27 Jul 2017Registered with MahaRERA
30 Jun 2019Promised completion
2Buildings
140Units registered109 booked (78%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
1 BHK, 1 RK, 2 BHK140 units in all
Address
859-1, Pune Banglore Highway, KhedShivapurPIN 412205
Designated bank account
76
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.34024, 73.85260
Girisparsh is at latitude 18.34024, longitude 73.85260.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2019

The latest completion date on record passed 7 years and 4 months ago.

Registered
27 Jul 2017
Promised
30 Jun 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000135427 Jul 201730 Jun 201930 Jun 2019Envision Landmarks LLPProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A1360
B1380

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

109 of 140 units booked (78%), as the promoter reported to MahaRERA

1 BHK · 77 units1 RK · 3 units2 BHK · 60 units
BuildingTypeCarpet areaUnitsBooked
A1 BHK29.92 sq m · 322 sq ft22
A1 BHK30.04 sq m · 323 sq ft1010
A1 BHK30.27 sq m · 326 sq ft87
A1 BHK30.47 sq m · 328 sq ft109
A1 BHK30.65 sq m · 330 sq ft99
A1 RK24.34 sq m · 262 sq ft11
A2 BHK42.39 sq m · 456 sq ft22
A2 BHK43.42 sq m · 467 sq ft1010
Show all 17 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A2 BHK43.51 sq m · 468 sq ft88
B1 BHK31.52 sq m · 339 sq ft1010
B1 BHK31.7 sq m · 341 sq ft1813
B1 BHK31.86 sq m · 343 sq ft86
B1 BHK31.88 sq m · 343 sq ft20
B1 RK24.92 sq m · 268 sq ft22
B2 BHK38.98 sq m · 420 sq ft10
B2 BHK42.25 sq m · 455 sq ft206
B2 BHK42.33 sq m · 456 sq ft1914

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 38 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardEnvision Pancard.pdf · uploaded 14 Jul 2017Source

Legal

  • Legal Title reportTitle Search Report.pdf · uploaded 14 Jul 2017Source
  • Declaration Form BForm B Complete Final.pdf · uploaded 26 Jul 2017Source
  • OtherReligare No Dues.pdf · uploaded 26 Oct 2018Source
  • OtherA bldg completion certificate.pdf · uploaded 21 Nov 2018Source
  • OtherB bldg completion certificate.pdf · uploaded 21 Nov 2018Source

Migrated

  • 1 PAN CardEnvision Pancard.pdf · uploaded 14 Jul 2017Source
Show all 39 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportTitle Search Report.pdf · uploaded 14 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Project Layout.pdf · uploaded 14 Jul 2017Source
  • 1 Building Plan Approval (IOD)A Bldg Layout.pdf · uploaded 14 Jul 2017Source
  • 2 Building Plan Approval (IOD)B Bldg Layout.pdf · uploaded 14 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 15 Jul 2017Source
  • 1 Details of encumbrancesEncumbrance final complete.pdf · uploaded 22 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Final Complete.pdf · uploaded 22 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engr form final complete.pdf · uploaded 22 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA_form_final_complete.pdf · uploaded 22 Jul 2017Source
  • 1 Proforma of Allotment letterProforma.pdf · uploaded 24 Jul 2017Source
  • 1 Declaration in FORM BForm B Complete Final.pdf · uploaded 26 Jul 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Certificate RERA Nov 2017 compressed.pdf · uploaded 11 Nov 2017Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Certificate RERA Nov 2017.pdf · uploaded 11 Dec 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engr Certificate RERA Nov 2017.pdf · uploaded 11 Dec 2017Source
  • 2 Certificates of CA (Form 3)CA FORM RERA NOV 2017.pdf · uploaded 11 Dec 2017Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engrs Certificate March 2018.pdf · uploaded 27 Mar 2018Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Envision-ilovepdf-compressed.pdf · uploaded 28 Mar 2018Source
  • 3 Certificates of CA (Form 3)CA Certificate Rera March 2018.pdf · uploaded 29 Mar 2018Source
  • 1 OtherReligare No Dues.pdf · uploaded 26 Oct 2018Source
  • 1 Certificates of Architect (Form 4)Form4 Arch certificate.pdf · uploaded 21 Nov 2018Source
  • 2 OtherA bldg completion certificate.pdf · uploaded 21 Nov 2018Source
  • 3 OtherB bldg completion certificate.pdf · uploaded 21 Nov 2018Source
  • 1 Certificates of CA (Form 5)RERA FORM 5.pdf · uploaded 11 Dec 2018Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate.pdf · uploaded 18 Feb 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentA bldg completion certificate.pdf · uploaded 3 Dec 2019Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentB bldg completion certificate.pdf · uploaded 3 Dec 2019Source

Technical

  • DocumentA Bldg Layout.pdf · uploaded 14 Jul 2017Source
  • DocumentB Bldg Layout.pdf · uploaded 14 Jul 2017Source
  • DocumentProject Layout.pdf · uploaded 14 Jul 2017Source

Technical (Architect)

  • DocumentEnvision-ilovepdf-compressed.pdf · uploaded 28 Mar 2018Source

Technical (Engineer)

  • DocumentEngrs Certificate March 2018.pdf · uploaded 27 Mar 2018Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Khed-Shivapur, Haveli taluka

Survey, CTS, gat or plot numbers

8591

Boundaries

North
Remaining portion of GAT NO 859-1
South
Remaining portion of GAT NO 859-1
East
Service Road Adjacent to NH4 Highway
West
Gat No 859-1-2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSandeep Hardikar & Associates—
Registered real estate agentKapil Dilip Laghate—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology