C Wing · Akasa
Wagholi · RERA P52100008158
IDBLD_02733612 floorsPromised date passed
12Sanctioned habitable floorsregistration certificate
31 Jan 2021Revised completionpromised 31 Jan 2021
2 of 74Units bookedMahaRERA project page
Floors
12 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100008158 · registered 18 Aug 2017
- Promised completion
- 31 Jan 2021
- Revised completion
- 31 Jan 2021
- Sanctioned habitable floors
- 12
- ProjectId
- 8,627
- ProjectName
- AKASA
- TotalUnitCount
- 0
- ProjectBuildingId
- 46,687
- BuildingNameNumber
- C WING
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100008158
- ProjectBuildingWingsId
- 46,687
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- C WING
- NoOfBuildingWingFloorProposed
- 12
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 12
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| RESIDENTIAL | 3,675 m² (39,557 sq.ft) | 74 | 2 |
| Total | 74 | 2 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology