Skip to content

Bliss Solitaire

Certificate Signed

Undri, Pune 411060 |Promoter: Venkatesh Bhoomi Constructions LLP

8 Sep 2020Registered with MahaRERA
30 May 2025Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Address
Survey No 5, Hissa No 2/4, Survey No 5, Hissa No 2/4, UndriPIN 411060
Designated bank account
76
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 May 2025

The latest completion date on record passed 1 year and 5 months ago.

Registered
8 Sep 2020
Promised
30 May 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000263228 Sep 202030 May 202530 May 2025Venkatesh Bhoomi Constructions LLPProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Bliss Solitaire, Phase I, Building A9—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

1 document held by Deedo, 64 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardVENKATESHBHOOMI PAN.pdf · uploaded 19 Aug 2020Source

Legal

  • Legal Title reportSearch And Title Report 35R.pdf · uploaded 19 Aug 2020Source
  • Declaration Form BFORM B.pdf · uploaded 19 Aug 2020Source

Migrated

  • 1 PAN CardVENKATESHBHOOMI PAN.pdf · uploaded 19 Aug 2020Source
  • 1 Copy of the legal title reportSearch And Title Report 35R.pdf · uploaded 19 Aug 2020Source
  • 1 Details of encumbrancesNO Encumbrance Certificate.pdf · uploaded 19 Aug 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE 35 R.pdf · uploaded 19 Aug 2020Source
Show all 65 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BFORM B.pdf · uploaded 19 Aug 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 19 Aug 2020Source
  • 1 Copy of Layout Approval (in case of layout)COPY OF LAYOUT APPROVAL.pdf · uploaded 2 Sep 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN APPROVAL 1.pdf · uploaded 2 Sep 2020Source
  • 2 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN APPROVAL 2.pdf · uploaded 2 Sep 2020Source
  • 3 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN APPROVAL 3.pdf · uploaded 2 Sep 2020Source
  • 4 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN APPROVAL 4.pdf · uploaded 2 Sep 2020Source
  • 5 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN APPROVAL 5.pdf · uploaded 2 Sep 2020Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 2 Sep 2020Source
  • 2 Proforma of Allotment letterApplication for Allotment .pdf · uploaded 2 Sep 2020Source
  • 3 Proforma of Allotment letterDraft of Agreement.pdf · uploaded 2 Sep 2020Source
  • 6 Building Plan Approval / NA Order for plotted development1_compressed.pdf · uploaded 31 Jul 2021Source
  • 7 Building Plan Approval / NA Order for plotted development1_6_compressed.pdf · uploaded 31 Jul 2021Source
  • 8 Building Plan Approval / NA Order for plotted development2_6_compressed.pdf · uploaded 31 Jul 2021Source
  • 9 Building Plan Approval / NA Order for plotted development3_6_compressed.pdf · uploaded 31 Jul 2021Source
  • 10 Building Plan Approval / NA Order for plotted development4_6_compressed.pdf · uploaded 31 Jul 2021Source
  • 11 Building Plan Approval / NA Order for plotted development5_6_compressed.pdf · uploaded 31 Jul 2021Source
  • 12 Building Plan Approval / NA Order for plotted development6_6_compressed.pdf · uploaded 31 Jul 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 15 Aug 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate Bliss Solitaire Bldg A.pdf · uploaded 15 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance Bliss Solitaire A bldg Q1 2022.pdf · uploaded 15 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF UNSOLD INVENTORY Q1.pdf · uploaded 15 Aug 2021Source
  • 2 Disclosure of sold/ booked inventoryFINAL DISCLOSURE OF SOLD OR UNSOLD INVENTORY Q1.pdf · uploaded 2 Sep 2021Source
  • 1 Declaration about Commencement CertificateA BUILDING DECLARATION ABOUT COMMENCEMENT CERTIFICATE BLISS SOLITAIRE.pdf · uploaded 27 Sep 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - Q1 2022.pdf · uploaded 7 Oct 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE Q2.pdf · uploaded 19 Nov 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE Q2.pdf · uploaded 19 Nov 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)QUALITY ASSURANCE CERTIFICATE Q2.pdf · uploaded 19 Nov 2021Source
  • 3 Disclosure of sold/ booked inventoryDISCLOSURE OF UNSOLD INVENTORY Q2.pdf · uploaded 19 Nov 2021Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - Q2 2022-compressed.pdf · uploaded 19 Nov 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFFICATE Q3.pdf · uploaded 19 Feb 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEERS CERTIFICATE.pdf · uploaded 19 Feb 2022Source
  • 4 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - UNSOLD INVENTORY TILLL DECEMBER 2021- NEW.pdf · uploaded 19 Feb 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 - VENKATESHBHOOMI-compressed.pdf · uploaded 19 Feb 2022Source
  • 5 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD - UNSOLD INVENTORY TILLL DECEMBER 2021- NEW.pdf · uploaded 6 Apr 2022Source
  • 1 CERSAI detailsUNDERTAKING FOR SECURITY INTEREST.pdf · uploaded 11 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 20-21.pdf · uploaded 18 Apr 2022Source
  • 6 Disclosure of sold/ booked inventoryINVENTORY DETAILS.pdf · uploaded 25 Apr 2022Source
  • 2 a Details of encumbrances concerned to FinanceNO Encumbrance Certificate.pdf · uploaded 2 Nov 2022Source
  • 1 b Details of encumbrances concerned to LegalNO Encumbrance Certificate.pdf · uploaded 2 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 FY 21-22.pdf · uploaded 2 Nov 2022Source
  • 1 Proforma of Agreement for saleDraft of Agreement.pdf · uploaded 28 Dec 2024Source

