Skip to content

ML Tower

Certificate Signed

Ravet, Pune 421101 |Promoter: BML Builders

27 Oct 2023Registered with MahaRERA
13 Jan 2027Promised completion
13 May 2027Revised completionPushed back 4 months
1Building
38Units registered14 booked (37%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK, 3BHK, Clinic, Office space, Shop38 units in all
Address
Survey No. 97/1A/1A/15 Ravet Pune 412101, S. B. Patil Road, PunePIN 421101
Designated bank account
85
Developed in phases
No

Registered transactions

9 registered documents matched to this project. Consideration is the value declared in the document; the Index II opens inside Deedo.

Registered transactions in this project
RegisteredUnitTypeConsideration₹ / sq.ftDocument
16 Sep 2026Primary sale—≈ ₹9,173
1 Aug 2026
Bldg या
Primary sale—≈ ₹8,577
12 May 2026
Bldg या
Primary sale—≈ ₹8,230
11 May 2026Primary sale—≈ ₹9,015
4 Apr 2026Primary sale—≈ ₹8,232
26 Mar 2026Primary sale—≈ ₹7,967
22 Mar 2026Primary sale—≈ ₹8,539
16 Mar 2026Primary sale—≈ ₹8,788
3 Feb 2026Primary sale—≈ ₹8,410

ML Tower in numbers

Registered deals, summarised

Deedo has 9 registered documents at ML Tower, from Feb 2026 to Sep 2026: 9 sales. The median registered sale works out to about ₹8,400 per sq ft, at a median of ₹44 L a deal; 0% of sales were resales.

What is the price per sq ft at ML Tower?
The median registered sale works out to about ₹8,400 per sq ft, at a median of ₹44 L a deal; 0% of sales were resales.
How many properties have been sold at ML Tower?
9 sales are registered at ML Tower.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at ML Tower by Deedo, last updated with deals registered in Sep 2026.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
27 Oct 2023
Promised
13 Jan 2027
Revised
13 May 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005332727 Oct 202313 Jan 202713 May 2027BML BuildersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A Building1038

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

14 of 38 units booked (37%), as the promoter reported to MahaRERA

2BHK · 4 units3BHK · 5 unitsClinic · 4 unitsOffice space · 16 unitsShop · 9 units
TypeCarpet areaUnitsBooked
2BHK73.03 sq m · 786 sq ft22
2BHK79.45 sq m · 855 sq ft20
3BHK34.05 sq m · 367 sq ft10
3BHK99.98 sq m · 1,076 sq ft20
3BHK102.47 sq m · 1,103 sq ft21
Clinic83.43 sq m · 898 sq ft10
Clinic83.45 sq m · 898 sq ft10
Clinic139.32 sq m · 1,500 sq ft10
Show all 32 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Clinic145.12 sq m · 1,562 sq ft10
Office space24.37 sq m · 262 sq ft22
Office space30.92 sq m · 333 sq ft11
Office space33 sq m · 355 sq ft11
Office space33.55 sq m · 361 sq ft10
Office space35.63 sq m · 384 sq ft10
Office space36.47 sq m · 393 sq ft10
Office space37.95 sq m · 408 sq ft11
Office space40.63 sq m · 437 sq ft10
Office space43.19 sq m · 465 sq ft11
Office space45.48 sq m · 490 sq ft10
Office space45.48 sq m · 490 sq ft10
Office space52.72 sq m · 567 sq ft10
Office space55.06 sq m · 593 sq ft10
Office space85.03 sq m · 915 sq ft20
Shop21 sq m · 226 sq ft11
Shop31.1 sq m · 335 sq ft11
Shop32.33 sq m · 348 sq ft10
Shop32.77 sq m · 353 sq ft10
Shop35.74 sq m · 385 sq ft11
Shop36.35 sq m · 391 sq ft11
Shop36.5 sq m · 393 sq ft10
Shop51.93 sq m · 559 sq ft10
Shop54.55 sq m · 587 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 129 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardBML BUILDERS Pancard .pdf · uploaded 25 Aug 2023Source

Legal

  • Declaration Form BBML Affidavit.pdf · uploaded 25 Aug 2023Source
  • Legal Title reportTitle Report_1 (3 files merged).pdf · uploaded 20 Oct 2023Source

Migrated

  • 1 PAN CardBML BUILDERS Pancard .pdf · uploaded 25 Aug 2023Source
  • 1 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Legal - ML Tower.pdf · uploaded 25 Aug 2023Source
  • 1 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Legal - ML Tower.pdf · uploaded 25 Aug 2023Source
Show all 131 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Plan 01.pdf · uploaded 25 Aug 2023Source
  • 2 Copy of Layout Approval (in case of layout)Plan 02.pdf · uploaded 25 Aug 2023Source
  • 3 Copy of Layout Approval (in case of layout)Plan 03.pdf · uploaded 25 Aug 2023Source
  • 4 Copy of Layout Approval (in case of layout)Plan 04.pdf · uploaded 25 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 01.pdf · uploaded 25 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 02.pdf · uploaded 25 Aug 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan 03.pdf · uploaded 25 Aug 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentPlan 04.pdf · uploaded 25 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 25 Aug 2023Source
  • 1 Declaration about Commencement CertificateForm D - ML Tower.pdf · uploaded 25 Aug 2023Source
  • 1 Declaration in FORM BBML Affidavit.pdf · uploaded 25 Aug 2023Source
  • 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 25 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations - ML Tower.pdf · uploaded 25 Aug 2023Source
  • 1 Proforma of Allotment letterAllotment Letter - ML Tower.pdf · uploaded 25 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account Declaration - ML Tower.pdf · uploaded 25 Aug 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation of Allotment Letter - ML Tower.pdf · uploaded 25 Aug 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation for AFS - ML Tower.pdf · uploaded 25 Aug 2023Source
  • 2 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Finance - ML Tower.pdf · uploaded 9 Oct 2023Source
  • 3 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Legal - ML Tower.pdf · uploaded 9 Oct 2023Source
  • 2 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Finance - ML Tower.pdf · uploaded 9 Oct 2023Source
  • 3 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Legal - ML Tower.pdf · uploaded 9 Oct 2023Source
  • 1 Proforma of Agreement for saleAgreement for sale- BML Builders (Shailesh sir).pdf · uploaded 9 Oct 2023Source
  • 1 Other – TechnicalCC confirmation.pdf · uploaded 9 Oct 2023Source
  • 1 Copy of the legal title reportTitle Report_1 (3 files merged).pdf · uploaded 20 Oct 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA-BML Buildernew (1).pdf · uploaded 20 Oct 2023Source
  • 2 Proforma of Agreement for saleRERA AGREEMENT kiran sir 03102023.pdf · uploaded 15 Dec 2023Source
  • 5 Building Plan Approval / NA Order for plotted developmentBuilding Plan_Revised Sheet-1.pdf · uploaded 24 Mar 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentBuilding Plan_Revised Sheet-2.pdf · uploaded 24 Mar 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentBuilding Plan_Revised Sheet-3.pdf · uploaded 24 Mar 2024Source
  • 8 Building Plan Approval / NA Order for plotted developmentBuilding Plan_Revised Sheet-4.pdf · uploaded 24 Mar 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised_CC.pdf · uploaded 24 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)29-4-24 Architect Certificate_compressed.pdf · uploaded 11 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)12-9-24 Architect Certificate .pdf · uploaded 11 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (3).pdf · uploaded 11 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)16-5-24 CA Certificate-compressed.pdf · uploaded 11 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)15-5-24 Engineer Certificate.pdf · uploaded 11 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)12-9-24 Engineer Certificate .pdf · uploaded 11 Oct 2024Source
  • 2 Commencement Certificates / NA Order for plotted development9-9-24 बांधकाम परवानगी 4th-compressed.pdf · uploaded 11 Oct 2024Source
  • 2 Other – Technical15-4-23 Plinth checking Certificate.pdf · uploaded 11 Oct 2024Source
  • 3 Other – Technicalwork in progress Certificate .pdf · uploaded 11 Oct 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samenew Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same.pdf · uploaded 21 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)9-9-24 बांधकाम परवानगी 4th (1)-pages-compressed.pdf · uploaded 18 Nov 2024Source
  • 7 Copy of Layout Approval (in case of layout)9-9-24 बांधकाम परवानगी 4th (1)-pages-compressed.pdf · uploaded 18 Nov 2024Source
  • 1 Proforma of Agreement for salerera bml.pdf · uploaded 16 Dec 2024Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A ordern n0 34 2022.pdf · uploaded 21 Dec 2024Source
  • 2 Proforma of Agreement for saleRERA AGREEMENT kiran.pdf · uploaded 30 Dec 2024Source
  • 2 Copy of Layout Approval (in case of layout)HPSC0725_11zon.pdf · uploaded 21 Jan 2025Source
  • 3 Copy of Layout Approval (in case of layout)HPSC0726_11zon.pdf · uploaded 21 Jan 2025Source
  • 4 Copy of Layout Approval (in case of layout)HPSC0727_11zon.pdf · uploaded 21 Jan 2025Source
  • 5 Copy of Layout Approval (in case of layout)HPSC0728_11zon.pdf · uploaded 21 Jan 2025Source
  • 6 Copy of Layout Approval (in case of layout)HPSC0729_11zon.pdf · uploaded 21 Jan 2025Source
  • 1 Copy of Layout Approval (in case of layout)HPSC0724_11zon.pdf · uploaded 21 Jan 2025Source
  • 1 Commencement Certificates / NA Order for plotted development20250120095555_11zon.pdf · uploaded 21 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)4th Architect Certificate 10-02-2025-output.pdf · uploaded 13 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)4th CA Certificate 07-02-25_11zon.pdf · uploaded 13 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 13 Feb 2025Source
  • 1 Other – Technical4th Work Progress Certificate 10-02-2025.pdf · uploaded 13 Feb 2025Source
  • 1 Proforma of Agreement for saleFinal Draft for RERA BML BUILDERS 17-03-2025.pdf · uploaded 17 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)1st Revised Sanction Plan_11zon.pdf · uploaded 31 Mar 2025Source
  • 1 Proforma of Agreement for saleFinal Draft - Narayani 31-03-2025 Submitted to RERA_compressed.pdf · uploaded 31 Mar 2025Source
  • Form 1June form 1.pdf · uploaded 10 Jul 2026Source
  • Form 1June form 1.pdf · uploaded 10 Jul 2026Source
  • Form 1Sept form 1.pdf · uploaded 10 Jul 2026Source
  • Form 1Dec form 1.pdf · uploaded 10 Jul 2026Source
  • Form 1march form 1.pdf · uploaded 10 Jul 2026Source
  • Form 2June form 2.pdf · uploaded 10 Jul 2026Source
  • Form 2June form 2.pdf · uploaded 10 Jul 2026Source
  • Form 2Sept form 2.pdf · uploaded 10 Jul 2026Source
  • Form 2Dec form 2.pdf · uploaded 10 Jul 2026Source
  • Form 2March form 2.pdf · uploaded 10 Jul 2026Source
  • Form 3June form 3.pdf · uploaded 10 Jul 2026Source
  • Form 3June form 3.pdf · uploaded 10 Jul 2026Source
  • Form 3Sept form 3.pdf · uploaded 10 Jul 2026Source
  • Form 3Dec form 3.pdf · uploaded 10 Jul 2026Source
  • Form 3march form 3.pdf · uploaded 10 Jul 2026Source
  • Disclosure of Sold and Booked InventoryJune sold booked inventory Data.pdf · uploaded 10 Jul 2026Source
  • Disclosure of Sold and Booked InventoryJune form 3.pdf · uploaded 10 Jul 2026Source
  • Disclosure of Sold and Booked InventorySept Sold Booked Inventory data.pdf · uploaded 10 Jul 2026Source
  • Disclosure of Sold and Booked InventoryDec sold booked inventory Data.pdf · uploaded 10 Jul 2026Source
  • Disclosure of Sold and Booked InventoryMarch sold booked Inventory Data.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 12 Jul 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 12 Jul 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 12 Jul 2026Source
  • Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 12 Jul 2026Source

