Skip to content

Amrut Aura

Certificate Signed

Moshi, Pune 412105 |Promoter: Simmoni Developers

29 Dec 2021Registered with MahaRERA
23 Dec 2023Promised completion
22 Dec 2024Revised completionPushed back 1 year
2Buildings
62Units registered36 booked (58%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
2BHK, 3BHK, Office space, Shop62 units in all
Address
Gat No 223 224 228 1 Borhadewadi, Borhadewadi, MoshiPIN 412105
Designated bank account
76
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.68135, 73.83781
Amrut Aura is at latitude 18.68135, longitude 73.83781.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

The latest completion date on record passed 1 year and 10 months ago.

Registered
29 Dec 2021
Promised
23 Dec 2023
Revised
22 Dec 2024

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210003231729 Dec 202123 Dec 202322 Dec 2024Simmoni DevelopersProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A Building1055
B Building57

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

36 of 62 units booked (58%), as the promoter reported to MahaRERA

2BHK · 20 units3BHK · 10 unitsOffice space · 17 unitsShop · 15 units
BuildingTypeCarpet areaUnitsBooked
A Building2BHK58 sq m · 624 sq ft2020
A Building3BHK74 sq m · 797 sq ft11
A Building3BHK78 sq m · 840 sq ft99
A BuildingOffice space10.5 sq m · 113 sq ft33
A BuildingOffice space24.5 sq m · 264 sq ft10
A BuildingOffice space25 sq m · 269 sq ft31
A BuildingOffice space28 sq m · 301 sq ft40
A BuildingOffice space29 sq m · 312 sq ft11
Show all 22 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A BuildingOffice space80 sq m · 861 sq ft20
A BuildingShop23 sq m · 248 sq ft10
A BuildingShop32 sq m · 344 sq ft20
A BuildingShop41 sq m · 441 sq ft21
A BuildingShop43 sq m · 463 sq ft30
A BuildingShop46 sq m · 495 sq ft10
A BuildingShop51 sq m · 549 sq ft20
B BuildingOffice space1,420 sq m · 15,285 sq ft10
B BuildingOffice space1,452 sq m · 15,629 sq ft10
B BuildingOffice space1,586 sq m · 17,072 sq ft10
B BuildingShop325 sq m · 3,498 sq ft10
B BuildingShop440 sq m · 4,736 sq ft10
B BuildingShop473.5 sq m · 5,097 sq ft10
B BuildingShop490 sq m · 5,274 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 140 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardCompany Pan card.pdf · uploaded 26 Nov 2021Source

Legal

  • Legal Title reportFormat A (2).pdf · uploaded 1 Dec 2021Source
  • Legal Title reportSearch title.pdf · uploaded 1 Dec 2021Source
  • Legal Title reportSearch title teport_compressed.pdf · uploaded 1 Dec 2021Source
  • Legal Title reportsearch report (1)_compressed.pdf · uploaded 1 Dec 2021Source
  • Declaration Form BREVISED FORM B.pdf · uploaded 1 Dec 2021Source
Show all 142 documentsShow fewer documents

