Skip to content

Wing A · Bora Pride

Pimpri Chinchawad (M Corp.) · RERA P52100048667

IDBLD_0354514 floorsPromised date passed
4Sanctioned habitable floorsregistration certificate
31 Mar 2025Revised completionpromised 31 Mar 2025
4 of 12Units bookedMahaRERA project page

Floors

4 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100048667 · registered 12 Jan 2023
Promised completion
31 Mar 2025
Revised completion
31 Mar 2025
Sanctioned habitable floors
4
ProjectId
38,567
ProjectName
BORA PRIDE
TotalUnitCount
0
ProjectBuildingId
64,283
BuildingNameNumber
Wing A
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52100048667
ProjectBuildingWingsId
64,283
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Wing A
NoOfBuildingWingFloorProposed
4
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
4

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK45.2 m² (486 sq.ft)124
Total124
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology