Skip to content

Aarav Palm Springs

Certificate Signed

Wagholi, Pune 412207 |Promoter: Dikshit Rajan Agarwal

Residential / Group HousingRERAP52100051910
12 Jul 2023Registered with MahaRERA
31 Dec 2025Promised completion
2Buildings
10Units registered3 booked (30%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
Bungalow10 units in all
Address
Survey No 849 to 854 Plot No 23, Na, WagholiPIN 412207
Designated bank account
86
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.59159, 74.01022
Aarav Palm Springs is at latitude 18.59159, longitude 74.01022.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2025

The latest completion date on record passed 10 months ago.

Registered
12 Jul 2023
Promised
31 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005191012 Jul 202331 Dec 202531 Dec 2025Dikshit Rajan AgarwalProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A35
B35

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

3 of 10 units booked (30%), as the promoter reported to MahaRERA

Bungalow · 10 units
BuildingTypeCarpet areaUnitsBooked
ABungalow543.75 sq m · 5,853 sq ft51
BBungalow543.75 sq m · 5,853 sq ft52

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 92 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPANCARD.pdf · uploaded 26 Apr 2023Source

Legal

  • Legal Title reportLegal Title Report.pdf · uploaded 3 May 2023Source
  • Declaration Form BFORM B DIKSHIT.pdf · uploaded 3 May 2023Source
  • Declaration Form BFORM B VASWANI.pdf · uploaded 3 May 2023Source

Migrated

  • 1 PAN CardPANCARD.pdf · uploaded 26 Apr 2023Source
  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 3 May 2023Source
  • 1 a Details of encumbrances concerned to FinanceENCUMBRANCE LETTER -FINANCE.pdf · uploaded 3 May 2023Source
Show all 93 documentsShow fewer documents

