Ace Aastha
Completion date passedPimpri Chinchawad (M Corp.), Pune 412105 |Promoter: Sakshi Developers
Project summary
As registered with MahaRERA
- RERA registrations
- 3
- Phases
- 3
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Oct 2022
P52100016214The latest completion date on record passed 4 years ago.
- Registered
- 24 Apr 2018
- Promised
- 30 Oct 2022
Completion promised for 30 Oct 2023
P52100016438The latest completion date on record passed 3 years ago.
- Registered
- 10 May 2018
- Promised
- 30 Oct 2023
Completion promised for 30 Sep 2025
P52100024476The latest completion date on record passed 1 year and 1 month ago.
- Registered
- 18 Feb 2020
- Promised
- 30 Sep 2025
3 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100016214 | 24 Apr 2018 | 30 Oct 2022 | — | Sakshi Developers | Project page |
| P52100016438 | 10 May 2018 | 30 Oct 2023 | — | Sakshi Developers | Project page |
| P52100024476 | 18 Feb 2020 | 30 Sep 2025 | 30 Sep 2025 | Sakshi Developers | Project page |
Documents
4 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Pimpri Chinchawad (M Corp.)
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.