Om Paradise
Completion date passedPimpri Chinchawad (M Corp.), Pune 412101 |Promoter: S K Buildcon
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2017
P52100002744The latest completion date on record passed 8 years and 10 months ago.
- Registered
- 4 Aug 2017
- Promised
- 31 Dec 2017
Completion pushed back 5 months
P52100008127The latest completion date on record passed 4 years and 5 months ago.
- Registered
- 18 Aug 2017
- Promised
- 30 Dec 2021
- Revised
- 31 May 2022
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100002744 | 4 Aug 2017 | 31 Dec 2017 | — | S K Buildcon | Project page |
| P52100008127 | 18 Aug 2017 | 30 Dec 2021 | 31 May 2022 | S K Buildcon | Project page |
Documents
3 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Pimpri Chinchawad (M Corp.)
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.