RERA projects in Others

5 projects under 5 MahaRERA registrations, registered 2025–2026. 60% have a completion date extended beyond the one promised.

Locality
5RERA projects
5Registrations
5Completion still due0 past their completion date
4 monthsMedian extension beyond promised date60% of registrations extended
0Regulatory casesnone on MahaRERA's lists
9Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20252
20263

Projects in Others

5 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Vijay By Altius ConstructionVaishali Vijay Vangikar MohitePM126000260245819 Oct 202628 Feb 2030—Not yet due0
Akshay ResidencyMahakal DevelopersPR12600025026389 Mar 202631 Dec 202730 Apr 2028Extended 4 mo0
Shrisha InfiniaEmperos BuildconPM126000250237016 Feb 202631 Dec 203131 Dec 2031Not yet due0
Krishnai ResidencyVastu BuildconPR12600025007239 Sep 202530 Sep 202630 Jan 2027Extended 4 mo0
Suvarnadip SarthaKrishnaraj DevelopersPR126000250013826 Jun 202531 Dec 202730 Apr 2028Extended 4 mo0

Other localities in Pune

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Emperos Buildcon1 project
  2. Krishnaraj Developers1 project
  3. Mahakal Developers1 project
  4. Vaishali Vijay Vangikar Mohite1 project
  5. Vastu Buildcon1 project
Data through19 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology