Mantra Meraki
Completion due Dec 2027Pimpri Chinchawad (M Corp.), Pune 411035 |Promoter: Mantra Residential Akurdi Private Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 7
- Phases
- 7
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2025
P52100030518The latest completion date on record passed 10 months ago.
- Registered
- 30 Aug 2021
- Promised
- 31 Dec 2025
Completion promised for 31 Dec 2025
P52100030605The latest completion date on record passed 10 months ago.
- Registered
- 1 Sep 2021
- Promised
- 31 Dec 2025
Completion promised for 31 Dec 2025
P52100030585The latest completion date on record passed 10 months ago.
- Registered
- 1 Sep 2021
- Promised
- 31 Dec 2025
Completion promised for 31 Mar 2025
P52100032354The latest completion date on record passed 1 year and 7 months ago.
- Registered
- 29 Dec 2021
- Promised
- 31 Mar 2025
Show 3 more registrations
Completion promised for 31 Dec 2026
P52100034671- Registered
- 20 Apr 2022
- Promised
- 31 Dec 2026
Completion pushed back 1 year
P52100034738- Registered
- 20 Apr 2022
- Promised
- 31 Dec 2026
- Revised
- 31 Dec 2027
Completion promised for 31 Dec 2026
P52100034965- Registered
- 28 Apr 2022
- Promised
- 31 Dec 2026
7 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100030518 | 30 Aug 2021 | 31 Dec 2025 | — | Mantra Residential Akurdi Private Limited | Project page |
| P52100030605 | 1 Sep 2021 | 31 Dec 2025 | — | Mantra Residential Akurdi Private Limited | Project page |
| P52100030585 | 1 Sep 2021 | 31 Dec 2025 | — | Mantra Residential Akurdi Private Limited | Project page |
| P52100032354 | 29 Dec 2021 | 31 Mar 2025 | — | Mantra Residential Akurdi Private Limited | Project page |
| P52100034671 | 20 Apr 2022 | 31 Dec 2026 | — | Mantra Residential Akurdi Private Limited | Project page |
| P52100034738 | 20 Apr 2022 | 31 Dec 2026 | 31 Dec 2027 | Mantra Residential Akurdi Private Limited | Project page |
| P52100034965 | 28 Apr 2022 | 31 Dec 2026 | — | Mantra Residential Akurdi Private Limited | Project page |
Documents
8 documents held by Deedo
Registration certificates
- Registration certificateP52100030518 · 30 Aug 2021ViewSource
- Registration certificateP52100030605 · 1 Sep 2021ViewSource
- Registration certificateP52100030585 · 1 Sep 2021ViewSource
- Registration certificateP52100032354 · 29 Dec 2021ViewSource
- Registration certificateP52100034671 · 20 Apr 2022ViewSource
- Registration certificateP52100034965 · 28 Apr 2022ViewSource
- Registration certificateP52100034738 · 6 Jan 2023ViewSource
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Pimpri Chinchawad (M Corp.)
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.