C · Excel Celestia Residency
Pimpri Chinchawad (M Corp.) · RERA P52100015436
IDBLD_03227011 floorsExtended 12 mo
11Sanctioned habitable floorsregistration certificate
30 Dec 2023Revised completionpromised 30 Dec 2022
44 of 47Units bookedMahaRERA project page
Floors
11 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100015436 · registered 23 Feb 2018
- Promised completion
- 30 Dec 2022
- Revised completion
- 30 Dec 2023
- Sanctioned habitable floors
- 11
- ProjectId
- 18,030
- ProjectName
- EXCEL CELESTIA RESIDENCY WING B AND C
- TotalUnitCount
- 47
- ProjectBuildingId
- 50,792
- BuildingNameNumber
- C
- FsiWithSanctionSqmts
- 11
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 47
- ProjectRegistartionNo
- P52100015436
- ProjectBuildingWingsId
- 50,792
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- C
- NoOfBuildingWingFloorProposed
- 11
- NoOfBuildingWingFloorHabitable
- 11
- NoOfBuildingWingFloorSanctioned
- 11
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 32 m² (344 sq.ft) | 24 | 24 |
| 1 BHK | 32.4 m² (348 sq.ft) | 23 | 20 |
| Total | 47 | 44 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology