Moshi, Pune 412105 |Promoter: Sitai Construction

7 Mar 2025Registered with MahaRERA
31 Dec 2027Promised completion
30 Apr 2028Revised completionPushed back 4 months
1Building
88Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1 BHK Landowner, 1 BHK Promoter, 2.5 BHK Promoter, 2 BHK Landowner, 2 BHK Promoter, Shop Landowner, ShopPromoter, SHOP Promoter88 units in all
Address
Gat No 305, Kudale wasti, Near Kudale GardenPIN 412105
Designated bank account
76
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.67443, 73.86161
RKH Mountain Manor is at latitude 18.67443, longitude 73.86161.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
7 Mar 2025
Promised
31 Dec 2027
Revised
30 Apr 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000794807 Mar 202531 Dec 202730 Apr 2028Sitai ConstructionProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A Wing1588

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 88 units booked (0%), as the promoter reported to MahaRERA

1 BHK Landowner · 5 units1 BHK Promoter · 19 units2.5 BHK Promoter · 15 units2 BHK Landowner · 1 unit2 BHK Promoter · 35 unitsShop Landowner · 4 unitsShopPromoter · 8 unitsSHOP Promoter · 1 unit
TypeCarpet areaUnitsBooked
1 BHK Landowner39.83 sq m · 429 sq ft50
1 BHK Promoter39.83 sq m · 429 sq ft190
2.5 BHK Promoter68.51 sq m · 737 sq ft60
2.5 BHK Promoter73.96 sq m · 796 sq ft90
2 BHK Landowner58.86 sq m · 634 sq ft10
2 BHK Promoter58.86 sq m · 634 sq ft290
2 BHK Promoter59.92 sq m · 645 sq ft60
Shop Landowner26.5 sq m · 285 sq ft20
Show all 17 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop Landowner27.29 sq m · 294 sq ft10
Shop Landowner29.11 sq m · 313 sq ft10
ShopPromoter13.83 sq m · 149 sq ft10
ShopPromoter19.15 sq m · 206 sq ft30
ShopPromoter21.24 sq m · 229 sq ft10
ShopPromoter23.13 sq m · 249 sq ft10
ShopPromoter31.08 sq m · 335 sq ft10
ShopPromoter33.69 sq m · 363 sq ft10
SHOP Promoter27.46 sq m · 296 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 117 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Sitai.pdf · uploaded 22 Jan 2025Source
  • Other – Financepdf_to_scan_67a7180535e54_temp_67a717fa6e879.pdf · uploaded 8 Feb 2025Source

Legal

  • Legal Title reportpdf_to_scan_67a88f635959d_temp_67a88f59b24c1.pdf · uploaded 22 Jan 2025Source
  • Other – LegalAnnexure A .pdf · uploaded 24 Jan 2025Source
  • Other – Legalमोशी_305_Satbara (1).pdf · uploaded 25 Jan 2025Source
  • Declaration Form Bform b promoter.pdf · uploaded 1 Feb 2025Source
  • Legal Title reportUpdated Legal Title report_11zon (1).pdf · uploaded 9 Feb 2025Source
Show all 118 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN Sitai.pdf · uploaded 22 Jan 2025Source
  • 1 Copy of the legal title reportpdf_to_scan_67a88f635959d_temp_67a88f59b24c1.pdf · uploaded 22 Jan 2025Source
  • 1 Copy of Layout Approval (in case of layout)1_11zon.pdf · uploaded 22 Jan 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC (2).pdf · uploaded 22 Jan 2025Source
  • 7 Copy of Layout Approval (in case of layout)7_11zon.pdf · uploaded 23 Jan 2025Source
  • 8 Copy of Layout Approval (in case of layout)8_11zon.pdf · uploaded 23 Jan 2025Source
  • 6 Copy of Layout Approval (in case of layout)6_11zon.pdf · uploaded 23 Jan 2025Source
  • 5 Copy of Layout Approval (in case of layout)5_11zon.pdf · uploaded 23 Jan 2025Source
  • 4 Copy of Layout Approval (in case of layout)4_11zon.pdf · uploaded 23 Jan 2025Source
  • 3 Copy of Layout Approval (in case of layout)3_11zon.pdf · uploaded 23 Jan 2025Source
  • 2 Copy of Layout Approval (in case of layout)2_11zon.pdf · uploaded 23 Jan 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentLAYOUT.pdf · uploaded 23 Jan 2025Source
  • 1 a Details of encumbrances concerned to Financedetails encumbrances to finance.pdf · uploaded 24 Jan 2025Source
  • 1 Other – LegalAnnexure A .pdf · uploaded 24 Jan 2025Source
  • 1 CERSAI detailsCERSAI Report.pdf · uploaded 24 Jan 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)A .pdf · uploaded 24 Jan 2025Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report Allotment .pdf · uploaded 24 Jan 2025Source
  • 1 b Details of encumbrances concerned to Legaldetails encumbrances to finance.pdf · uploaded 24 Jan 2025Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsdisclousre in other real estate org-1.pdf · uploaded 24 Jan 2025Source
  • 2 Disclosure of Interest in Other Real Estate Organizationsdisclousre in other real estate org-2.pdf · uploaded 24 Jan 2025Source
  • 3 Disclosure of Interest in Other Real Estate Organizationsdisclousre in other real estate org-3.pdf · uploaded 24 Jan 2025Source
  • 4 Disclosure of Interest in Other Real Estate Organizationsdisclousre in other real estate org-4-output (1).pdf · uploaded 24 Jan 2025Source
  • 5 Disclosure of Interest in Other Real Estate Organizationspdf_to_scan_679cb40d02c67_temp_679cb40a18c78.pdf · uploaded 24 Jan 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)b.pdf · uploaded 24 Jan 2025Source
  • 2 Other – Legalमोशी_305_Satbara (1).pdf · uploaded 25 Jan 2025Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 25 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 (3)-output (2).pdf · uploaded 27 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate RKH Mountain Manor 15-02-2025-output.pdf · uploaded 28 Jan 2025Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER (1).pdf · uploaded 31 Jan 2025Source
  • 1 Declaration in FORM Bform b promoter.pdf · uploaded 1 Feb 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectdis.pdf · uploaded 1 Feb 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation.pdf · uploaded 5 Feb 2025Source
  • 1 Other – Financepdf_to_scan_67a7180535e54_temp_67a717fa6e879.pdf · uploaded 8 Feb 2025Source
  • 2 Copy of the legal title reportUpdated Legal Title report_11zon (1).pdf · uploaded 9 Feb 2025Source
  • 2 a Details of encumbrances concerned to FinanceENCUMBRANCE CERTIFICATE.pdf · uploaded 9 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3(1)-output_11zon.pdf · uploaded 9 Feb 2025Source
  • 2 b Details of encumbrances concerned to LegalENCUMBRANCE CERTIFICATE.pdf · uploaded 9 Feb 2025Source
  • 1 Proforma of Agreement for saleSitai Draft final sitai - sec 2 (1).pdf · uploaded 9 Feb 2025Source
  • 1 Other – Technicalcc verif.pdf · uploaded 11 Feb 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentNA Order for plotted development.pdf · uploaded 4 Mar 2025Source
  • Form 1Form 1 Q4.pdf · uploaded 18 Aug 2025Source
  • Form 2Form 2 Q4.pdf · uploaded 18 Aug 2025Source
  • Form 3Form 3 Q4.pdf · uploaded 18 Aug 2025Source
  • Disclosure of Sold and Booked InventoryPromoters disclosure Q4 RKH M.pdf · uploaded 18 Aug 2025Source
  • Withdrawal Update Form 1Form 1 Q1.pdf · uploaded 24 Aug 2025Source
  • Withdrawal Update Form 1Form 1 Q1.pdf · uploaded 24 Aug 2025Source
  • Withdrawal Update Form 2Form 2 Q1.pdf · uploaded 24 Aug 2025Source
  • Withdrawal Update Form 2Form 2 Q1.pdf · uploaded 24 Aug 2025Source
  • Withdrawal Update Form 3Form 3 Q1.pdf · uploaded 24 Aug 2025Source
  • Withdrawal Update Form 3Form 3 Q1.pdf · uploaded 24 Aug 2025Source
  • Withdrawal Update Form 1FROM 1.pdf · uploaded 26 Aug 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 26 Aug 2025Source
  • Withdrawal Update Form 3FROM 3.pdf · uploaded 26 Aug 2025Source
  • Withdrawal Update Form 1FROM 1.pdf · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 3Form 3 Q1.pdf · uploaded 11 Sep 2025Source
  • Withdrawal Update Form 1FROM 1.pdf · uploaded 13 Sep 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 13 Sep 2025Source
  • Withdrawal Update Form 3Form 3 Q1.pdf · uploaded 13 Sep 2025Source
  • Withdrawal Update Form 1FROM 1.pdf · uploaded 21 Sep 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 21 Sep 2025Source
  • Withdrawal Update Form 3Form 3 Q1 Revised.pdf · uploaded 21 Sep 2025Source
  • Withdrawal Update Form 1FROM 1.pdf · uploaded 24 Sep 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 24 Sep 2025Source
  • Withdrawal Update Form 3Form 3 Q1 Revised.pdf · uploaded 24 Sep 2025Source
  • Withdrawal Update Form 1Sitai Construction Form-1.pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 2Sitai Construction Form-2.pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 3Sitai Cons_Form 3 (1).pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 1Sitai Construction Form 1 (4).pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 2RKH mountain manor engineering certificate 07-01-2026 (1).pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 3Sitai Cons_Form 3 (1).pdf · uploaded 18 Feb 2026Source
  • Withdrawal Update Form 1Q 4 form 1.pdf · uploaded 20 May 2026Source
  • Withdrawal Update Form 2Q 4 Form2.pdf · uploaded 20 May 2026Source
  • Withdrawal Update Form 3Q 4 Form 3.pdf · uploaded 20 May 2026Source
  • Form 5 (FY 2024-2025)Form 5.pdf · uploaded 23 Jul 2026Source
  • Form 2A (FY 2024-2025)Form 2A 2024 25.pdf · uploaded 29 Jul 2026Source
  • Withdrawal Update Form 1Q 1 Form 1.pdf · uploaded 7 Aug 2026Source
  • Withdrawal Update Form 2Q 1 Form 2.pdf · uploaded 7 Aug 2026Source
  • Withdrawal Update Form 3Q 1 form 3.pdf · uploaded 7 Aug 2026Source

Technical

  • Document1_11zon.pdf · uploaded 22 Jan 2025Source
  • Document2_11zon.pdf · uploaded 23 Jan 2025Source
  • Document3_11zon.pdf · uploaded 23 Jan 2025Source
  • Document4_11zon.pdf · uploaded 23 Jan 2025Source
  • Document5_11zon.pdf · uploaded 23 Jan 2025Source
  • Document6_11zon.pdf · uploaded 23 Jan 2025Source
  • Document7_11zon.pdf · uploaded 23 Jan 2025Source
  • Document8_11zon.pdf · uploaded 23 Jan 2025Source
  • DocumentLAYOUT.pdf · uploaded 23 Jan 2025Source
  • Other – Technicalcc verif.pdf · uploaded 11 Feb 2025Source
  • DocumentNA Order for plotted development.pdf · uploaded 4 Mar 2025Source
  • DocumentPlan 1.pdf · uploaded 9 Oct 2025Source
  • DocumentPlan 2.pdf · uploaded 9 Oct 2025Source
  • DocumentPlan 3.pdf · uploaded 9 Oct 2025Source
  • DocumentPlan 4.pdf · uploaded 9 Oct 2025Source
  • DocumentPlan 5.pdf · uploaded 9 Oct 2025Source
  • DocumentPlan 6.pdf · uploaded 9 Oct 2025Source
  • DocumentPlan 7.pdf · uploaded 9 Oct 2025Source
  • DocumentPlan 8.pdf · uploaded 9 Oct 2025Source
  • DocumentPlan 9.pdf · uploaded 9 Oct 2025Source
  • Document2.pdf · uploaded 18 Jul 2026Source
  • Document3.pdf · uploaded 18 Jul 2026Source
  • Document4.pdf · uploaded 18 Jul 2026Source
  • Document5.pdf · uploaded 18 Jul 2026Source
  • Document6.pdf · uploaded 18 Jul 2026Source
  • Document7.pdf · uploaded 18 Jul 2026Source
  • Document8.pdf · uploaded 18 Jul 2026Source
  • Document9.pdf · uploaded 18 Jul 2026Source
  • DocumentLayout.pdf · uploaded 18 Jul 2026Source

Technical (Architect)

  • DocumentQ 1 Form 1.pdf · uploaded 7 Aug 2026Source

Technical (Engineer)

  • DocumentQ 1 Form 2.pdf · uploaded 7 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Moshi, Haveli taluka

Survey, CTS, gat or plot numbers

Gat No. 305P of Mouje-Moshi

Boundaries

North
By Property bearing Gat No 298 and 305
South
By 18 mtr wide DP road
East
By Property bearing Gat No 304 and 305
West
By Property bearing Gat No 299

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectLandmark Design Group—
Chartered accountantCA.Jayesh R Meena—
EngineerSwamiraj Pmc—
OtherAb Asso—
OtherAr Design Tec—
OtherLaxmi Legal—
OtherSkyline Mep—
OtherVastushaili Architects—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology