Nisarg Vatika

Completion date passed

Pimpri Chinchawad (M Corp.), Pune 412105 |Promoter: Nisarg Ventures

14 Aug 2017Registered with MahaRERAFirst of 2 registrations
30 Dec 2022Promised completionLatest across registrations
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.68068, 73.83909
Nisarg Vatika is at latitude 18.68068, longitude 73.83909.

Also registered as

Nisarg Vatika Phase II
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Sep 2019

P52100006131

The latest completion date on record passed 7 years and 1 month ago.

Registered
14 Aug 2017
Promised
30 Sep 2019

Completion promised for 30 Dec 2022

P52100020731

The latest completion date on record passed 3 years and 10 months ago.

Registered
7 May 2019
Promised
30 Dec 2022

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000613114 Aug 201730 Sep 2019—Nisarg VenturesProject page
P521000207317 May 201930 Dec 2022—Nisarg VenturesProject page

Documents

2 documents held by Deedo

Registration certificates

  • Registration certificateP52100006131 · 14 Aug 2017ViewSource
  • Registration certificateP52100020731 · 8 Sep 2021ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pimpri Chinchawad (M Corp.)

Survey, CTS, gat or plot numbers

245Gat No 245

Source: registration certificates, as stated there.