Shankeshwaram Plaza

Certificate Signed

Kondhwa Bk, Pune 411048 |Promoter: Surekha Sachin Ghule

16 Oct 2019Registered with MahaRERA
30 Dec 2023Promised completion
1Building
44Units registered25 booked (57%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
Office space, Shop44 units in all
Address
65/A/2/7 And 65/B/2/10, Kondhwa Budruk, Kondhwa BudrukPIN 411048
Developed in phases
No

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2023

The latest completion date on record passed 2 years and 10 months ago.

Registered
16 Oct 2019
Promised
30 Dec 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002276716 Oct 201930 Dec 202330 Dec 2023Surekha Sachin GhuleProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shankeshwaram Plaza1044

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

25 of 44 units booked (57%), as the promoter reported to MahaRERA

Office space · 30 unitsShop · 14 units
TypeCarpet areaUnitsBooked
Office space23.87 sq m · 257 sq ft21
Office space24.06 sq m · 259 sq ft20
Office space28.18 sq m · 303 sq ft41
Office space28.29 sq m · 305 sq ft41
Office space30.33 sq m · 326 sq ft21
Office space30.7 sq m · 330 sq ft43
Office space30.82 sq m · 332 sq ft22
Office space30.97 sq m · 333 sq ft20
Show all 24 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Office space33.42 sq m · 360 sq ft20
Office space36.61 sq m · 394 sq ft22
Office space40.46 sq m · 436 sq ft21
Office space532.13 sq m · 5,728 sq ft11
Office space532.14 sq m · 5,728 sq ft11
Shop19.37 sq m · 208 sq ft11
Shop28.27 sq m · 304 sq ft10
Shop39.39 sq m · 424 sq ft11
Shop40.13 sq m · 432 sq ft21
Shop40.31 sq m · 434 sq ft21
Shop43.08 sq m · 464 sq ft11
Shop43.51 sq m · 468 sq ft22
Shop48.59 sq m · 523 sq ft11
Shop58.3 sq m · 628 sq ft11
Shop69.92 sq m · 753 sq ft11
Shop69.95 sq m · 753 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 110 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 12 Oct 2019Source

Legal

  • OtherGram Panchyat NOC.pdf · uploaded 12 Oct 2019Source
  • Legal Title reportTitle And Search Report.pdf · uploaded 12 Oct 2019Source
  • Legal Title reportTitle And Search Report.pdf · uploaded 12 Oct 2019Source
  • Declaration Form BForm B.pdf · uploaded 12 Oct 2019Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 12 Oct 2019Source
  • 1 Copy of the legal title reportTitle And Search Report.pdf · uploaded 12 Oct 2019Source
Show all 111 documentsShow fewer documents

Migrated

  • 2 Copy of the legal title reportTitle And Search Report.pdf · uploaded 12 Oct 2019Source
  • 1 Details of encumbrancesEncumberance Certificate.pdf · uploaded 12 Oct 2019Source
  • 1 Copy of Layout Approval (in case of layout)Plan 1 by 8 Main Layout.pdf · uploaded 12 Oct 2019Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 2 by 8 Commercial Ground And Meza.pdf · uploaded 12 Oct 2019Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 3 by 8 Commercial 1st 2nd 3rd 4th Floor.pdf · uploaded 12 Oct 2019Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan 4 by 8 Commercial Terrace And Parking.pdf · uploaded 12 Oct 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 12 Oct 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentNA Order.pdf · uploaded 12 Oct 2019Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 12 Oct 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architech Certificate Plaza.pdf · uploaded 12 Oct 2019Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 12 Oct 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 12 Oct 2019Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 12 Oct 2019Source
  • 2 Proforma of Allotment letterAgreement to Sale.pdf · uploaded 12 Oct 2019Source
  • 1 OtherGram Panchyat NOC.pdf · uploaded 12 Oct 2019Source
  • 2 Details of encumbrancesEncumberance Certificate.pdf · uploaded 3 Mar 2022Source
  • 3 Details of encumbrancesEncumberance Certificate.pdf · uploaded 3 Mar 2022Source
  • 4 Details of encumbrancesEncumberance Certificate.pdf · uploaded 3 Mar 2022Source
  • 5 Details of encumbrancesEncumberance Certificate.pdf · uploaded 3 Mar 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 3 Mar 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 3 Mar 2022Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-ARCHITECTS CERTIFICATE.pdf · uploaded 3 Mar 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-ARCHITECTS CERTIFICATE.pdf · uploaded 3 Mar 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 3 Mar 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 3 Mar 2022Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engg Certificate.pdf · uploaded 3 Mar 2022Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engg Certificate.pdf · uploaded 3 Mar 2022Source
  • 1 Disclosure of sold/ booked inventoryDisclosure about closing inventory.pdf · uploaded 3 Mar 2022Source
  • 2 Disclosure of sold/ booked inventoryDisclosure about closing inventory.pdf · uploaded 3 Mar 2022Source
  • 3 Disclosure of sold/ booked inventoryDisclosure about closing inventory.pdf · uploaded 3 Mar 2022Source
  • 4 Disclosure of sold/ booked inventoryDisclosure about closing inventory.pdf · uploaded 3 Mar 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 3 Mar 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 3 Mar 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 3 Mar 2022Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Declaration Association of allottee.pdf · uploaded 3 Mar 2022Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)Declaration Association of allottee.pdf · uploaded 3 Mar 2022Source
  • 3 Status of Formation of Legal Entity (Society/Co Op etc.)Declaration-Association of allottees.pdf · uploaded 3 Mar 2022Source
  • 4 Status of Formation of Legal Entity (Society/Co Op etc.)Declaration-Association of allottees.pdf · uploaded 3 Mar 2022Source
  • 1 Status of ConveyanceDeclaration conveyance deed.pdf · uploaded 3 Mar 2022Source
  • 2 Status of ConveyanceDeclaration - Conveyance Deed.pdf · uploaded 3 Mar 2022Source
  • 3 Status of ConveyanceDeclaration - Conveyance Deed.pdf · uploaded 3 Mar 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5- Signed.pdf · uploaded 10 Mar 2022Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Plaza_Q4_FY2021-22.pdf · uploaded 28 Feb 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.PDF · uploaded 28 Feb 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Plaza_Q1_FY2022-23.pdf · uploaded 28 Feb 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Plaza_Q2_FY2022-23.pdf · uploaded 28 Feb 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Plaza_Q3_FY2022-23.pdf · uploaded 28 Feb 2023Source
  • 2 Copy of Layout Approval (in case of layout)1 Complete Plot Revised Layout Merged.pdf · uploaded 14 Feb 2024Source
  • 4 Building Plan Approval / NA Order for plotted development2 Commercial Revised Plan.pdf · uploaded 14 Feb 2024Source
  • 5 Building Plan Approval / NA Order for plotted development3 Commertial Revised Plan.pdf · uploaded 14 Feb 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 MAR22 FORM1.pdf · uploaded 14 Feb 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 JUNE 22 FORM1.pdf · uploaded 14 Feb 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 SEPT 22 FORM 1.pdf · uploaded 14 Feb 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 Dec22 Form1.pdf · uploaded 14 Feb 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Mar 23 Form 1.pdf · uploaded 14 Feb 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Dec 21 Form 2.pdf · uploaded 14 Feb 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Mar 22 Form 2.pdf · uploaded 14 Feb 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 June 22 Form 2.pdf · uploaded 14 Feb 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 SEPT-22 Form 2.pdf · uploaded 14 Feb 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 Dec 22 Form 2.pdf · uploaded 14 Feb 2024Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 MAR-23 Form 2.pdf · uploaded 14 Feb 2024Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 June 23 Form 2.pdf · uploaded 14 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FY 19-20.pdf · uploaded 14 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FY 20-21.pdf · uploaded 14 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FY 21-22.pdf · uploaded 14 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FY 22-23.pdf · uploaded 14 Feb 2024Source
  • 5 Disclosure of sold/ booked inventoryInventory Details December 22.pdf · uploaded 14 Feb 2024Source
  • 6 Disclosure of sold/ booked inventoryInventory Details March 23.pdf · uploaded 14 Feb 2024Source
  • 7 Disclosure of sold/ booked inventoryInventory Details June 23.pdf · uploaded 14 Feb 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 Form 3 March 23 11zon.pdf · uploaded 14 Feb 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 Form 3 June 23 11zon.pdf · uploaded 14 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)1 Form 5 FY 2021 22.pdf · uploaded 14 Feb 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)2 Form 5 FY 2022 23.pdf · uploaded 14 Feb 2024Source
  • 6 a Details of encumbrances concerned to Finance8 Non Encumberances Certificate Legal.pdf · uploaded 15 Feb 2024Source
  • 1 b Details of encumbrances concerned to Legal8 Non Encumberances Certificate Legal.pdf · uploaded 15 Feb 2024Source
  • 1 Declaration about Commencement Certificate5 Format D Decleration about commencement Certificate.pdf · uploaded 15 Feb 2024Source
  • 1 CERSAI details9 CERSAI Report Sankeshwaram Plaza 200296936428.pdf · uploaded 15 Feb 2024Source
  • 1 Disclosure of Interest in Other Real Estate Organizations10 Disclosure of Interest in Other Real Estate Org.pdf · uploaded 15 Feb 2024Source
  • 1 Proforma of Agreement for sale1 Agreement for Sale.pdf · uploaded 15 Feb 2024Source
  • 3 Proforma of Allotment letter3 Proforma for Allotment Letter.pdf · uploaded 15 Feb 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development1 Part Occupancy Certificate 29 7 22.pdf · uploaded 15 Feb 2024Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development2 Part Occupancy Certificate 5 4 23.pdf · uploaded 15 Feb 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same4 Bank Account Decleration.pdf · uploaded 15 Feb 2024Source
  • 1 Deviation Report with respect to Allotment letter6 Devisation Letter for Allotment Letter.pdf · uploaded 15 Feb 2024Source
  • 1 Deviation Report with respect to model copy of Agreement7 Deviation Report for Agreement to Sales.pdf · uploaded 15 Feb 2024Source
  • 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentDecleration about Full Occupancy Certificate.pdf · uploaded 18 Mar 2024Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)Form 4 Archtect.pdf · uploaded 18 Mar 2024Source
  • 8 Disclosure of sold/ booked inventorySold Unsold Inventory Mar 24.pdf · uploaded 28 Jun 2024Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 March 24_11zon.pdf · uploaded 28 Jun 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFull Completion Certificate Kondhwa Site Residency and Plaza.pdf · uploaded 8 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 2023-24 - Signed.pdf · uploaded 6 Dec 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Certificate_0001.pdf · uploaded 21 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Dec-24.pdf · uploaded 21 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySold Booked Inventory Plaza March 25.pdf · uploaded 30 Apr 2025Source

Technical

  • DocumentPlan 1 by 8 Main Layout.pdf · uploaded 12 Oct 2019Source
  • DocumentPlan 2 by 8 Commercial Ground And Meza.pdf · uploaded 12 Oct 2019Source
  • DocumentPlan 3 by 8 Commercial 1st 2nd 3rd 4th Floor.pdf · uploaded 12 Oct 2019Source
  • DocumentPlan 4 by 8 Commercial Terrace And Parking.pdf · uploaded 12 Oct 2019Source
  • Document1 Complete Plot Revised Layout Merged.pdf · uploaded 14 Feb 2024Source
  • Document2 Commercial Revised Plan.pdf · uploaded 14 Feb 2024Source
  • Document3 Commertial Revised Plan.pdf · uploaded 14 Feb 2024Source

Technical (Architect)

  • Document5 Mar 23 Form 1.pdf · uploaded 14 Feb 2024Source

Technical (Engineer)

  • Document7 June 23 Form 2.pdf · uploaded 14 Feb 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In kondhwa BK, Haveli taluka

Survey, CTS, gat or plot numbers

65/A/2/765/B/2/10

Boundaries

North
Sr No 65 B 2 20
South
Sr No 65 A
East
Sr No 65
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDilip G. Kale & Associates—
Chartered accountantAkshay Ramdas Kadam—
Chartered accountantSheetal M Gadiya—
EngineerKiran Mohan Kalumbe—
OtherAquamat Consultant Pvt. Ltd.—
OtherShree Enterprises—
OtherZopate Electrical Consultant Pvt. Ltd.—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology