Building H · Project Abcd Phase 4
Mundhawa · RERA P52100031240
IDBLD_0303839 floorsNot yet due
9Sanctioned habitable floorsregistration certificate
31 Dec 2026Revised completionpromised 31 Dec 2026
0 of 51Units bookedMahaRERA project page
Floors
9 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100031240 · registered 11 Oct 2021
- Promised completion
- 31 Dec 2026
- Revised completion
- 31 Dec 2026
- Sanctioned habitable floors
- 9
- ProjectId
- 30,393
- ProjectName
- PROJECT ABCD PHASE 4
- TotalUnitCount
- 51
- ProjectBuildingId
- 1,49,858
- BuildingNameNumber
- BUILDING H
- FsiWithSanctionSqmts
- 7
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 51
- ProjectRegistartionNo
- P52100031240
- ProjectBuildingWingsId
- 1,53,275
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- BUILDING H
- NoOfBuildingWingFloorProposed
- 9
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 9
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 40 m² (430 sq.ft) | 51 | 0 |
| Total | 51 | 0 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology