Skip to content
Deedo home
Menu
BLD_003858Not yet due8 floors · 32 units

Building A · Sai Savera

Kiwale · RERA PM1260002502537

8Sanctioned habitable floorsregistration certificate
32Unitsregistration certificate
9Floors with commencement certificate
31 Dec 2027Promised completion

Floors

8 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
PM1260002502537 · registered 2 Mar 2026
Promised completion
31 Dec 2027
Sanctioned habitable floors
8
Units
32
Floors with commencement certificate
9

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

No unit inventory yetUnit types and bookings come from MahaRERA's project page, which hasn't been imported for this registration.
SourcesMahaRERA registration certificateFloors and units are as registered; a promoter can revise them in later filings.Methodology