B wing Anandibaug Phase ii · B Wing
Pimpri Chinchawad (M Corp.) · RERA P52100002168
IDBLD_02435312 floorsPromised date passed
12Sanctioned habitable floorsregistration certificate
31 Dec 2017Revised completionpromised 31 Dec 2017
19 of 33Units bookedMahaRERA project page
Floors
12 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100002168 · registered 13 Nov 2017
- Promised completion
- 31 Dec 2017
- Revised completion
- 31 Dec 2017
- Sanctioned habitable floors
- 12
- ProjectId
- 4,902
- ProjectName
- B WING
- TotalUnitCount
- 0
- ProjectBuildingId
- 47,646
- BuildingNameNumber
- B wing Anandibaug Phase ii
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100002168
- ProjectBuildingWingsId
- 47,646
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- B wing Anandibaug Phase ii
- NoOfBuildingWingFloorProposed
- 12
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 12
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2 BHK | 54.4 m² (586 sq.ft) | 2 | 2 |
| 2 BHK | 57.1 m² (614 sq.ft) | 3 | 3 |
| 2 BHK | 58.7 m² (632 sq.ft) | 1 | 1 |
| 2 BHK | 59 m² (635 sq.ft) | 3 | 3 |
| 2 BHK | 59.8 m² (643 sq.ft) | 3 | 0 |
| 2 BHK | 59.8 m² (643 sq.ft) | 3 | 2 |
| 2 BHK | 60.1 m² (646 sq.ft) | 3 | 1 |
| 2 BHK | 61.3 m² (660 sq.ft) | 3 | 3 |
| 2 BHK | 63.7 m² (686 sq.ft) | 3 | 0 |
| 2 BHK | 72.9 m² (784 sq.ft) | 1 | 0 |
Show all 14 unit typesShow fewer unit types
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 3 BHK | 73.1 m² (787 sq.ft) | 3 | 1 |
| 3 BHK | 74.5 m² (802 sq.ft) | 3 | 2 |
| 3 BHK | 88.6 m² (953 sq.ft) | 1 | 1 |
| 3 BHK | 96.2 m² (1,035 sq.ft) | 1 | 0 |
| Total | 33 | 19 |