C · Rose Aster

Punawale · RERA P52100018281

IDBLD_04195713 floorsPromised date passed
13Sanctioned habitable floorsregistration certificate
30 Dec 2023Revised completionpromised 30 Dec 2023
16 of 77Units bookedMahaRERA project page

Floors

13 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100018281 · registered 22 Oct 2018
Promised completion
30 Dec 2023
Revised completion
30 Dec 2023
Sanctioned habitable floors
13
ProjectId
20,834
ProjectName
ROSE ASTER
TotalUnitCount
0
ProjectBuildingId
53,212
BuildingNameNumber
C
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52100018281
ProjectBuildingWingsId
53,212
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
C
NoOfBuildingWingFloorProposed
13
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
13

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK34.3 m² (369 sq.ft)127
2BHK42.9 m² (461 sq.ft)116
2BHK43.1 m² (464 sq.ft)100
2BHK43.2 m² (465 sq.ft)220
2BHK43.4 m² (467 sq.ft)122
2BHK43.4 m² (467 sq.ft)101
Total7716