Kesar Kingdom
Completion date passedPimpri Chinchawad (M Corp.), Pune 411015 |Promoter: Param Group
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
P52100004710The latest completion date on record passed 7 years and 4 months ago.
- Registered
- 9 Aug 2017
- Promised
- 30 Jun 2018
- Revised
- 30 Jun 2019
Completion pushed back 1 year
P52100017986The latest completion date on record passed 3 years and 4 months ago.
- Registered
- 3 Oct 2018
- Promised
- 30 Jun 2022
- Revised
- 30 Jun 2023
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100004710 | 9 Aug 2017 | 30 Jun 2018 | 30 Jun 2019 | Param Group | Project page |
| P52100017986 | 3 Oct 2018 | 30 Jun 2022 | 30 Jun 2023 | Param Group | Project page |
Documents
4 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Pimpri Chinchawad (M Corp.)
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.