Migrated

  • 1 PAN CardCompany Pan card.pdf · uploaded 26 Nov 2021Source
  • 1 Details of encumbrancesEncumbrance.pdf · uploaded 26 Nov 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Nov 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_compressed.pdf · uploaded 26 Nov 2021Source
  • 1 Copy of the legal title reportFormat A (2).pdf · uploaded 1 Dec 2021Source
  • 2 Copy of the legal title reportSearch title.pdf · uploaded 1 Dec 2021Source
  • 3 Copy of the legal title reportSearch title teport_compressed.pdf · uploaded 1 Dec 2021Source
  • 4 Copy of the legal title reportsearch report (1)_compressed.pdf · uploaded 1 Dec 2021Source
  • 1 Copy of Layout Approval (in case of layout)IMG-9830.pdf · uploaded 1 Dec 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 1 Dec 2021Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 1 Dec 2021Source
  • 1 Declaration in FORM BREVISED FORM B.pdf · uploaded 1 Dec 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A QUALITY ASSURANCE.pdf · uploaded 1 Dec 2021Source
  • 1 CERSAI detailsCERSAI_Search_Report_200225550115_For_Asset_Based_Search_08_12_2021_18_19_58_381.pdf · uploaded 1 Dec 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate (2).pdf · uploaded 1 Dec 2021Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 1 Dec 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentIMG-9828.pdf · uploaded 2 Dec 2021Source
  • 2 Proforma of Allotment letterRERA Flat Agreement for Borhadewadi Amrut Aura.pdf · uploaded 2 Dec 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentIMG-9827.pdf · uploaded 4 Dec 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentIMG-9826.pdf · uploaded 13 Dec 2021Source
  • 4 Building Plan Approval / NA Order for plotted developmentIMG-9825.pdf · uploaded 20 Dec 2021Source
  • 5 Building Plan Approval / NA Order for plotted developmentAdobe Scan Dec 20, 2021-5.pdf · uploaded 20 Dec 2021Source
  • 6 Building Plan Approval / NA Order for plotted developmentIMG-9824.pdf · uploaded 20 Dec 2021Source
  • 7 Building Plan Approval / NA Order for plotted developmentIMG-9822.pdf · uploaded 20 Dec 2021Source
  • 2 Copy of Layout Approval (in case of layout)PLAN_1_compressed (1).pdf · uploaded 25 Feb 2022Source
  • 8 Building Plan Approval / NA Order for plotted developmentPLAN_2_compressed.pdf · uploaded 25 Feb 2022Source
  • 9 Building Plan Approval / NA Order for plotted developmentPLAN_3_compressed.pdf · uploaded 25 Feb 2022Source
  • 10 Building Plan Approval / NA Order for plotted developmentPLAN_4_compressed.pdf · uploaded 25 Feb 2022Source
  • 11 Building Plan Approval / NA Order for plotted developmentPLAN_5_compressed.pdf · uploaded 25 Feb 2022Source
  • 12 Building Plan Approval / NA Order for plotted developmentPLAN_7_compressed.pdf · uploaded 25 Feb 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 25 Feb 2022Source
  • 3 Proforma of Allotment letterRERA Flat Agreement Amrut Aura_23_2_22 (1).pdf · uploaded 25 Feb 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 29 Mar 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Amrut Aura.pdf · uploaded 29 Mar 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 (2).pdf · uploaded 29 Mar 2022Source
  • 4 Proforma of Allotment letterFLAT AGREEMENT FOR RERA_28_3_22.pdf · uploaded 29 Mar 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Khalsa Form 1 _compressed.pdf · uploaded 6 Jul 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Amrut Aura _compressed.pdf · uploaded 6 Jul 2022Source
  • 1 Disclosure of sold/ booked inventorySIMMONI DEVE-Circular 29_AMRUT AURA (1).pdf · uploaded 6 Jul 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate July-2022 for RERA.pdf · uploaded 6 Jul 2022Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 8 Oct 2022Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Amrut Aura.pdf · uploaded 8 Oct 2022Source
  • 2 Disclosure of sold/ booked inventoryDefault Folder (11).pdf · uploaded 8 Oct 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Oct 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate 13-12-22.pdf · uploaded 4 Jan 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Amrut Aura .pdf · uploaded 4 Jan 2023Source
  • 3 Disclosure of sold/ booked inventorysold_unsold.pdf · uploaded 4 Jan 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 16 Feb 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 23 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 23 Feb 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 (4).pdf · uploaded 28 Feb 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate.pdf · uploaded 24 Mar 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's certificate Amrut Aura March 23.pdf · uploaded 24 Mar 2023Source
  • 4 Disclosure of sold/ booked inventorySold Unsold (6).pdf · uploaded 25 Mar 2023Source
  • 3 Copy of Layout Approval (in case of layout)Plan 1 (2)_compressed.pdf · uploaded 10 Apr 2023Source
  • 13 Building Plan Approval / NA Order for plotted developmentPlan 2 (1)_compressed (1).pdf · uploaded 10 Apr 2023Source
  • 14 Building Plan Approval / NA Order for plotted developmentPlan 3 (2)_compressed.pdf · uploaded 10 Apr 2023Source
  • 15 Building Plan Approval / NA Order for plotted developmentPlan 3 (3)_compressed.pdf · uploaded 10 Apr 2023Source
  • 16 Building Plan Approval / NA Order for plotted developmentPlan 5_compressed.pdf · uploaded 10 Apr 2023Source
  • 17 Building Plan Approval / NA Order for plotted developmentPlan 6_compressed.pdf · uploaded 10 Apr 2023Source
  • 18 Building Plan Approval / NA Order for plotted developmentPlan 4 (1)_compressed (1).pdf · uploaded 10 Apr 2023Source
  • 19 Building Plan Approval / NA Order for plotted developmentPlan 8_compressed.pdf · uploaded 10 Apr 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC (1).pdf · uploaded 10 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A 17-3-23.pdf · uploaded 10 Apr 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Default Folder (3)_compressed.pdf · uploaded 10 Apr 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1_RERA_ARCH_UPDATE_compressed.pdf · uploaded 15 Jun 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)form-2 Amrut aura.pdf · uploaded 15 Jun 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM2A_14_6_23.pdf · uploaded 15 Jun 2023Source
  • 5 Disclosure of sold/ booked inventorySOLD_UNSOLD.pdf · uploaded 15 Jun 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_CERT_compressed.pdf · uploaded 15 Jul 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)arch_letter.pdf · uploaded 22 Sep 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)qu simmoni sep 23.pdf · uploaded 22 Sep 2023Source
  • 6 Disclosure of sold/ booked inventorysold unsld Amrut.pdf · uploaded 23 Sep 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A QUALITY ASSURANCE.pdf · uploaded 26 Oct 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 6 Jan 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2.pdf · uploaded 6 Jan 2024Source
  • 7 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 6 Jan 2024Source
  • 2 Declaration about Commencement CertificateExtension Decleration 1.pdf · uploaded 20 Jan 2024Source
  • 2 a Details of encumbrances concerned to Finance1 Details of encumbrances.pdf · uploaded 2 Feb 2024Source
  • 1 b Details of encumbrances concerned to Legal1 Details of encumbrances.pdf · uploaded 2 Feb 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A.pdf · uploaded 3 Feb 2024Source
  • 3 Details of encumbrancesFORMAT_A-1.pdf · uploaded 10 Feb 2024Source
  • 8 Disclosure of sold/ booked inventoryGetUserDocumentFileContent (23) (1).pdf · uploaded 10 Feb 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsFORMAT_A-3.pdf · uploaded 10 Feb 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsFORMAT_A-4.pdf · uploaded 10 Feb 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT_A-2.pdf · uploaded 10 Feb 2024Source
  • 4 Copy of Layout Approval (in case of layout)Plan_1_6_11zon.pdf · uploaded 20 Mar 2024Source
  • 20 Building Plan Approval / NA Order for plotted developmentPlan_2_7_11zon.pdf · uploaded 20 Mar 2024Source
  • 21 Building Plan Approval / NA Order for plotted developmentPlan_3_8_11zon.pdf · uploaded 20 Mar 2024Source
  • 22 Building Plan Approval / NA Order for plotted developmentPlan_4_9_11zon.pdf · uploaded 20 Mar 2024Source
  • 23 Building Plan Approval / NA Order for plotted developmentPlan_5_2_11zon.pdf · uploaded 20 Mar 2024Source
  • 24 Building Plan Approval / NA Order for plotted developmentPlan_6_3_11zon.pdf · uploaded 20 Mar 2024Source
  • 25 Building Plan Approval / NA Order for plotted developmentPlan_7_4_11zon.pdf · uploaded 20 Mar 2024Source
  • 26 Building Plan Approval / NA Order for plotted developmentPlan_8_5_11zon.pdf · uploaded 20 Mar 2024Source
  • 3 Declaration about Commencement CertificateCC (3).pdf · uploaded 20 Mar 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH_FOEM1.pdf · uploaded 20 Mar 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM-2A ENGINNER'S CERTIFICATE.pdf · uploaded 20 Mar 2024Source
  • 9 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLID INVENTORY SIMMONI.pdf · uploaded 20 Mar 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_CERT_8_2_24_merged_11zon.pdf · uploaded 20 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM-5 SIMMONI DEVELOPERS.pdf · uploaded 20 Mar 2024Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)ilovepdf_merged (43).pdf · uploaded 20 Mar 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentcomplition certificate (1).pdf · uploaded 20 Mar 2024Source

Technical

  • DocumentIMG-9830.pdf · uploaded 1 Dec 2021Source
  • DocumentIMG-9828.pdf · uploaded 2 Dec 2021Source
  • DocumentIMG-9827.pdf · uploaded 4 Dec 2021Source
  • DocumentIMG-9826.pdf · uploaded 13 Dec 2021Source
  • DocumentIMG-9825.pdf · uploaded 20 Dec 2021Source
  • DocumentAdobe Scan Dec 20, 2021-5.pdf · uploaded 20 Dec 2021Source
  • DocumentIMG-9824.pdf · uploaded 20 Dec 2021Source
  • DocumentIMG-9822.pdf · uploaded 20 Dec 2021Source
  • DocumentPLAN_1_compressed (1).pdf · uploaded 25 Feb 2022Source
  • DocumentPLAN_2_compressed.pdf · uploaded 25 Feb 2022Source
  • DocumentPLAN_3_compressed.pdf · uploaded 25 Feb 2022Source
  • DocumentPLAN_4_compressed.pdf · uploaded 25 Feb 2022Source
  • DocumentPLAN_5_compressed.pdf · uploaded 25 Feb 2022Source
  • DocumentPLAN_7_compressed.pdf · uploaded 25 Feb 2022Source
  • DocumentPlan 1 (2)_compressed.pdf · uploaded 10 Apr 2023Source
  • DocumentPlan 2 (1)_compressed (1).pdf · uploaded 10 Apr 2023Source
  • DocumentPlan 3 (2)_compressed.pdf · uploaded 10 Apr 2023Source
  • DocumentPlan 3 (3)_compressed.pdf · uploaded 10 Apr 2023Source
  • DocumentPlan 5_compressed.pdf · uploaded 10 Apr 2023Source
  • DocumentPlan 6_compressed.pdf · uploaded 10 Apr 2023Source
  • DocumentPlan 4 (1)_compressed (1).pdf · uploaded 10 Apr 2023Source
  • DocumentPlan 8_compressed.pdf · uploaded 10 Apr 2023Source
  • DocumentPlan_1_6_11zon.pdf · uploaded 20 Mar 2024Source
  • DocumentPlan_2_7_11zon.pdf · uploaded 20 Mar 2024Source
  • DocumentPlan_3_8_11zon.pdf · uploaded 20 Mar 2024Source
  • DocumentPlan_4_9_11zon.pdf · uploaded 20 Mar 2024Source
  • DocumentPlan_5_2_11zon.pdf · uploaded 20 Mar 2024Source
  • DocumentPlan_6_3_11zon.pdf · uploaded 20 Mar 2024Source
  • DocumentPlan_7_4_11zon.pdf · uploaded 20 Mar 2024Source
  • DocumentPlan_8_5_11zon.pdf · uploaded 20 Mar 2024Source

Technical (Architect)

  • DocumentARCH_FOEM1.pdf · uploaded 20 Mar 2024Source

Technical (Engineer)

  • DocumentForm2.pdf · uploaded 6 Jan 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Moshi, Haveli taluka

Survey, CTS, gat or plot numbers

GAT NO 223 224 228 1 BORHADEWADI

Boundaries

North
18 40 52 90 N 73 50 15 36 E
South
18 40 51 09 N 73 50 15 70 E
East
18 40 51 83 N 73 50 16 21 E
West
18 40 52 79 N 73 50 14 27 E

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVastushali Architects—
Chartered accountantTilokchandani And Associates—
EngineerMr Nitin Kharat—
OtherInvental Projects And Construction—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology