Block C · Dominion Park

Punawale · RERA P52100024698

IDBLD_0394465 floorsPromised date passed
5Sanctioned habitable floorsregistration certificate
30 Dec 2023Revised completionpromised 30 Dec 2023
0 of 5Units bookedMahaRERA project page

Floors

5 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100024698 · registered 28 Feb 2020
Promised completion
30 Dec 2023
Revised completion
30 Dec 2023
Sanctioned habitable floors
5
ProjectId
27,274
ProjectName
Dominion Park
TotalUnitCount
0
ProjectBuildingId
56,746
BuildingNameNumber
Block C
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52100024698
ProjectBuildingWingsId
56,746
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Block C
NoOfBuildingWingFloorProposed
5
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
5

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
SHOP N0.0031,073.1 m² (11,550 sq.ft)10
SHOP NO.0011,524.3 m² (16,407 sq.ft)10
SHOP NO.0021,073.1 m² (11,550 sq.ft)10
SHOP NO.0041,073.1 m² (11,550 sq.ft)10
SHOP NO.0051,073.1 m² (11,550 sq.ft)10
Total50
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology