G Building · K City Phase 3

Mundhawa · RERA P52100052901

IDBLD_03191913 floorsExtended 4 mo
13Sanctioned habitable floorsregistration certificate
30 Apr 2029Revised completionpromised 31 Dec 2028
52 of 52Units bookedMahaRERA project page

Floors

13 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100052901 · registered 5 Oct 2023
Promised completion
31 Dec 2028
Revised completion
30 Apr 2029
Sanctioned habitable floors
13
ProjectId
41,548
ProjectName
K City Phase 3
TotalUnitCount
52
ProjectBuildingId
1,72,451
BuildingNameNumber
G BUILDING
FsiWithSanctionSqmts
16
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
52
ProjectRegistartionNo
P52100052901
ProjectBuildingWingsId
1,75,908
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
G BUILDING
NoOfBuildingWingFloorProposed
16
NoOfBuildingWingFloorHabitable
13
NoOfBuildingWingFloorSanctioned
16

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK63.2 m² (680 sq.ft)2626
3BHK84.8 m² (913 sq.ft)2626
Total5252
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology