A Wing · Mirai Phase-I
Punawale · RERA P52100050306
IDBLD_06237316 floorsNot yet due
16Sanctioned habitable floorsregistration certificate
31 Dec 2026Revised completionpromised 31 Dec 2026
4 of 126Units bookedMahaRERA project page
Floors
16 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100050306 · registered 1 Apr 2023
- Promised completion
- 31 Dec 2026
- Revised completion
- 31 Dec 2026
- Sanctioned habitable floors
- 16
- ProjectId
- 39,319
- ProjectName
- MIRAI PHASE-I
- TotalUnitCount
- 126
- ProjectBuildingId
- 64,883
- BuildingNameNumber
- A Wing
- FsiWithSanctionSqmts
- 18
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 126
- ProjectRegistartionNo
- P52100050306
- ProjectBuildingWingsId
- 64,883
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- A Wing
- NoOfBuildingWingFloorProposed
- 18
- NoOfBuildingWingFloorHabitable
- 16
- NoOfBuildingWingFloorSanctioned
- 18
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 59.3 m² (638 sq.ft) | 94 | 1 |
| 3BHK | 83.7 m² (901 sq.ft) | 32 | 3 |
| Total | 126 | 4 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology