Wing A and Wing B · Manorath

Lonavala (M Cl) · RERA P52100028793

IDBLD_0377283 floorsPromised date passed
3Sanctioned habitable floorsregistration certificate
30 Jun 2026Revised completionpromised 30 Jun 2026
2 of 42Units bookedMahaRERA project page

Floors

3 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100028793 · registered 30 Mar 2021
Promised completion
30 Jun 2026
Revised completion
30 Jun 2026
Sanctioned habitable floors
3
ProjectId
29,286
ProjectName
Manorath
TotalUnitCount
42
ProjectBuildingId
1,69,465
BuildingNameNumber
Wing A and Wing B
FsiWithSanctionSqmts
4
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
42
ProjectRegistartionNo
P52100028793
ProjectBuildingWingsId
1,72,922
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Wing A and Wing B
NoOfBuildingWingFloorProposed
4
NoOfBuildingWingFloorHabitable
3
NoOfBuildingWingFloorSanctioned
4

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK42.3 m² (456 sq.ft)30
1BHK45.5 m² (490 sq.ft)150
2BHK56.3 m² (606 sq.ft)60
2BHK56.4 m² (608 sq.ft)60
2BHK61.7 m² (664 sq.ft)62
2BHK62.3 m² (671 sq.ft)30
2BHK65.8 m² (708 sq.ft)30
Total422
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology