C · Twin Arcs
Punawale · RERA P52100001145
IDBLD_02938614 floorsPromised date passed
14Sanctioned habitable floorsregistration certificate
31 Dec 2019Revised completionpromised 31 Dec 2019
122 of 122Units bookedMahaRERA project page
Floors
14 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100001145 · registered 26 Jul 2017
- Promised completion
- 31 Dec 2019
- Revised completion
- 31 Dec 2019
- Sanctioned habitable floors
- 14
- ProjectId
- 3,326
- ProjectName
- Twin Arcs
- TotalUnitCount
- 0
- ProjectBuildingId
- 41,807
- BuildingNameNumber
- C
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100001145
- ProjectBuildingWingsId
- 41,807
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- C
- NoOfBuildingWingFloorProposed
- 14
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 14
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 34.1 m² (367 sq.ft) | 22 | 22 |
| 2BHK | 42.7 m² (460 sq.ft) | 5 | 5 |
| 2BHK | 42.8 m² (461 sq.ft) | 5 | 5 |
| 2BHK | 42.9 m² (462 sq.ft) | 14 | 14 |
| 2BHK | 48 m² (516 sq.ft) | 6 | 6 |
| 2BHK | 48.1 m² (518 sq.ft) | 6 | 6 |
| 2BHK | 48.4 m² (521 sq.ft) | 6 | 6 |
| 2BHK | 48.6 m² (523 sq.ft) | 7 | 7 |
| 2BHK | 49.6 m² (534 sq.ft) | 6 | 6 |
| 2BHK | 50.4 m² (543 sq.ft) | 7 | 7 |
Show all 16 unit typesShow fewer unit types
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 52 m² (560 sq.ft) | 6 | 6 |
| 2BHK | 52.9 m² (569 sq.ft) | 6 | 6 |
| 2BHK | 60.5 m² (651 sq.ft) | 6 | 6 |
| 3BHK | 60.4 m² (650 sq.ft) | 7 | 7 |
| 3BHK | 61.3 m² (660 sq.ft) | 6 | 6 |
| 3BHK | 64.4 m² (693 sq.ft) | 7 | 7 |
| Total | 122 | 122 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology