 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA-certificate RGS RELATY Signed.PDF · uploaded 9 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RGS Realty LLP Form 5.PDF · uploaded 9 Feb 2024Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration Format A on Separate bank account.PDF · uploaded 9 Feb 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate September 2023.PDF · uploaded 10 Feb 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate December 2023.PDF · uploaded 10 Feb 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate September 2023.PDF · uploaded 10 Feb 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate December 2023.PDF · uploaded 10 Feb 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of Inventory_11zon.pdf · uploaded 13 Feb 2024Source
  • 3 Disclosure of sold/ booked inventoryDisclosure of Inventory September 2023.PDF · uploaded 13 Feb 2024Source
  • 4 Disclosure of sold/ booked inventoryDisclosure of Inventory December 2023.PDF · uploaded 13 Feb 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate March 2024.PDF · uploaded 29 May 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate March 2024.PDF · uploaded 29 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.PDF · uploaded 29 May 2024Source
  • 5 Disclosure of sold/ booked inventoryDislosure of inventory.PDF · uploaded 29 May 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA-Certificate RGS REALTY Signed.PDF · uploaded 29 May 2024Source
  • 2 Declaration about Commencement CertificateCC Declaration.PDF · uploaded 20 Jul 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.PDF · uploaded 20 Jul 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.PDF · uploaded 20 Jul 2024Source
  • 6 Disclosure of sold/ booked inventoryDisclosure of Inventory - June 2024.PDF · uploaded 20 Jul 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate New Format - RGS -Sign.PDF · uploaded 20 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect certificate Signed.PDF · uploaded 2 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate New Format - RGS Signed.PDF · uploaded 2 Dec 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of Inventory - September 2024 Signed.PDF · uploaded 2 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.PDF · uploaded 3 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate Dec 2024.PDF · uploaded 24 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate New Format - RGS - Signed.PDF · uploaded 24 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Dec 2024.PDF · uploaded 24 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Inventory - December 2024.PDF · uploaded 24 Jan 2025Source
  • 1 Copy of Layout Approval (in case of layout)Layout Approval.pdf · uploaded 18 Feb 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 18 Feb 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentBuilding Plan 4.pdf · uploaded 18 Feb 2025Source
  • 12 Building Plan Approval / NA Order for plotted developmentBuilding Plan 12.pdf · uploaded 18 Feb 2025Source
  • 11 Building Plan Approval / NA Order for plotted developmentBuilding Plan 11.pdf · uploaded 18 Feb 2025Source
  • 10 Building Plan Approval / NA Order for plotted developmentBuilding Plan 10.pdf · uploaded 18 Feb 2025Source
  • 9 Building Plan Approval / NA Order for plotted developmentBuilding Plan 9.pdf · uploaded 18 Feb 2025Source
  • 8 Building Plan Approval / NA Order for plotted developmentBuilding Plan 8.pdf · uploaded 18 Feb 2025Source
  • 7 Building Plan Approval / NA Order for plotted developmentBuilding Plan 7.pdf · uploaded 18 Feb 2025Source
  • 6 Building Plan Approval / NA Order for plotted developmentBuilding Plan 6.pdf · uploaded 18 Feb 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentBuilding Plan 5.pdf · uploaded 18 Feb 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentBuilding Plan 3.pdf · uploaded 18 Feb 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan 2.pdf · uploaded 18 Feb 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan 1.pdf · uploaded 18 Feb 2025Source
  • 1 Declaration about Commencement CertificateCC Declaration.PDF · uploaded 18 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)RERA Form 5 RGS Forte.pdf · uploaded 26 Feb 2025Source
  • Form 1Form 1 Architects Certificate March 2025.pdf · uploaded 14 Jul 2025Source
  • Form 2Form 2 Engineer Certificate March 2025.PDF · uploaded 14 Jul 2025Source
  • Form 3Form 3 CA Certificate - RGS March 2025 Signed.PDF · uploaded 14 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure Of Inventory March 2025.PDF · uploaded 14 Jul 2025Source
  • Withdrawal Update Form 1Form 1 Architects Certificate June 25.PDF · uploaded 28 Jul 2025Source
  • Withdrawal Update Form 2Form 2 Engineers Certificate June 25.PDF · uploaded 28 Jul 2025Source
  • Withdrawal Update Form 3RGS Realty LLP Form-3 CA Certificate Q-1 Compressed.pdf · uploaded 28 Jul 2025Source
  • Withdrawal Update Form 1Form 1 Architect Certificate September 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Architect Certificate September 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Architect Certificate September 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Architect Certificate September 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Engineers Certificate - Sept 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Engineers Certificate - Sept 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Engineers Certificate - Sept 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Engineers Certificate - Sept 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 3Form 3 CA Certificate - Sept 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 3Form 3 CA Certificate - Sept 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 3Form 3 CA Certificate - Sept 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 3Form 3 CA Certificate - Sept 2025.PDF · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Architect Certificate September 2025.PDF · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Architect Certificate September 2025.PDF · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Engineers Certificate - Sept 2025.PDF · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Engineers Certificate - Sept 2025.PDF · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 3Form 3 CA Certificate - Sept 2025.PDF · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 3Form 3 CA Certificate - Sept 2025.PDF · uploaded 4 Nov 2025Source
  • Form 5 (FY 2024-2025)CA Form 5_RGS_FY 2024-25_Signed.PDF · uploaded 17 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Architects Certificate - December 2025.pdf · uploaded 15 Jan 2026Source
  • Withdrawal Update Form 2Form 2 Engineer Certificate - December 2025.pdf · uploaded 15 Jan 2026Source
  • Withdrawal Update Form 3Form 3 CA Certificate - December 2025.PDF · uploaded 15 Jan 2026Source
  • Withdrawal Update Form 1FORM 1 RGS Forte Architects Certificate.PDF · uploaded 18 Apr 2026Source
  • Withdrawal Update Form 2FORM 2RGS Forte Engineer Certificate.PDF · uploaded 18 Apr 2026Source
  • Withdrawal Update Form 3FORM 3 RGS Forte CA Certificate.pdf · uploaded 18 Apr 2026Source
  • Form 2A (FY 2025-2026)RGS Forte Form 2A Engineers Certificate.PDF · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 1Form 1 Architects Certificate June 26 Forte.PDF · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Engineer Certificate June 26 Forte.PDF · uploaded 18 Jul 2026Source
  • Withdrawal Update Form 3Form 3 CA Certificate June 2026.pdf · uploaded 18 Jul 2026Source

Technical

  • Documentffssfyu002_compressed.pdf · uploaded 15 Mar 2022Source
  • Documentffssfyu003_compressed.pdf · uploaded 15 Mar 2022Source
  • Documentffssfyu004_compressed.pdf · uploaded 15 Mar 2022Source
  • Documentffssfyu005_compressed.pdf · uploaded 15 Mar 2022Source
  • Documentffssfyu006_compressed.pdf · uploaded 15 Mar 2022Source
  • Documentffssfyu007_compressed.pdf · uploaded 15 Mar 2022Source
  • Documentffssfyu008_compressed.pdf · uploaded 15 Mar 2022Source
  • Documentffssfyu009_compressed.pdf · uploaded 15 Mar 2022Source
  • Documentffssfyu010_compressed_compressed.pdf · uploaded 15 Mar 2022Source
  • Documentffssfyu011_compressed.pdf · uploaded 15 Mar 2022Source
  • DocumentBuilding Plan IOD_compressed.pdf · uploaded 25 Mar 2022Source
  • Documentvggf004_compressed.pdf · uploaded 30 Apr 2022Source
  • Documentvggf005_compressed.pdf · uploaded 30 Apr 2022Source
  • Documentvggf006_compressed.pdf · uploaded 30 Apr 2022Source
  • Documentvggf007_compressed.pdf · uploaded 30 Apr 2022Source
  • Documentvggf008 (1)_compressed.pdf · uploaded 30 Apr 2022Source
  • Documentvggf009_compressed.pdf · uploaded 30 Apr 2022Source
  • Documentvggf010_compressed.pdf · uploaded 30 Apr 2022Source
  • Documentvggf011_compressed.pdf · uploaded 30 Apr 2022Source
  • Documentvggf012_compressed.pdf · uploaded 30 Apr 2022Source
  • Documentn1vhyg035.pdf · uploaded 7 Feb 2023Source
  • Documentn1vhyg036.pdf · uploaded 7 Feb 2023Source
  • Documentn1vhyg037.pdf · uploaded 7 Feb 2023Source
  • Documentn1vhyg038.pdf · uploaded 7 Feb 2023Source
  • Documentn1vhyg039.pdf · uploaded 7 Feb 2023Source
  • Documentn1vhyg041.pdf · uploaded 7 Feb 2023Source
  • Documentn1vhyg042.pdf · uploaded 7 Feb 2023Source
  • Documentn1vhyg043.pdf · uploaded 7 Feb 2023Source
  • Documentn1vhyg044.pdf · uploaded 7 Feb 2023Source
  • Documentn1vhyg045.pdf · uploaded 7 Feb 2023Source
  • Documentn1vhyg046.pdf · uploaded 7 Feb 2023Source
  • DocumentLayout Apporval_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 1_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 2_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 3_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 4_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 5_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 6_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 7_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 8_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 9_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 10_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentBuilding Plan 11_Compressed.pdf · uploaded 11 Jul 2023Source
  • DocumentLayout Approval.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 1.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 2.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 3.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 4.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 5.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 6.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 7.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 8.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 9.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 10.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 11.pdf · uploaded 18 Feb 2025Source
  • DocumentBuilding Plan 12.pdf · uploaded 18 Feb 2025Source

Technical (Architect)

  • DocumentForm 1 Architect certificate Signed.PDF · uploaded 2 Dec 2024Source
  • DocumentForm 1 Architect Certificate Dec 2024.PDF · uploaded 24 Jan 2025Source
  • DocumentForm 1 Architects Certificate June 26 Forte.PDF · uploaded 18 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 Engineer Certificate.PDF · uploaded 3 Dec 2024Source
  • DocumentForm 2 Engineer Certificate Dec 2024.PDF · uploaded 24 Jan 2025Source
  • DocumentForm 2 Engineer Certificate June 26 Forte.PDF · uploaded 18 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Wakad, Mulshi taluka

Survey, CTS, gat or plot numbers

S No. 113/1/1

Boundaries

North
By Survey No 112
South
By Survey No 113-2
East
By remaining Part of S No 113-1-1
West
By Survey No 113-1-2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAmit Bhat—
EngineerMaheshkumar Kantilal Butala—
EngineerSanjay Taware—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology