Ashok Nirvaan
Deregistration on recordLonavala (M Cl), Pune 410401 |Promoter: Truewin Realty Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 8
- Phases
- 8
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 4 Aug 2024
P52100026350The latest completion date on record passed 2 years and 2 months ago.
- Registered
- 11 Sep 2020
- Promised
- 4 Aug 2024
Completion promised for 4 Aug 2024
P52100026371The latest completion date on record passed 2 years and 2 months ago.
- Registered
- 16 Sep 2020
- Promised
- 4 Aug 2024
Completion promised for 4 Aug 2024
P52100026374The latest completion date on record passed 2 years and 2 months ago.
- Registered
- 16 Sep 2020
- Promised
- 4 Aug 2024
Completion promised for 4 Aug 2024
P52100026377The latest completion date on record passed 2 years and 2 months ago.
- Registered
- 16 Sep 2020
- Promised
- 4 Aug 2024
Show 4 more registrations
Completion promised for 4 Aug 2024
P52100026375The latest completion date on record passed 2 years and 2 months ago.
- Registered
- 16 Sep 2020
- Promised
- 4 Aug 2024
Completion promised for 4 Aug 2024
P52100026382The latest completion date on record passed 2 years and 2 months ago.
- Registered
- 16 Sep 2020
- Promised
- 4 Aug 2024
Completion promised for 4 Aug 2024
P52100026418The latest completion date on record passed 2 years and 2 months ago.
- Registered
- 17 Sep 2020
- Promised
- 4 Aug 2024
Completion promised for 4 Aug 2024
P52100026442The latest completion date on record passed 2 years and 2 months ago.
- Registered
- 22 Sep 2020
- Promised
- 4 Aug 2024
8 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100026350 | 11 Sep 2020 | 4 Aug 2024 | — | Truewin Realty Limited | Project page |
| P52100026371 | 16 Sep 2020 | 4 Aug 2024 | — | Truewin Realty Limited | Project page |
| P52100026374 | 16 Sep 2020 | 4 Aug 2024 | — | Truewin Realty Limited | Project page |
| P52100026377 | 16 Sep 2020 | 4 Aug 2024 | — | Truewin Realty Limited | Project page |
| P52100026375 | 16 Sep 2020 | 4 Aug 2024 | — | Truewin Realty Limited | Project page |
| P52100026382 | 16 Sep 2020 | 4 Aug 2024 | — | Truewin Realty Limited | Project page |
| P52100026418 | 17 Sep 2020 | 4 Aug 2024 | — | Truewin Realty Limited | Project page |
| P52100026442 | 22 Sep 2020 | 4 Aug 2024 | — | Truewin Realty Limited | Project page |
Documents
8 documents held by Deedo
Registration certificates
- Registration certificateP52100026350 · 8 Sep 2021ViewSource
- Registration certificateP52100026371 · 8 Sep 2021ViewSource
- Registration certificateP52100026374 · 8 Sep 2021ViewSource
- Registration certificateP52100026377 · 8 Sep 2021ViewSource
- Registration certificateP52100026375 · 8 Sep 2021ViewSource
- Registration certificateP52100026418 · 8 Sep 2021ViewSource
- Registration certificateP52100026382 · 8 Sep 2021ViewSource
- Registration certificateP52100026442 · 8 Sep 2021ViewSource
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- DeregisteredMatched by RERA number
Deregistered: Ashok Nirvaan Phase 2
- DeregisteredMatched by RERA number
Deregistered: Ashok Nirvaan Phase- 3
- DeregisteredMatched by RERA number
Deregistered: Ashok Nirvaan Phase 4
- DeregisteredMatched by RERA number
Deregistered: Ashok Nirvaan Phase 6
- DeregisteredMatched by RERA number
Deregistered: Ashok Nirvaan Phase 5
- DeregisteredMatched by RERA number
Deregistered: Ashok Nirvaan Phase 7
- DeregisteredMatched by RERA number
Deregistered: Ashok Nirvaan Phase 9
- DeregisteredMatched by RERA number
Deregistered: Ashok Nirvaan Phase 8
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Lonavala (M Cl)
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.