Atulya Nirman A B Wing

Certificate Signed

Punawale, Pune 411033 |Promoter: D S Associates

Residential / Group HousingRERAP52100017797
17 Sep 2018Registered with MahaRERA
30 Dec 2022Promised completion
30 Jun 2024Revised completionPushed back 1 year and 6 months
2Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
2
Address
S No 18/3 18/4, Opp DSK Kunjban, Near Kate VastiPIN 411033
Designated bank account
82
Developed in phases
Yes

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 6 months

The latest completion date on record passed 2 years and 4 months ago.

Registered
17 Sep 2018
Promised
30 Dec 2022
Revised
30 Jun 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001779717 Sep 201830 Dec 202230 Jun 2024D S AssociatesProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A5—
B6—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

2 documents held by Deedo, 154 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN Cardds associates.pdf · uploaded 2 Feb 2018Source

Legal

  • Legal Title reportTITLE REPORT.pdf · uploaded 2 Feb 2018Source
  • Declaration Form BForm B.pdf · uploaded 5 Sep 2018Source
  • Declaration Form BForm B (Co-Promoters).pdf · uploaded 5 Sep 2018Source

Migrated

  • 1 PAN Cardds associates.pdf · uploaded 2 Feb 2018Source
  • 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 2 Feb 2018Source
Show all 156 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentimg-107002133.pdf · uploaded 2 Feb 2018Source
  • 1 Details of encumbrancesIndex II.pdf · uploaded 30 Aug 2018Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 30 Aug 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 30 Aug 2018Source
  • 1 Copy of Layout Approval (in case of layout)LAY OUT.pdf · uploaded 5 Sep 2018Source
  • 1 Building Plan Approval (IOD)Plan 0002.pdf · uploaded 5 Sep 2018Source
  • 2 Building Plan Approval (IOD)Plan 0003.pdf · uploaded 5 Sep 2018Source
  • 3 Building Plan Approval (IOD)Plan 0004.pdf · uploaded 5 Sep 2018Source
  • 4 Building Plan Approval (IOD)Plan 0005.pdf · uploaded 5 Sep 2018Source
  • 5 Building Plan Approval (IOD)Plan 0006.pdf · uploaded 5 Sep 2018Source
  • 6 Building Plan Approval (IOD)Plan 0007.pdf · uploaded 5 Sep 2018Source
  • 7 Building Plan Approval (IOD)Plan 0008.pdf · uploaded 5 Sep 2018Source
  • 8 Building Plan Approval (IOD)Plan 0009.pdf · uploaded 5 Sep 2018Source
  • 9 Building Plan Approval (IOD)Plan 0010.pdf · uploaded 5 Sep 2018Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 5 Sep 2018Source
  • 2 Declaration in FORM BForm B (Co-Promoters).pdf · uploaded 5 Sep 2018Source
  • 1 Proforma of Allotment letterDraft Agreement.pdf · uploaded 5 Sep 2018Source
  • 1 Certificates of CA (Form 3)Form III.pdf · uploaded 6 Sep 2018Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM II.pdf · uploaded 9 May 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form1 latest.pdf · uploaded 16 Feb 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2.pdf · uploaded 16 Feb 2023Source
  • 2 Certificates of CA (Form 3)Form 3 latest.pdf · uploaded 16 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 2018-19.pdf · uploaded 22 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 2019-20.pdf · uploaded 22 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 2020-21.pdf · uploaded 22 Feb 2023Source
  • 3 Certificates of CA (Form 3)Form 3.pdf · uploaded 8 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 2021-22.pdf · uploaded 8 Apr 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 12 Apr 2023Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form2(signed).pdf · uploaded 13 Apr 2023Source
  • 2 Proforma of Allotment letterAtulya Nirman AB WIng agreemnt draft.pdf · uploaded 13 Apr 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 april- june 2023.pdf · uploaded 11 Jul 2023Source
  • 4 Certificates of CA (Form 3)form 3 aprl - June 2023.pdf · uploaded 15 Jul 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 06jul2023.pdf · uploaded 10 Oct 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1_01_oct_23.pdf · uploaded 11 Oct 2023Source
  • 5 Certificates of CA (Form 3)form 3.pdf · uploaded 28 Oct 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentdeclaration abourt comemncement certificate.pdf · uploaded 13 Dec 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 dec 2023.pdf · uploaded 27 Jan 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1- 26 03 19.pdf · uploaded 27 Jan 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)form1-26 03 20.pdf · uploaded 27 Jan 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1-26 03 21.pdf · uploaded 27 Jan 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 -26 6 21.pdf · uploaded 27 Jan 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 -26 9 21.pdf · uploaded 27 Jan 2024Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 -26 12 21.pdf · uploaded 27 Jan 2024Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 26 12 22.pdf · uploaded 27 Jan 2024Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 26 3 22.pdf · uploaded 27 Jan 2024Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 26 6 22.pdf · uploaded 27 Jan 2024Source
  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 26 9 22.pdf · uploaded 27 Jan 2024Source
  • 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 26 12 22.pdf · uploaded 27 Jan 2024Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atulya Nirman Mar2019.pdf · uploaded 27 Jan 2024Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atultya NirmanMar2020.pdf · uploaded 27 Jan 2024Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atulya NIrman June2021.pdf · uploaded 27 Jan 2024Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atulya NIrman Sept2021.pdf · uploaded 27 Jan 2024Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atulya NIrman Dec2021.pdf · uploaded 27 Jan 2024Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atulya Nirman Mar2022.pdf · uploaded 27 Jan 2024Source
  • 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atulya Nirman June2022.pdf · uploaded 27 Jan 2024Source
  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atulya NirmanSept2022.pdf · uploaded 27 Jan 2024Source
  • 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atulya NirmanDec2022.pdf · uploaded 27 Jan 2024Source
  • 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atulya NirmanDec2023.pdf · uploaded 27 Jan 2024Source
  • 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 1 26 3 22.pdf · uploaded 27 Jan 2024Source
  • 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 1 26 6 22.pdf · uploaded 27 Jan 2024Source
  • 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 1 26 9 22.pdf · uploaded 27 Jan 2024Source
  • 18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 1 26 12 22.pdf · uploaded 27 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)form 2 A - March 2023 (1).pdf · uploaded 27 Jan 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)form 2 A - March 2023 (2).pdf · uploaded 27 Jan 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)form 2 A - March 2023 (3).pdf · uploaded 27 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)form 2 A - March 2023 (4).pdf · uploaded 27 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)form 2 A - March 2023 (5).pdf · uploaded 27 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2 A - March 2023.pdf · uploaded 27 Jan 2024Source
  • 6 Certificates of CA (Form 3)q1 2017-18-signed.pdf · uploaded 27 Jan 2024Source
  • 7 Certificates of CA (Form 3)q1 2018-19-signed.pdf · uploaded 27 Jan 2024Source
  • 8 Certificates of CA (Form 3)q1 2019-20-signed.pdf · uploaded 27 Jan 2024Source
  • 9 Certificates of CA (Form 3)q 1 2020-21-signed.pdf · uploaded 27 Jan 2024Source
  • 10 Certificates of CA (Form 3)q1 2021-22-signed.pdf · uploaded 27 Jan 2024Source
  • 11 Certificates of CA (Form 3)q1 2022-23-signed.pdf · uploaded 27 Jan 2024Source
  • 12 Certificates of CA (Form 3)q2 2017-18-signed.pdf · uploaded 27 Jan 2024Source
  • 13 Certificates of CA (Form 3)q3 2017-18-signed.pdf · uploaded 27 Jan 2024Source
  • 14 Certificates of CA (Form 3)q4 2017-18-signed.pdf · uploaded 27 Jan 2024Source
  • 15 Certificates of CA (Form 3)q1 2018-19-signed.pdf · uploaded 27 Jan 2024Source
  • 16 Certificates of CA (Form 3)q2 2018-19-signed.pdf · uploaded 27 Jan 2024Source
  • 17 Certificates of CA (Form 3)q3 2018-19-signed.pdf · uploaded 27 Jan 2024Source
  • 18 Certificates of CA (Form 3)q4 2018-19-signed.pdf · uploaded 27 Jan 2024Source
  • 19 Certificates of CA (Form 3)q1 2019-20-signed.pdf · uploaded 27 Jan 2024Source
  • 20 Certificates of CA (Form 3)q 2 2019-20-signed.pdf · uploaded 27 Jan 2024Source
  • 21 Certificates of CA (Form 3)q3 2019-20-signed.pdf · uploaded 27 Jan 2024Source
  • 22 Certificates of CA (Form 3)q4 2019-20-signed.pdf · uploaded 27 Jan 2024Source
  • 23 Certificates of CA (Form 3)q 1 2020-21-signed.pdf · uploaded 27 Jan 2024Source
  • 24 Certificates of CA (Form 3)q2 2020-21-signed.pdf · uploaded 27 Jan 2024Source
  • 25 Certificates of CA (Form 3)q 3 2020-21-signed.pdf · uploaded 27 Jan 2024Source
  • 26 Certificates of CA (Form 3)q4 2020-21-signed.pdf · uploaded 27 Jan 2024Source
  • 27 Certificates of CA (Form 3)q1 2021-22-signed.pdf · uploaded 27 Jan 2024Source
  • 28 Certificates of CA (Form 3)q2 2021-22-signed.pdf · uploaded 27 Jan 2024Source
  • 29 Certificates of CA (Form 3)q3 2021-22-signed.pdf · uploaded 27 Jan 2024Source
  • 30 Certificates of CA (Form 3)q4 2021-22-signed.pdf · uploaded 27 Jan 2024Source
  • 31 Certificates of CA (Form 3)q1 -2022-23-signed.pdf · uploaded 27 Jan 2024Source
  • 32 Certificates of CA (Form 3)q2-2022-23-signed.pdf · uploaded 27 Jan 2024Source
  • 33 Certificates of CA (Form 3)q3 2022-23-signed.pdf · uploaded 27 Jan 2024Source
  • 34 Certificates of CA (Form 3)q4 2022-23-signed.pdf · uploaded 27 Jan 2024Source
  • 1 Disclosure of sold/ booked inventorysold booked upto 31 12 22.pdf · uploaded 29 Jan 2024Source
  • 2 Disclosure of sold/ booked inventorysold booked 31 3 23 signed.pdf · uploaded 29 Jan 2024Source
  • 3 Disclosure of sold/ booked inventorysold booked 30 6 23 signed.pdf · uploaded 29 Jan 2024Source
  • 4 Disclosure of sold/ booked inventorySOLD BOOKED INVENTORY 31 12 23.pdf · uploaded 29 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameformat A (4).pdf · uploaded 30 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)DS Associates Form 5 FY 2022 23 signed.pdf · uploaded 2 Feb 2024Source
  • 19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Atulya NirmanDec2023.pdf · uploaded 6 Feb 2024Source
  • 4 Commencement Certificates / NA Order for plotted developmentPlinth Completion.pdf · uploaded 7 Feb 2024Source
  • 18 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dec 2018.pdf · uploaded 12 Feb 2024Source
  • 19 Architect’s Certificate of Percentage of Completion of Work (Form 1)Mar 2019.pdf · uploaded 12 Feb 2024Source
  • 20 Architect’s Certificate of Percentage of Completion of Work (Form 1)D S June 2019.pdf · uploaded 12 Feb 2024Source
  • 21 Architect’s Certificate of Percentage of Completion of Work (Form 1)D S June Sep 2019.pdf · uploaded 12 Feb 2024Source
  • 22 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dec 2019 (2).pdf · uploaded 12 Feb 2024Source
  • 23 Architect’s Certificate of Percentage of Completion of Work (Form 1)D S Mar 2020.pdf · uploaded 12 Feb 2024Source
  • 24 Architect’s Certificate of Percentage of Completion of Work (Form 1)D S June 2020.pdf · uploaded 12 Feb 2024Source
  • 25 Architect’s Certificate of Percentage of Completion of Work (Form 1)D S Sep 2020.pdf · uploaded 12 Feb 2024Source
  • 26 Architect’s Certificate of Percentage of Completion of Work (Form 1)D S Dec 2020.pdf · uploaded 12 Feb 2024Source
  • 35 Certificates of CA (Form 3)CA Certificate dec 2023 -signed_11zon.pdf · uploaded 12 Feb 2024Source
  • 27 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 (50).pdf · uploaded 13 Feb 2024Source
  • 20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Dec 2018.pdf · uploaded 13 Feb 2024Source
  • 21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 June 2019.pdf · uploaded 13 Feb 2024Source
  • 22 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sep 2019.pdf · uploaded 13 Feb 2024Source
  • 23 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Dec 2019.pdf · uploaded 13 Feb 2024Source
  • 24 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Mar 2020.pdf · uploaded 13 Feb 2024Source
  • 25 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 June 2020.pdf · uploaded 13 Feb 2024Source
  • 26 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sep 2020.pdf · uploaded 13 Feb 2024Source
  • 27 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Dec 2020.pdf · uploaded 13 Feb 2024Source
  • 28 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Mar 2021.pdf · uploaded 13 Feb 2024Source
  • 29 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 June 2023.pdf · uploaded 13 Feb 2024Source
  • 30 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Dec 2023 (1).pdf · uploaded 13 Feb 2024Source
  • 31 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Dec 2023.pdf · uploaded 13 Feb 2024Source
  • 5 Disclosure of sold/ booked inventory5 (49) (1).pdf · uploaded 13 Feb 2024Source
  • 28 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 certificate.pdf · uploaded 4 May 2024Source
  • 32 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer certificate -signed.pdf · uploaded 4 May 2024Source
  • 6 Disclosure of sold/ booked inventorydisclosure of sold inventries.pdf · uploaded 4 May 2024Source
  • 7 Disclosure of sold/ booked inventorydisclosure of sold inventries.pdf · uploaded 4 May 2024Source
  • 36 Certificates of CA (Form 3)CA Form 3-signed.pdf · uploaded 4 May 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentcompletion certificate A B Wing.pdf · uploaded 4 May 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 arch certificate.pdf · uploaded 4 May 2024Source

Technical

  • DocumentLAY OUT.pdf · uploaded 5 Sep 2018Source
  • DocumentPlan 0002.pdf · uploaded 5 Sep 2018Source
  • DocumentPlan 0003.pdf · uploaded 5 Sep 2018Source
  • DocumentPlan 0004.pdf · uploaded 5 Sep 2018Source
  • DocumentPlan 0005.pdf · uploaded 5 Sep 2018Source
  • DocumentPlan 0006.pdf · uploaded 5 Sep 2018Source
  • DocumentPlan 0007.pdf · uploaded 5 Sep 2018Source
  • DocumentPlan 0008.pdf · uploaded 5 Sep 2018Source
  • DocumentPlan 0009.pdf · uploaded 5 Sep 2018Source
  • DocumentPlan 0010.pdf · uploaded 5 Sep 2018Source

Technical (Architect)

  • DocumentForm 1 certificate.pdf · uploaded 4 May 2024Source

Technical (Engineer)

  • DocumentForm 2 Engineer certificate -signed.pdf · uploaded 4 May 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Punawale, Mulshi taluka

Survey, CTS, gat or plot numbers

S No 18/3 18/4

Boundaries

North
Land Of Shinde
South
Land Of Santosh Kate
East
Land Of Aga
West
Land Of Sachin Kate Vijay Kate

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNarendra D Joshi—
Chartered accountantGothe Durande & Associates—
EngineerAqeel M H—
OtherManojkumar Patel—
OtherSarlaben Ramani—
OtherSudarshan Thombre—
Registered real estate agentMantra Vastu Private Limited—

Source: MahaRERA project page. Contact details are not shown.