Technical

  • DocumentCOPY OF LAYOUT APPROVAL.pdf · uploaded 2 Sep 2020Source
  • DocumentBUILDING PLAN APPROVAL 1.pdf · uploaded 2 Sep 2020Source
  • DocumentBUILDING PLAN APPROVAL 2.pdf · uploaded 2 Sep 2020Source
  • DocumentBUILDING PLAN APPROVAL 3.pdf · uploaded 2 Sep 2020Source
  • DocumentBUILDING PLAN APPROVAL 4.pdf · uploaded 2 Sep 2020Source
  • DocumentBUILDING PLAN APPROVAL 5.pdf · uploaded 2 Sep 2020Source
  • Document1_compressed.pdf · uploaded 31 Jul 2021Source
  • Document1_6_compressed.pdf · uploaded 31 Jul 2021Source
  • Document2_6_compressed.pdf · uploaded 31 Jul 2021Source
  • Document3_6_compressed.pdf · uploaded 31 Jul 2021Source
  • Document4_6_compressed.pdf · uploaded 31 Jul 2021Source
  • Document5_6_compressed.pdf · uploaded 31 Jul 2021Source
  • Document6_6_compressed.pdf · uploaded 31 Jul 2021Source

Technical (Architect)

  • DocumentARCHITECT CERTIFFICATE Q3.pdf · uploaded 19 Feb 2022Source

Technical (Engineer)

  • DocumentFORM 2 ENGINEERS CERTIFICATE.pdf · uploaded 19 Feb 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Undri, Haveli taluka

Survey, CTS, gat or plot numbers

HISSA NO 2/4SURVEY NO 5

Boundaries

North
Shri Sonawanes Land
South
Road And Primero Project Land
East
Shri Ramdas Takles Land
West
Undri-Hadapsar Road And Ukt Constructions Land

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectCubix Architects Associates—
Chartered accountantM/s. PARESH K SHAH & CO—
EngineerMr. Sandeep Dhumal—
OtherAdvait Infra—
OtherChitlange Associates—
OtherG.a.bhilare Consultants Pvt Ltd—
OtherSandeep Hardikar & Associates—
OtherSiddhivinayak Mep Consultants—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology