Wing C · Infinia

Wakad · RERA P52100052465

IDBLD_04415011 floorsExtended 4 mo
11Sanctioned habitable floorsregistration certificate
30 Apr 2027Revised completionpromised 31 Dec 2026
0 of 44Units bookedMahaRERA project page

Floors

11 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100052465 · registered 8 Sep 2023
Promised completion
31 Dec 2026
Revised completion
30 Apr 2027
Sanctioned habitable floors
11
ProjectId
41,325
ProjectName
INFINIA
TotalUnitCount
44
ProjectBuildingId
66,001
BuildingNameNumber
WING C
FsiWithSanctionSqmts
14
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
44
ProjectRegistartionNo
P52100052465
ProjectBuildingWingsId
66,001
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
WING C
NoOfBuildingWingFloorProposed
14
NoOfBuildingWingFloorHabitable
11
NoOfBuildingWingFloorSanctioned
14

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK50.3 m² (542 sq.ft)10
2BHK65.3 m² (703 sq.ft)430
Total440