Skip to content
Deedo home
Menu

Dhananjay Paradise

Certificate Signed

Pimpri Chinchawad (M Corp.), Pune 412105 |Promoter: Sudam Pandurang Bhore

Residential / Group HousingRERAP52100025787
14 Jul 2020Registered with MahaRERA
30 Jun 2022Promised completion
31 Dec 2022Revised completionPushed back 6 months
1Building
8Units registered8 booked (100%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK8 units in all
Address
Plot No 158, Sector No 4, Moshi Pradhikaran, Near Panjarpol, Moshi PradhikaranPIN 412105
Designated bank account
43
Developed in phases
No

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 6 months

The latest completion date on record passed 3 years and 10 months ago.

Registered
14 Jul 2020
Promised
30 Jun 2022
Revised
31 Dec 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002578714 Jul 202030 Jun 202231 Dec 2022Sudam Pandurang BhoreProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Dhananjay Paradise58

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

8 of 8 units booked (100%), as the promoter reported to MahaRERA

2BHK · 8 units
TypeCarpet areaUnitsBooked
2BHK67.66 sq m · 728 sq ft88

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 28 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPan card.pdf · uploaded 9 Jul 2020Source

Legal

  • Legal Title reportSearch Report and Title Certificate.pdf · uploaded 9 Jul 2020Source
  • Declaration Form BFormB.pdf · uploaded 9 Jul 2020Source
  • Legal Title reportTITLE REPORT.pdf · uploaded 15 Jun 2022Source

Migrated

  • 1 PAN CardPan card.pdf · uploaded 9 Jul 2020Source
  • 1 Copy of the legal title reportSearch Report and Title Certificate.pdf · uploaded 9 Jul 2020Source
Show all 30 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesEncumbrance.pdf · uploaded 9 Jul 2020Source
  • 1 Copy of Layout Approval (in case of layout)Layout Approved.pdf · uploaded 9 Jul 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout Approved.pdf · uploaded 9 Jul 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 9 Jul 2020Source
  • 1 Declaration in FORM BFormB.pdf · uploaded 9 Jul 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 scanned.pdf · uploaded 9 Jul 2020Source
  • 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 9 Jul 2020Source
  • 2 Copy of the legal title reportTITLE REPORT.pdf · uploaded 15 Jun 2022Source
  • 1 Declaration about Commencement CertificateDeclaration About Commencement Certificate.pdf · uploaded 15 Jun 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 15 Jun 2022Source
  • 1 Disclosure of sold/ booked inventoryDisclosure Of Sold Book Inventory.pdf · uploaded 15 Jun 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200239816134_For_Asset_Based_Search_15_06_2022_17_25_20_646.pdf · uploaded 15 Jun 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA Architect Certificate.pdf · uploaded 30 Dec 2022Source
  • 2 Disclosure of sold/ booked inventoryDisclosure Of Sold- Booked Inventory.pdf · uploaded 30 Dec 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5_signed.pdf · uploaded 30 Dec 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5_Dhananjay Pradise_Signed.pdf · uploaded 30 Dec 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate.pdf · uploaded 30 Dec 2022Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4_Architect_Architect_Certificate_Upload.PDF · uploaded 2 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 PS.pdf · uploaded 31 Dec 2023Source

Technical

  • DocumentLayout Approved.pdf · uploaded 9 Jul 2020Source
  • DocumentLayout Approved.pdf · uploaded 9 Jul 2020Source

Technical (Architect)

  • DocumentRERA Architect Certificate.pdf · uploaded 30 Dec 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pimpri Chinchawad (M Corp.), Haveli taluka

Survey, CTS, gat or plot numbers

PLOT NO 158SECTOR NO 4

Boundaries

North
By 15 Mtrs Wide Road
South
By Property Of Common Housing Scheme No 09
East
By Property Of Plot No157
West
By Property Of Plot No 159 And 160

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectR D Deshpandey—
Chartered accountantCa Vaibhav Modi—
EngineerMahadev B Biradar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology