Building A · Ace Augusta

Man · RERA P52100000080

IDBLD_01360423 floorsCompleted
23Sanctioned habitable floorsregistration certificate
30 Sep 2022Revised completionpromised 30 Mar 2021

Floors

23 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100000080 · registered 28 Jun 2017
Promised completion
30 Mar 2021
Revised completion
30 Sep 2022
Sanctioned habitable floors
23

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK51.6 m² (555 sq.ft)23not published
2BHK52 m² (560 sq.ft)16not published
2BHK52.2 m² (562 sq.ft)2not published
2BHK52.9 m² (569 sq.ft)2not published
2BHK53.4 m² (575 sq.ft)8not published
2BHK54.9 m² (591 sq.ft)40not published
2BHK55.1 m² (593 sq.ft)32not published
Total123

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered00028
Open Space00018

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
Show all 11 activitiesShow fewer activities
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Data through12 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology