Skip to content
Deedo home
Menu

Devraee

Completion date passed

Pimpri Chinchawad (M Corp.), Pune 412114 |Promoter: Laxman Takkekar Enterprises

20 Jul 2017Registered with MahaRERAFirst of 2 registrations
31 May 2019Promised completionLatest across registrations
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.68311, 73.79779
Devraee is at latitude 18.68311, longitude 73.79779.

Also registered as

Devraee C WingDevraee A And B Wing
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 May 2019

P52100000682

The latest completion date on record passed 7 years and 5 months ago.

Registered
20 Jul 2017
Promised
31 May 2019

Completion promised for 31 Dec 2017

P52100000679

The latest completion date on record passed 8 years and 10 months ago.

Registered
20 Jul 2017
Promised
31 Dec 2017

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000068220 Jul 201731 May 2019—Laxman Takkekar EnterprisesProject page
P5210000067920 Jul 201731 Dec 2017—Laxman Takkekar EnterprisesProject page

Documents

2 documents held by Deedo

Registration certificates

  • Registration certificateP52100000682 · 20 Jul 2017ViewSource
  • Registration certificateP52100000679 · 20 Jul 2017ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pimpri Chinchawad (M Corp.)

Survey, CTS, gat or plot numbers

286GAT NO 285

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology