As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Address
- GAT NO. 1382, 1383/p, 1384, 1386, 1387, 1388, 1389, 1393/p, 1394, 1395/p, 1403, 1404, 1405, 1406 CHAKAN TQ KHED, Chakan Talegaon road, ChakanPIN 410501
- Designated bank account
- 99
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Mar 2027
- Registered
- 24 Jan 2022
- Promised
- 31 Mar 2027
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100032693 | 24 Jan 2022 | 31 Mar 2027 | 31 Mar 2027 | Jagrutsara Structures LLP | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Sara Kasturi Building B | 16 | — |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Documents
1 document held by Deedo, 88 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD JAGRUTSARA STRUCTURES LLP.pdf · uploaded 8 Jan 2022Source
Legal
Migrated
- 1 PAN CardPAN CARD JAGRUTSARA STRUCTURES LLP.pdf · uploaded 8 Jan 2022Source
- 1 Copy of Layout Approval (in case of layout)Layot.PDF · uploaded 13 Jan 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentNA ORDER KASTURI.pdf · uploaded 13 Jan 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 13 Jan 2022Source
Show all 89 documentsShow fewer documents
Migrated
- 1 Declaration in FORM BFORM B KASTURI.pdf · uploaded 13 Jan 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CHARTERED ACCOUNTANTS CERTIFICATE.pdf · uploaded 13 Jan 2022Source
- 1 Proforma of Allotment letterAllotment letter for sara kasturi.pdf · uploaded 13 Jan 2022Source
- 2 Proforma of Allotment letterKasturi agreement.pdf · uploaded 13 Jan 2022Source
- 1 Copy of the legal title reportLEGAL TITLE REPORT.pdf · uploaded 14 Jan 2022Source
- 1 Details of encumbrancesJSLLP-TO WHOM IT MAY CONCERN_0001_compressed.pdf · uploaded 15 Jan 2022Source
- 1 Declaration about Commencement CertificateJSLLP-FORMAT-D_0001.pdf · uploaded 15 Jan 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200228172787_For_Asset_Based_Search_16_01_2022_15_50_48_209.pdf · uploaded 16 Jan 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT'S CERTIFICATE -FORM 1 March 2022_compressed.pdf · uploaded 10 Jul 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 SARA KASTURI BUI B_0001_compressed.pdf · uploaded 10 Jul 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM-2A SARA KASTURI BUI-B Dec 2021.pdf · uploaded 10 Jul 2022Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM-2A SARA KASTURI BUI B MArch 2022.pdf · uploaded 10 Jul 2022Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM-2A SARA KASTURI BUI June 2022.pdf · uploaded 10 Jul 2022Source
- 1 Disclosure of sold/ booked inventoryDISCLOSER OF SOLD-SARA KASTURI BUI-B_0001_compressed.pdf · uploaded 10 Jul 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FOMR 2 A JUNE 2022.pdf · uploaded 3 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Sara Kasturi B (April).pdf · uploaded 14 Sep 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Sara Kasturi B (June).pdf · uploaded 14 Sep 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SARA KASTURI BLDG B Apr 2023.pdf · uploaded 14 Sep 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SARA KASTURI BLDG B Jun 2023.pdf · uploaded 14 Sep 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM- 2A SARA KASTURI BLDG B.pdf · uploaded 14 Sep 2023Source
- 2 Disclosure of sold/ booked inventorySOLD- UNSOLD INVENTORY- SARA KASTURI BLDG B_compressed.pdf · uploaded 14 Sep 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Sara Kasturi Building B_compressed.pdf · uploaded 14 Sep 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100032693 Jagrutsara Sara Kasturi B.pdf · uploaded 14 Oct 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SARA KASTURI BUILDING B.pdf · uploaded 26 Oct 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2- Sara Kasturi B Building.pdf · uploaded 26 Oct 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)SARA KASTURI B BLDG - FORM 1.pdf · uploaded 31 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 SARA KASTURI B BLDG.pdf · uploaded 31 Jan 2024Source
- 3 Disclosure of sold/ booked inventorySOLD UNSOLD B BLDG_compressed.pdf · uploaded 31 Jan 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)SARA KASTURI B BLDGI SELF SECLARATION FORM 3_0001.pdf · uploaded 31 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5_JSS LLP_Sara Kasturi-B.pdf · uploaded 11 Dec 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 Bldg B March.pdf · uploaded 30 Dec 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 Bldg B Jun.pdf · uploaded 30 Dec 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Bldg B Sep.pdf · uploaded 30 Dec 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Bldg B March.pdf · uploaded 30 Dec 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Bldg B Jun.pdf · uploaded 30 Dec 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Bldg B Sep.pdf · uploaded 30 Dec 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Bldg B March.pdf · uploaded 30 Dec 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Bldg B Jun.pdf · uploaded 30 Dec 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 bldg B Sep.pdf · uploaded 30 Dec 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 bldg B Sep.pdf · uploaded 30 Dec 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Kasturi B form-3 of Sara Kasturi B Building.pdf · uploaded 4 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 SARA KASTURI B bldg DEC.pdf · uploaded 9 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 December Kasturi B.pdf · uploaded 9 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Sara Kasturi B bldg.pdf · uploaded 13 Jan 2025Source
- Form 1FORM-1 Sara Kasturi B March 2025.pdf · uploaded 11 Oct 2025Source
- Form 2FORM2 Sara Kasturi B March.pdf · uploaded 11 Oct 2025Source
- Form 3RERA form-3 of Sara Kasturi B Building-310325.pdf · uploaded 11 Oct 2025Source
- Disclosure of Sold and Booked InventorySOLD UNSOLD SARA KASTURI B BLDG MARCH 2025_compressed.pdf · uploaded 11 Oct 2025Source
- Form 1FORM-1 Sara Kasturi B June 2025.pdf · uploaded 11 Oct 2025Source
- Form 2SARA KASTURI B BLDG FORM2 JUNE 2025.pdf · uploaded 11 Oct 2025Source
- Form 3Form3 Declaration Sara kasturi B bldg.pdf · uploaded 11 Oct 2025Source
- Disclosure of Sold and Booked InventorySold-Unsold Sara Kasturi B bldg June.pdf · uploaded 11 Oct 2025Source
- Form 1Form 1 - Architect's Kasturi B SEP 2025.pdf · uploaded 29 Nov 2025Source
- Form 2Form 2 - Engineer's Certificate SEP 2025 Sara kasturi B.pdf · uploaded 29 Nov 2025Source
- Form 3Form 3 Declaration sep Kasturi B Sep 2025.pdf · uploaded 29 Nov 2025Source
- Disclosure of Sold and Booked InventoryDiscloser of bookings Kasturi -B Sep 2025.pdf · uploaded 29 Nov 2025Source
- Form 5 (FY 2024-2025)FORM 5_JSS LLP_Sara Kasturi-B.pdf · uploaded 10 Mar 2026Source
- Form 1FORM -1 Sara Kasturi B 16-01-2026.pdf · uploaded 24 Apr 2026Source
- Form 2Form 2 Sara Kasturi -B.pdf · uploaded 24 Apr 2026Source
- Form 3Form 3 Declaration Sara Kasturi -B.pdf · uploaded 24 Apr 2026Source
- Disclosure of Sold and Booked InventoryDiscloser of Sold Sara Kasturi -B 31-12-2025.pdf · uploaded 24 Apr 2026Source
- Form 2A (FY 2023-2024)FORM -2A Sara Kasturi Bldg B.pdf · uploaded 14 May 2026Source
- Form 1FORM-1 Sara Kasturi B.pdf · uploaded 24 Jun 2026Source
- Form 2FORM-2 Kasturi B.pdf · uploaded 24 Jun 2026Source
- Form 3Self-Declaration Form 3 Kasturi -B.pdf · uploaded 24 Jun 2026Source
- Disclosure of Sold and Booked InventoryDiscloser of Sold - Sara Kasturi B.pdf · uploaded 24 Jun 2026Source
- Occupational CertificateBuilding B.pdf · uploaded 24 Jun 2026Source
- Occupational CertificateSARA KASTURI Occupency Certificate BBuilding.pdf · uploaded 24 Jun 2026Source
Technical
Technical (Architect)
- DocumentSARA KASTURI B BLDG - FORM 1.pdf · uploaded 31 Jan 2024Source
- DocumentFORM-1 Bldg B March.pdf · uploaded 30 Dec 2024Source
- DocumentFORM-1 Bldg B Jun.pdf · uploaded 30 Dec 2024Source
- DocumentForm-1 Bldg B Sep.pdf · uploaded 30 Dec 2024Source
- DocumentFORM-1 SARA KASTURI B bldg DEC.pdf · uploaded 9 Jan 2025Source
Technical (Engineer)
- DocumentFORM-2 SARA KASTURI B BLDG.pdf · uploaded 31 Jan 2024Source
- DocumentFORM-2 Bldg B March.pdf · uploaded 30 Dec 2024Source
- DocumentFORM-2 Bldg B Jun.pdf · uploaded 30 Dec 2024Source
- DocumentFORM-2 bldg B Sep.pdf · uploaded 30 Dec 2024Source
- DocumentFORM -2 bldg B Sep.pdf · uploaded 30 Dec 2024Source
- DocumentFORM-2 December Kasturi B.pdf · uploaded 9 Jan 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | ABS Architects and Associates | — |
| Architect | Advantage Architecture | — |
| Chartered accountant | Yogesh J Agrawal & Co | — |
| Engineer | Er Arvind Gurav | — |
| Engineer | Spectrum Consultants | — |