Migrated

  • 2 a Details of encumbrances concerned to FinanceENCUMBRANCE LETTER -LEGAL.pdf · uploaded 3 May 2023Source
  • 1 b Details of encumbrances concerned to LegalENCUMBRANCE LETTER -FINANCE.pdf · uploaded 3 May 2023Source
  • 2 b Details of encumbrances concerned to LegalENCUMBRANCE LETTER -LEGAL.pdf · uploaded 3 May 2023Source
  • 1 Copy of Layout Approval (in case of layout)Layout Approval1.pdf · uploaded 3 May 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan (1).pdf · uploaded 3 May 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 3 May 2023Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 3 May 2023Source
  • 1 Declaration in FORM BFORM B DIKSHIT.pdf · uploaded 3 May 2023Source
  • 2 Declaration in FORM BFORM B VASWANI.pdf · uploaded 3 May 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST.pdf · uploaded 3 May 2023Source
  • 1 Proforma of Agreement for saleAgreement for sale.pdf · uploaded 3 May 2023Source
  • 1 Proforma of Allotment letterAarav-allotment letter.pdf · uploaded 3 May 2023Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION ALLOTMENT.pdf · uploaded 3 May 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION AGREEMENT.pdf · uploaded 3 May 2023Source
  • 3 a Details of encumbrances concerned to FinanceENCUMBRANCE LETTER -FINANCE 2.pdf · uploaded 18 May 2023Source
  • 3 b Details of encumbrances concerned to LegalENCUMBRANCE LETTER -FINANCE 2.pdf · uploaded 18 May 2023Source
  • 1 CERSAI detailsUNDERTAKINGS FOR CERSAI.pdf · uploaded 18 May 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3.pdf · uploaded 18 May 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Declaration new.pdf · uploaded 22 May 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Form-1.pdf · uploaded 28 Oct 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate form-2.pdf · uploaded 28 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_compressed.pdf · uploaded 28 Oct 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 27 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE.pdf · uploaded 27 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3.pdf · uploaded 27 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 AARAV PALM APRING MARCH 24.pdf · uploaded 26 Apr 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 AARAV PALM SPRING MARCH 24.pdf · uploaded 26 Apr 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Aarav Palmspring Form-3.pdf · uploaded 29 Apr 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 aarav plamspring.pdf · uploaded 19 Jul 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 aarav palmspring.pdf · uploaded 19 Jul 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 aarav palmspring.pdf · uploaded 19 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1 SEP24.pdf · uploaded 12 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM3 SEP24.pdf · uploaded 12 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM2 SEP24.pdf · uploaded 12 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form -1.pdf · uploaded 31 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3.pdf · uploaded 31 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form- 2.pdf · uploaded 31 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 10 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 10 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 10 May 2025Source
  • Form 1Form 1.pdf · uploaded 12 Aug 2025Source
  • Form 2Form 2.pdf · uploaded 12 Aug 2025Source
  • Form 3Form 3.pdf · uploaded 12 Aug 2025Source
  • Disclosure of Sold and Booked InventoryInventory Disclosure Sep 2023.pdf · uploaded 12 Aug 2025Source
  • Form 1Form 1.pdf · uploaded 12 Aug 2025Source
  • Form 2Form 2.pdf · uploaded 12 Aug 2025Source
  • Form 3FORM 3.pdf · uploaded 12 Aug 2025Source
  • Disclosure of Sold and Booked InventoryInventory Disclosure Dec 2023.pdf · uploaded 12 Aug 2025Source
  • Form 1FORM 1.pdf · uploaded 12 Aug 2025Source
  • Form 2FORM 2.pdf · uploaded 12 Aug 2025Source
  • Form 3Form 3.pdf · uploaded 12 Aug 2025Source
  • Disclosure of Sold and Booked InventoryInventory Disclosure March 2024.pdf · uploaded 12 Aug 2025Source
  • Form 1Form 1.pdf · uploaded 12 Aug 2025Source
  • Form 2Form 2.pdf · uploaded 12 Aug 2025Source
  • Form 3Form 3.pdf · uploaded 12 Aug 2025Source
  • Disclosure of Sold and Booked InventoryInventory Disclosure June 2024.pdf · uploaded 12 Aug 2025Source
  • Form 1FORM 1.pdf · uploaded 12 Aug 2025Source
  • Form 2FORM 2.pdf · uploaded 12 Aug 2025Source
  • Form 3FORM 3.pdf · uploaded 12 Aug 2025Source
  • Disclosure of Sold and Booked InventoryInventory Disclosure Sep 2024.pdf · uploaded 12 Aug 2025Source
  • Form 1Form 1.pdf · uploaded 12 Aug 2025Source
  • Form 2Form 2.pdf · uploaded 12 Aug 2025Source
  • Form 3Form 3.pdf · uploaded 12 Aug 2025Source
  • Disclosure of Sold and Booked InventoryInventory Disclosure Dec 2024.pdf · uploaded 12 Aug 2025Source
  • Form 1Form 1.pdf · uploaded 12 Aug 2025Source
  • Form 2Form 2.pdf · uploaded 12 Aug 2025Source
  • Form 3Form 3.pdf · uploaded 12 Aug 2025Source
  • Disclosure of Sold and Booked InventoryInventory Disclosure March 2025.pdf · uploaded 12 Aug 2025Source
  • Withdrawal Update Form 1Form-1 aarav plamspring.pdf · uploaded 3 Sep 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 3 Sep 2025Source
  • Withdrawal Update Form 3Form-3 aarav palmspring.pdf · uploaded 3 Sep 2025Source
  • Withdrawal Update Form 1FORM 1 SEP 2025.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 2FORM 2 SEP 2025.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 3FORM 3 SEP 2025.pdf · uploaded 11 Nov 2025Source
  • Occupational CertificateOC - PLOT NO 23- WAGHOLI -DIKSHIT AGARWAL.pdf · uploaded 11 Nov 2025Source

Technical

  • DocumentLayout Approval1.pdf · uploaded 3 May 2023Source
  • DocumentBuilding Plan (1).pdf · uploaded 3 May 2023Source

Technical (Architect)

  • DocumentFORM1 SEP24.pdf · uploaded 12 Nov 2024Source
  • DocumentForm -1.pdf · uploaded 31 Jan 2025Source
  • DocumentForm 1.pdf · uploaded 10 May 2025Source
  • DocumentFORM 1 SEP 2025.pdf · uploaded 11 Nov 2025Source

Technical (Engineer)

  • DocumentFORM2 SEP24.pdf · uploaded 12 Nov 2024Source
  • DocumentForm- 2.pdf · uploaded 31 Jan 2025Source
  • DocumentForm 2.pdf · uploaded 10 May 2025Source
  • DocumentFORM 2 SEP 2025.pdf · uploaded 11 Nov 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Wagholi, Haveli taluka

Survey, CTS, gat or plot numbers

Survey No 849 to 854 Plot No 23

Boundaries

North
By Plot No 14
South
By Garden
East
By Plot No 22
West
By 9 Mtrs wide Internal Society Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectWalhekar & Associates—
Chartered accountantK S Bendre—
EngineerVijay Rajput—
OtherJeevan M Wagaskar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology