I · Puneville
Punawale · RERA P52100000440
IDBLD_02527524 floorsExtended 12 mo
24Sanctioned habitable floorsregistration certificate
29 Dec 2023Revised completionpromised 30 Dec 2022
129 of 129Units bookedMahaRERA project page
Floors
24 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100000440 · registered 17 Jul 2017
- Promised completion
- 30 Dec 2022
- Revised completion
- 29 Dec 2023
- Sanctioned habitable floors
- 24
- ProjectId
- 3,840
- ProjectName
- Puneville Phase II Cluster A
- TotalUnitCount
- 0
- ProjectBuildingId
- 41,855
- BuildingNameNumber
- I
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100000440
- ProjectBuildingWingsId
- 41,855
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- I
- NoOfBuildingWingFloorProposed
- 24
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 24
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2.5 BHK | 76.9 m² (828 sq.ft) | 43 | 43 |
| 2.5 BHK | 77 m² (829 sq.ft) | 44 | 44 |
| 2BHK | 60.2 m² (648 sq.ft) | 21 | 21 |
| 2BHK | 60.4 m² (650 sq.ft) | 1 | 1 |
| 2BHK | 60.4 m² (650 sq.ft) | 20 | 20 |
| Total | 129 | 129 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology