Completion date passed

Punawale, Pune 411033 |Promoter: B A Consulting

26 Jul 2017Registered with MahaRERAFirst of 2 registrations
30 Dec 2023Promised completionLatest across registrations
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.63449, 73.74781
7 Plumeria Drive is at latitude 18.63449, longitude 73.74781.

Also registered as

7 Plumeria Drive- Phase 17 Plumeria Drive- Phase 2
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2021

P52100001152

The latest completion date on record passed 4 years and 10 months ago.

Registered
26 Jul 2017
Promised
30 Dec 2021

Completion promised for 30 Dec 2023

P52100023970

The latest completion date on record passed 2 years and 10 months ago.

Registered
14 Jan 2020
Promised
30 Dec 2023

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000115226 Jul 201730 Dec 2021—B A ConsultingProject page
P5210002397014 Jan 202030 Dec 2023—B A ConsultingProject page

Documents

2 documents held by Deedo

Registration certificate (2)

  • Registration certificateP52100023970 · 8 Sep 2021ViewSource
  • Registration certificateP52100001152 · 9 Sep 2021ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Punawale

Survey, CTS, gat or plot numbers

S no 6 partS no 7S no 8 part

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology