Completion date passed

Pimpri Chinchawad (M Corp.), Pune 411018 |Promoter: Ravima Developer

14 Jun 2019Registered with MahaRERAFirst of 2 registrations
30 Jun 2024Promised completionLatest across registrations
30 Jun 2025Revised completion1 of 2 registrations pushed back, by up to 1 year
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.63000, 73.80000
The Work Club is at latitude 18.63000, longitude 73.80000.

Also registered as

The Work Club Phase IThe Work Club Phase II
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Apr 2023

P52100021171

The latest completion date on record passed 3 years and 6 months ago.

Registered
14 Jun 2019
Promised
30 Apr 2023

Completion pushed back 1 year

P52100027555

The latest completion date on record passed 1 year and 4 months ago.

Registered
16 Dec 2020
Promised
30 Jun 2024
Revised
30 Jun 2025

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002117114 Jun 201930 Apr 2023—Ravima DeveloperProject page
P5210002755516 Dec 202030 Jun 202430 Jun 2025Ravima DeveloperProject page

Documents

3 documents held by Deedo

Registration certificates

  • Registration certificateP52100021171 · 8 Sep 2021ViewSource
  • Registration certificateP52100027555 · 8 Sep 2021ViewSource

Extension certificate

  • Extension certificateP52100027555 · 29 May 2024ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pimpri Chinchawad (M Corp.)

Survey, CTS, gat or plot numbers

5764

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology