Goodwill Metropolis East

Completion due Mar 2028

Lohgaon, Pune 411047 |Promoter: Krishna Buildcon

8 Mar 2022Registered with MahaRERAFirst of 3 registrations
31 Mar 2028Promised completionLatest across registrations
30 Mar 2024Revised completion1 of 3 registrations pushed back, by up to 1 year
2Buildings3 phases
120Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
3
Phases
3
Buildings
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.60392, 73.91164
Goodwill Metropolis East is at latitude 18.60392, longitude 73.91164.

Also registered as

Goodwill Metropolis East Phase 1Goodwill Metropolis East Phase 2Goodwill Metropolis East Phase 3
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

P52100033839

The latest completion date on record passed 2 years and 7 months ago.

Registered
8 Mar 2022
Promised
31 Mar 2023
Revised
30 Mar 2024

Completion promised for 31 Dec 2026

P52100051011
Registered
19 May 2023
Promised
31 Dec 2026

Completion promised for 31 Mar 2028

PR1262022600347
Registered
5 May 2026
Promised
31 Mar 2028

3 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000338398 Mar 202231 Mar 202330 Mar 2024Krishna BuildconProject page
P5210005101119 May 202331 Dec 2026—Krishna BuildconProject page
PR12620226003475 May 202631 Mar 2028—Krishna BuildconProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Wing E121472
Wing F121448

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

4 documents held by Deedo

Registration certificates

  • Registration certificateP52100033839 · 8 Mar 2022ViewSource
  • Registration certificatePR1262022600347 · 5 May 2026ViewSource
  • Registration certificateP52100051011 · 20 Aug 2026ViewSource

Extension certificate

  • Extension certificateP52100033839 · 21 Apr 2023ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Lohgaon

Survey, CTS, gat or plot numbers

283/2283/3+4/1S. NO. 283/3a/1aSURVEY NO 283/3+4/1

Source: registration certificates, as stated there.