Technical

  • DocumentPlan 01.pdf · uploaded 25 Aug 2023Source
  • DocumentPlan 02.pdf · uploaded 25 Aug 2023Source
  • DocumentPlan 03.pdf · uploaded 25 Aug 2023Source
  • DocumentPlan 04.pdf · uploaded 25 Aug 2023Source
  • DocumentPlan 01.pdf · uploaded 25 Aug 2023Source
  • DocumentPlan 02.pdf · uploaded 25 Aug 2023Source
  • DocumentPlan 03.pdf · uploaded 25 Aug 2023Source
  • DocumentPlan 04.pdf · uploaded 25 Aug 2023Source
  • Other – TechnicalCC confirmation.pdf · uploaded 9 Oct 2023Source
  • DocumentBuilding Plan_Revised Sheet-1.pdf · uploaded 24 Mar 2024Source
  • DocumentBuilding Plan_Revised Sheet-2.pdf · uploaded 24 Mar 2024Source
  • DocumentBuilding Plan_Revised Sheet-3.pdf · uploaded 24 Mar 2024Source
  • DocumentBuilding Plan_Revised Sheet-4.pdf · uploaded 24 Mar 2024Source
  • Other – Technical15-4-23 Plinth checking Certificate.pdf · uploaded 11 Oct 2024Source
  • Other – Technicalwork in progress Certificate .pdf · uploaded 11 Oct 2024Source
  • Document9-9-24 बांधकाम परवानगी 4th (1)-pages-compressed.pdf · uploaded 18 Nov 2024Source
  • Document9-9-24 बांधकाम परवानगी 4th (1)-pages-compressed.pdf · uploaded 18 Nov 2024Source
  • DocumentHPSC0724_11zon.pdf · uploaded 21 Jan 2025Source
  • DocumentHPSC0725_11zon.pdf · uploaded 21 Jan 2025Source
  • DocumentHPSC0726_11zon.pdf · uploaded 21 Jan 2025Source
  • DocumentHPSC0727_11zon.pdf · uploaded 21 Jan 2025Source
  • DocumentHPSC0728_11zon.pdf · uploaded 21 Jan 2025Source
  • DocumentHPSC0729_11zon.pdf · uploaded 21 Jan 2025Source
  • Other – Technical4th Work Progress Certificate 10-02-2025.pdf · uploaded 13 Feb 2025Source
  • Document1st Revised Sanction Plan_11zon.pdf · uploaded 31 Mar 2025Source
  • DocumentLayout.pdf · uploaded 23 Jul 2026Source
  • Documentsanction plan 2.pdf · uploaded 23 Jul 2026Source
  • Documentsanction plan 3.pdf · uploaded 23 Jul 2026Source
  • Documentsanction plan 4.pdf · uploaded 23 Jul 2026Source
  • Documentsanction plan 5.pdf · uploaded 23 Jul 2026Source
  • DocumentSanction plan 6.pdf · uploaded 23 Jul 2026Source

Technical (Architect)

  • Document29-4-24 Architect Certificate_compressed.pdf · uploaded 11 Oct 2024Source
  • Document12-9-24 Architect Certificate .pdf · uploaded 11 Oct 2024Source
  • Document4th Architect Certificate 10-02-2025-output.pdf · uploaded 13 Feb 2025Source
  • DocumentForm 1.pdf · uploaded 12 Jul 2026Source

Technical (Engineer)

  • Document15-5-24 Engineer Certificate.pdf · uploaded 11 Oct 2024Source
  • Document12-9-24 Engineer Certificate .pdf · uploaded 11 Oct 2024Source
  • Documentform 2.pdf · uploaded 13 Feb 2025Source
  • Documentform 2.pdf · uploaded 12 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Ravet, Haveli taluka

Survey, CTS, gat or plot numbers

Survey No. 97/1A/1A/15 Ravet Pune

Boundaries

North
Mr Dheerjlal Hiralal Bhojni Land
South
Out of Land of Survey No 97
East
Out of Land of Survey No 97
West
80 Meter wide DP Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectIntegrity Arch and Associates—
ArchitectShamal Kavatkar—
Chartered accountantCA Bhushan S Chhajed—
Chartered accountantEshan Porwal—
Chartered accountantSiddhi Warik—
EngineerGovind Bhanudas Nimbalkar—
EngineerPawan Khengare—
OtherGovind Bhanudas Nimbalkar—
OtherSukhakarta Construction—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology