33 keshav kunj
Certificate SignedMundhawa, Pune 411036 |Promoter: Crystal Properties
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 2
- Unit types
- 3BHK, Cafeteria, Godown, Office space, Shoowroom, Showroom85 units in all
- Address
- S.NO.33/3B/1A, 33/3B/1B, 33/3B/2 33/3B/3B, 333B/4, 33/3B/5, 33/3B3A, Mundhawa, Keshavnagar, MundhawaPIN 411036
- Designated bank account
- 88
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 6 years and 3 months
The latest completion date on record passed 10 months ago.
- Registered
- 5 Aug 2017
- Promised
- 30 Sep 2019
- Revised
- 31 Dec 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100003364 | 5 Aug 2017 | 30 Sep 2019 | 31 Dec 2025 | Crystal Properties | Project page |
2 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| 33 keshav kunj D Wing | 13 | 52 |
| Crystal Fortune | 7 | 33 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
58 of 85 units booked (68%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| 33 keshav kunj D Wing | 3BHK | 53.79 sq m · 579 sq ft | 2 | 2 |
| 33 keshav kunj D Wing | 3BHK | 54 sq m · 581 sq ft | 2 | 2 |
| 33 keshav kunj D Wing | 3BHK | 54.62 sq m · 588 sq ft | 16 | 16 |
| 33 keshav kunj D Wing | 3BHK | 66.51 sq m · 716 sq ft | 1 | 1 |
| 33 keshav kunj D Wing | 3BHK | 67.26 sq m · 724 sq ft | 4 | 4 |
| 33 keshav kunj D Wing | 3BHK | 67.35 sq m · 725 sq ft | 11 | 11 |
| 33 keshav kunj D Wing | 3BHK | 67.54 sq m · 727 sq ft | 6 | 6 |
| 33 keshav kunj D Wing | 3BHK | 68 sq m · 732 sq ft | 5 | 5 |
Show all 26 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| 33 keshav kunj D Wing | 3BHK | 68.09 sq m · 733 sq ft | 5 | 5 |
| Crystal Fortune | Cafeteria | 803.56 sq m · 8,649 sq ft | 1 | 0 |
| Crystal Fortune | Godown | 45.1 sq m · 485 sq ft | 1 | 0 |
| Crystal Fortune | Office space | 76.15 sq m · 820 sq ft | 3 | 1 |
| Crystal Fortune | Office space | 82.6 sq m · 889 sq ft | 3 | 0 |
| Crystal Fortune | Office space | 90.96 sq m · 979 sq ft | 3 | 0 |
| Crystal Fortune | Office space | 91.79 sq m · 988 sq ft | 3 | 0 |
| Crystal Fortune | Office space | 101.02 sq m · 1,087 sq ft | 3 | 0 |
| Crystal Fortune | Office space | 104.14 sq m · 1,121 sq ft | 3 | 0 |
| Crystal Fortune | Office space | 107.78 sq m · 1,160 sq ft | 3 | 0 |
| Crystal Fortune | Office space | 122.18 sq m · 1,315 sq ft | 3 | 0 |
| Crystal Fortune | Shoowroom | 63.33 sq m · 682 sq ft | 1 | 1 |
| Crystal Fortune | Showroom | 50.43 sq m · 543 sq ft | 1 | 1 |
| Crystal Fortune | Showroom | 50.95 sq m · 548 sq ft | 1 | 1 |
| Crystal Fortune | Showroom | 59.92 sq m · 645 sq ft | 1 | 0 |
| Crystal Fortune | Showroom | 61.72 sq m · 664 sq ft | 1 | 1 |
| Crystal Fortune | Showroom | 80.87 sq m · 870 sq ft | 1 | 0 |
| Crystal Fortune | Showroom | 103.94 sq m · 1,119 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 82 filings listed on MahaRERA's project page
Finance
- PAN Cardcrystal properties pan card.pdf · uploaded 26 Jul 2017Source
Legal
Show all 84 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesEncumberance Certificate.pdf · uploaded 26 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)sanstion plan.pdf · uploaded 26 Jul 2017Source
- 1 Building Plan Approval (IOD)sanstion plan.pdf · uploaded 26 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentNA Order 2011.PDF · uploaded 26 Jul 2017Source
- 2 Commencement Certificates / NA Order for plotted developmentNA Order 2012.PDF · uploaded 26 Jul 2017Source
- 3 Commencement Certificates / NA Order for plotted developmentNA Order 2014.PDF · uploaded 26 Jul 2017Source
- 1 Declaration in FORM BFORM-B.pdf · uploaded 26 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form A (Architect Certificate).pdf · uploaded 26 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer Certificate .pdf · uploaded 26 Jul 2017Source
- 1 Certificates of CA (Form 3)Form 3 C ACertificate.pdf · uploaded 26 Jul 2017Source
- 1 Proforma of Allotment letterRera Format Proforma Agreement.pdf · uploaded 26 Jul 2017Source
- 2 Building Plan Approval (IOD)Plan Sanction.pdf · uploaded 13 Mar 2018Source
- 4 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 13 Mar 2018Source
- 1 Certificates of CA (Form 5)form 5.pdf · uploaded 15 Oct 2018Source
- 1 OtherCompletion Certificate D wing.pdf · uploaded 30 Oct 2018Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentD_bld_Completion_0002.pdf · uploaded 3 Mar 2020Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Crystal-RERA Form 4_1.pdf · uploaded 5 Mar 2020Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentD wing Completion 2.pdf · uploaded 6 Mar 2020Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Architects Certificate.pdf · uploaded 9 Mar 2020Source
- 1 Proforma of Agreement for saleAGREEMENT TO SALE KESHAV.pdf · uploaded 15 May 2023Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)1 FORM 1.pdf · uploaded 18 May 2023Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)2 FORM 2.pdf · uploaded 18 May 2023Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)3 FORM 1.pdf · uploaded 18 May 2023Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)4 FORM 1.pdf · uploaded 18 May 2023Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)5 FORM 1.pdf · uploaded 18 May 2023Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)6 FORM 1.pdf · uploaded 18 May 2023Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)7 FORM 1.pdf · uploaded 18 May 2023Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)8 FORM 1.pdf · uploaded 18 May 2023Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)9 FORM 1.pdf · uploaded 18 May 2023Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)10 FORM 1.pdf · uploaded 18 May 2023Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)11 FORM 1.pdf · uploaded 18 May 2023Source
- 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)12 FORM 1.pdf · uploaded 18 May 2023Source
- 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)13 FORM 1.pdf · uploaded 18 May 2023Source
- 16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)14 FORM 1.pdf · uploaded 18 May 2023Source
- 17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)15 FORM 1.pdf · uploaded 18 May 2023Source
- 18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)16 FORM 1.pdf · uploaded 18 May 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2 A MARCH 2018.pdf · uploaded 19 May 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2 A MARCH 2019.pdf · uploaded 19 May 2023Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2 A MARCH 2020.pdf · uploaded 19 May 2023Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2 A SEP 2018.pdf · uploaded 19 May 2023Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2 A SEP 2019.pdf · uploaded 19 May 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2 A MARCH 2021.pdf · uploaded 19 May 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2 A SEP 2020.pdf · uploaded 19 May 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2 A SEP 2021.pdf · uploaded 19 May 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2 A MARCH 2022.pdf · uploaded 19 May 2023Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2 A SEP 2022.pdf · uploaded 19 May 2023Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2 A MARCH 2023.pdf · uploaded 19 May 2023Source
- 1 Disclosure of sold/ booked inventoryInformation of sold - booked inventory.pdf · uploaded 19 May 2023Source
- 2 Disclosure of sold/ booked inventoryInformation of sold - booked inventory new.pdf · uploaded 22 May 2023Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg-FORM 2 RERA For CP Apr 2020.pdf · uploaded 26 May 2023Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg-FORM 2 RERA For CP Apr 2021.pdf · uploaded 26 May 2023Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg-FORM 2 RERA For CP July 2022.pdf · uploaded 26 May 2023Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg-FORM 2 RERA For CP Apr 2023.pdf · uploaded 26 May 2023Source
- 2 Certificates of CA (Form 3)FORM 3 MARCH 2018_compressed.pdf · uploaded 1 Jun 2023Source
- 3 Certificates of CA (Form 3)FORM 3 MARCH 2019_compressed.pdf · uploaded 1 Jun 2023Source
- 4 Certificates of CA (Form 3)FORM 3 MARCH 2020_compressed.pdf · uploaded 1 Jun 2023Source
- 5 Certificates of CA (Form 3)FORM 3 MARCH 2021_compressed.pdf · uploaded 1 Jun 2023Source
- 6 Certificates of CA (Form 3)FORM 3 MARCH 2022_compressed.pdf · uploaded 1 Jun 2023Source
- 19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Rera Certificate for CP- Amenity Apr 2019.pdf · uploaded 2 Jun 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)18 19.pdf · uploaded 2 Jun 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)19 20_compressed.pdf · uploaded 2 Jun 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)20 21_compressed.pdf · uploaded 2 Jun 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)21 22_compressed.pdf · uploaded 2 Jun 2023Source
- 20 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 6 Dec 2023Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 6 Dec 2023Source
- 7 Certificates of CA (Form 3)FORM 3.pdf · uploaded 6 Dec 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5_compressed.pdf · uploaded 6 Dec 2023Source
- 5 Commencement Certificates / NA Order for plotted developmentCommencement certificate_compressed.pdf · uploaded 20 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A CRYSTAL.pdf · uploaded 29 Dec 2023Source
- 21 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 8 Jan 2024Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 8 Jan 2024Source
Technical
Technical (Architect)
- DocumentForm 1.pdf · uploaded 8 Jan 2024Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 8 Jan 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Mundhawa, Haveli taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- By Part Of S No 33
- South
- By S No 32
- East
- By Part Of S No 33
- West
- 60ft Rp Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Aniruddha Jagannath Shinde | — |
Source: MahaRERA project page. Contact details are not shown.