Skip to content

Eshan Culture

Certificate Signed

Pimpri Chinchawad (M Corp.), Pune 412101 |Promoter: Eshan Developers

Residential / Group HousingRERAP52100009970
23 Aug 2017Registered with MahaRERA
31 Dec 2019Promised completion
29 Feb 2024Revised completionPushed back 4 years and 2 months
1Building
19Units registered14 booked (74%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 1BHK 102, 1BHK 103, 1BHK 104, 1BHK 202, 1BHK 203, 1BHK 204, 1BHK 302, 1BHK 303, 1BHK 304, 1BHK 402, 2BHK, 2BHK 101, 2BHK 201, 2BHK 301, 2BHK 40119 units in all
Address
SR NO 13, Sainagar road, MamurdiPIN 412101
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.67686, 73.71317
Eshan Culture is at latitude 18.67686, longitude 73.71317.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 years and 2 months

The latest completion date on record passed 2 years and 8 months ago.

Registered
23 Aug 2017
Promised
31 Dec 2019
Revised
29 Feb 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000997023 Aug 201731 Dec 201929 Feb 2024Eshan DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Essan Culture619

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

14 of 19 units booked (74%), as the promoter reported to MahaRERA

1BHK · 4 units1BHK 102 · 1 unit1BHK 103 · 1 unit1BHK 104 · 1 unit1BHK 202 · 1 unit1BHK 203 · 1 unit1BHK 204 · 1 unit1BHK 302 · 1 unit1BHK 303 · 1 unit1BHK 304 · 1 unit1BHK 402 · 1 unit2BHK · 1 unit2BHK 101 · 1 unit2BHK 201 · 1 unit2BHK 301 · 1 unit2BHK 401 · 1 unit
TypeCarpet areaUnitsBooked
1BHK38.69 sq m · 416 sq ft10
1BHK39.68 sq m · 427 sq ft10
1BHK41.89 sq m · 451 sq ft10
1BHK46.04 sq m · 496 sq ft10
1BHK 10241.2 sq m · 443 sq ft11
1BHK 10338.03 sq m · 409 sq ft11
1BHK 10439.29 sq m · 423 sq ft11
1BHK 20241.21 sq m · 444 sq ft11
Show all 19 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK 20338.46 sq m · 414 sq ft11
1BHK 20439.29 sq m · 423 sq ft11
1BHK 30241.2 sq m · 443 sq ft11
1BHK 30338.03 sq m · 409 sq ft11
1BHK 30439.29 sq m · 423 sq ft11
1BHK 40241.2 sq m · 443 sq ft11
2BHK57.06 sq m · 614 sq ft10
2BHK 10157.02 sq m · 614 sq ft11
2BHK 20157.06 sq m · 614 sq ft11
2BHK 30157.02 sq m · 614 sq ft11
2BHK 40157.06 sq m · 614 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 68 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN CARD (FIRM ).pdf · uploaded 14 Aug 2017Source

Legal

  • Legal Title reportSEARCH TITLE REPORT.pdf · uploaded 14 Aug 2017Source
  • Declaration Form BFORM B.pdf · uploaded 14 Aug 2017Source
  • OtherCC Eshan (1).pdf · uploaded 23 Dec 2020Source
  • OtherA.pdf · uploaded 27 Apr 2023Source
  • OtherMAHA RERA AUTHORITY.pdf · uploaded 28 Apr 2023Source
Show all 70 documentsShow fewer documents

Legal

  • Declaration Form BFROM B.pdf · uploaded 28 Apr 2023Source

Migrated

  • 1 PAN CardPAN CARD (FIRM ).pdf · uploaded 14 Aug 2017Source
  • 1 Copy of the legal title reportSEARCH TITLE REPORT.pdf · uploaded 14 Aug 2017Source
  • 1 Details of encumbrancesFORM B.pdf · uploaded 14 Aug 2017Source
  • 1 Copy of Layout Approval (in case of layout)dRAWING 1(2).pdf · uploaded 14 Aug 2017Source
  • 2 Copy of Layout Approval (in case of layout)dRAWING 2(2).pdf · uploaded 14 Aug 2017Source
  • 1 Building Plan Approval (IOD)dRAWING 1(2).pdf · uploaded 14 Aug 2017Source
  • 2 Building Plan Approval (IOD)dRAWING 2(2).pdf · uploaded 14 Aug 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT.pdf · uploaded 14 Aug 2017Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 14 Aug 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECTS CERTIFICATE.pdf · uploaded 14 Aug 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)EINGCERTIFICATES.pdf · uploaded 14 Aug 2017Source
  • 1 Certificates of CA (Form 3)CA CRETI.pdf · uploaded 14 Aug 2017Source
  • 1 Proforma of Allotment letterPRO ALLOT CERTIFICATE.pdf · uploaded 14 Aug 2017Source
  • 2 Proforma of Allotment letterAGREEMENT TO SALE.pdf · uploaded 14 Aug 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS CERTIFICATE 20 04 19.pdf · uploaded 7 Jun 2019Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)CC Eshan.pdf · uploaded 23 Dec 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)CC Eshan.pdf · uploaded 23 Dec 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)CC Eshan.pdf · uploaded 23 Dec 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)CC Eshan.pdf · uploaded 23 Dec 2020Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCC Eshan.pdf · uploaded 23 Dec 2020Source
  • 1 Details of Restarting of Construction work post lockdownCC Eshan (1).pdf · uploaded 23 Dec 2020Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)FORM 4 ESHAN.pdf · uploaded 23 Dec 2020Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)CC Eshan.pdf · uploaded 23 Dec 2020Source
  • 1 Status of ConveyanceCC Eshan (1).pdf · uploaded 23 Dec 2020Source
  • 1 OtherCC Eshan (1).pdf · uploaded 23 Dec 2020Source
  • 2 a Details of encumbrances concerned to Finance1 Commencement Certificates NA Order for plotted development.pdf · uploaded 2 Jan 2023Source
  • 1 b Details of encumbrances concerned to Legal1 Commencement Certificates NA Order for plotted development.pdf · uploaded 2 Jan 2023Source
  • 3 Copy of Layout Approval (in case of layout)BULE PRINT 1_compressed.pdf · uploaded 2 Jan 2023Source
  • 4 Copy of Layout Approval (in case of layout)BULE PRINT.pdf · uploaded 2 Jan 2023Source
  • 3 Building Plan Approval (IOD)PLAN SACcompressed.pdf · uploaded 2 Jan 2023Source
  • 1 Declaration about Commencement Certificate1 Commencement Certificates NA Order for plotted development.pdf · uploaded 2 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A.pdf · uploaded 2 Jan 2023Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD BOOKED INVENTOR.pdf · uploaded 2 Jan 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 05 2019.pdf · uploaded 2 Jan 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 05 2020.pdf · uploaded 2 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 05 2021.pdf · uploaded 2 Jan 2023Source
  • 3 a Details of encumbrances concerned to FinanceENCUMBRANCE DECLA.pdf · uploaded 27 Apr 2023Source
  • 2 b Details of encumbrances concerned to LegalENCUMBRANCE DECLA.pdf · uploaded 27 Apr 2023Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECTS CERT.pdf · uploaded 27 Apr 2023Source
  • 2 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD.pdf · uploaded 27 Apr 2023Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentALLOTMENT LATER.pdf · uploaded 27 Apr 2023Source
  • 2 OtherA.pdf · uploaded 27 Apr 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentcommencement certificate.pdf · uploaded 28 Apr 2023Source
  • 2 Declaration in FORM BFROM B.pdf · uploaded 28 Apr 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 28 Apr 2023Source
  • 1 CERSAI detailsCREDAI .pdf · uploaded 28 Apr 2023Source
  • 3 Disclosure of sold/ booked inventorySOLD DETAILS.pdf · uploaded 28 Apr 2023Source
  • 2 Certificates of CA (Form 3)FORM3.pdf · uploaded 28 Apr 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST .pdf · uploaded 28 Apr 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK DETAILS.pdf · uploaded 28 Apr 2023Source
  • 1 Deviation Report with respect to Allotment letterALLOTMENT LATER.pdf · uploaded 28 Apr 2023Source
  • 3 OtherMAHA RERA AUTHORITY.pdf · uploaded 28 Apr 2023Source

Technical

  • DocumentdRAWING 1(2).pdf · uploaded 14 Aug 2017Source
  • DocumentdRAWING 2(2).pdf · uploaded 14 Aug 2017Source
  • DocumentdRAWING 1(2).pdf · uploaded 14 Aug 2017Source
  • DocumentdRAWING 2(2).pdf · uploaded 14 Aug 2017Source
  • DocumentBULE PRINT 1_compressed.pdf · uploaded 2 Jan 2023Source
  • DocumentBULE PRINT.pdf · uploaded 2 Jan 2023Source
  • DocumentPLAN SACcompressed.pdf · uploaded 2 Jan 2023Source

Technical (Architect)

  • DocumentARCHITECTS CERT.pdf · uploaded 27 Apr 2023Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 28 Apr 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pimpri Chinchawad (M Corp.), Haveli taluka

Survey, CTS, gat or plot numbers

SR NO 13

Boundaries

North
13 Part
South
15 Feet Road
East
20 Feet Road
West
Property Of Mr Shaikh

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSandeep Dange—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology