B Bldg · Prosperia
Pimpri Chinchawad (M Corp.) · RERA P52100020997
IDBLD_03356714 floorsPromised date passed
14Sanctioned habitable floorsregistration certificate
28 Nov 2025Revised completionpromised 28 Nov 2025
157 of 159Units bookedMahaRERA project page
Floors
14 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100020997 · registered 27 May 2019
- Promised completion
- 28 Nov 2025
- Revised completion
- 28 Nov 2025
- Sanctioned habitable floors
- 14
- ProjectId
- 20,534
- ProjectName
- PROSPERIA PART 1
- TotalUnitCount
- 0
- ProjectBuildingId
- 1,83,414
- BuildingNameNumber
- B BLDG
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100020997
- ProjectBuildingWingsId
- 1,87,988
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- B BLDG
- NoOfBuildingWingFloorProposed
- 14
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 14
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 24.1 m² (260 sq.ft) | 5 | 5 |
| 1BHK | 24.2 m² (261 sq.ft) | 6 | 6 |
| 1BHK | 24.4 m² (263 sq.ft) | 5 | 5 |
| 1BHK | 24.4 m² (263 sq.ft) | 12 | 12 |
| 1BHK | 24.5 m² (264 sq.ft) | 18 | 18 |
| 1BHK | 26.8 m² (289 sq.ft) | 1 | 1 |
| 1BHK | 27.1 m² (291 sq.ft) | 1 | 1 |
| 1BHK | 27.1 m² (292 sq.ft) | 1 | 1 |
| 1BHK | 29.5 m² (318 sq.ft) | 14 | 14 |
| 1BHK | 30.3 m² (326 sq.ft) | 14 | 14 |
Show all 14 unit typesShow fewer unit types
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 44.1 m² (474 sq.ft) | 24 | 23 |
| 2BHK | 45.2 m² (487 sq.ft) | 27 | 27 |
| 2BHK | 45.7 m² (492 sq.ft) | 30 | 30 |
| Refused area 808 | 12.6 m² (135 sq.ft) | 1 | 0 |
| Total | 159 | 157 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology