Sentosa Pride
Completion date passedPunawale, Pune 411033 |Promoter: Shree Krishna Associates
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Jun 2018
P52100001763The latest completion date on record passed 8 years and 4 months ago.
- Registered
- 29 Jul 2017
- Promised
- 30 Jun 2018
Completion pushed back 6 months
P52100018471The latest completion date on record passed 2 years and 4 months ago.
- Registered
- 2 Nov 2018
- Promised
- 30 Dec 2023
- Revised
- 30 Jun 2024
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100001763 | 29 Jul 2017 | 30 Jun 2018 | — | Shree Krishna Associates | Project page |
| P52100018471 | 2 Nov 2018 | 30 Dec 2023 | 30 Jun 2024 | Shree Krishna Associates | Project page |
Documents
3 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.