Skip to content

The Hub

Certificate Signed

Kesnand, Pune 412207 |Promoter: Vtp Corporation LLP

9 Feb 2022Registered with MahaRERA
31 Dec 2023Promised completion
30 Jun 2025Revised completionPushed back 1 year and 6 months
1Building
32Units registered11 booked (34%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
Clinic, Shop32 units in all
Address
S No 626 Part, 625 Part, 652 Part, 654 Part, 661, 662 Part, Kesnand Wagholi Road, KesnandPIN 412207
Designated bank account
85
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.57079, 74.01716
The Hub is at latitude 18.57079, longitude 74.01716.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 6 months

The latest completion date on record passed 1 year and 4 months ago.

Registered
9 Feb 2022
Promised
31 Dec 2023
Revised
30 Jun 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000331099 Feb 202231 Dec 202330 Jun 2025Vtp Corporation LLPProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
The Hub232

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

11 of 32 units booked (34%), as the promoter reported to MahaRERA

Clinic · 2 unitsShop · 30 units
TypeCarpet areaUnitsBooked
Clinic45.29 sq m · 487 sq ft10
Clinic47.84 sq m · 515 sq ft10
Shop9.85 sq m · 106 sq ft10
Shop11.5 sq m · 124 sq ft83
Shop11.53 sq m · 124 sq ft84
Shop11.63 sq m · 125 sq ft60
Shop11.68 sq m · 126 sq ft63
Shop11.76 sq m · 127 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 128 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN CARD_VTP.pdf · uploaded 3 Feb 2022Source

Legal

  • Legal Title reportTitle report - Approved.pdf · uploaded 3 Feb 2022Source
  • Legal Title reportAnnexure A- Title.pdf · uploaded 3 Feb 2022Source
  • Declaration Form BForm B.pdf · uploaded 3 Feb 2022Source
  • OtherDec signed.pdf · uploaded 4 Feb 2022Source
  • Legal Title reportAddendum.pdf · uploaded 4 Feb 2022Source
Show all 130 documentsShow fewer documents

Legal

  • Declaration Form BFORM B - THE HUB.pdf · uploaded 12 Jan 2024Source
  • Declaration Form BForm B_The Hub_10122024.pdf · uploaded 10 Dec 2024Source
  • Declaration Form BForm B_The Hub_10122024.pdf · uploaded 10 Dec 2024Source
  • Declaration Form BForm B_The Hub_10122024.pdf · uploaded 10 Dec 2024Source

Migrated

  • 1 PAN CardPAN CARD_VTP.pdf · uploaded 3 Feb 2022Source
  • 1 Copy of the legal title reportTitle report - Approved.pdf · uploaded 3 Feb 2022Source
  • 2 Copy of the legal title reportAnnexure A- Title.pdf · uploaded 3 Feb 2022Source
  • 1 Details of encumbrancesEncum_Signed.pdf · uploaded 3 Feb 2022Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 3 Feb 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentLAYOUT.pdf · uploaded 3 Feb 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC compressed.pdf · uploaded 3 Feb 2022Source
  • 1 Declaration about Commencement CertificateFormat D_Signed.pdf · uploaded 3 Feb 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 3 Feb 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 3 Feb 2022Source
  • 1 Proforma of Allotment letterAgreement_uploaded on rera.pdf · uploaded 3 Feb 2022Source
  • 2 Proforma of Allotment letterAllotment letter.pdf · uploaded 3 Feb 2022Source
  • 3 Copy of the legal title reportAddendum.pdf · uploaded 4 Feb 2022Source
  • 1 CERSAI detailsPublic search.pdf · uploaded 4 Feb 2022Source
  • 1 OtherDec signed.pdf · uploaded 4 Feb 2022Source
  • 2 Details of encumbrancesPurvanchal The Hub.pdf · uploaded 14 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 - The HUB.pdf · uploaded 3 Dec 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - The Hub 300622.pdf · uploaded 14 Mar 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - The Hub 310322.pdf · uploaded 14 Mar 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - The Hub 300922.pdf · uploaded 14 Mar 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - The Hub 311222.pdf · uploaded 14 Mar 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 31032022.pdf · uploaded 14 Mar 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - The Hub - 300622_compressed.pdf · uploaded 25 May 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3 - KP Square - 300922_compressed.pdf · uploaded 25 May 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 - The Hub - 311222_compressed.pdf · uploaded 25 May 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3 - The Hub - 310323_compressed.pdf · uploaded 25 May 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 31032023.pdf · uploaded 25 Jul 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 30062023.pdf · uploaded 25 Jul 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 THE HUB 30062022.pdf · uploaded 26 Jul 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 THE HUB 30092022.pdf · uploaded 26 Jul 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 THE HUB 31122022.pdf · uploaded 26 Jul 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 HUB 30062023_compressed.pdf · uploaded 21 Aug 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 -The Hub - 310323.pdf · uploaded 25 Aug 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 -The Hub - 300623.pdf · uploaded 25 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A THE HUB 31032023.pdf · uploaded 14 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Form 5 VTP The HUB 22-23.pdf · uploaded 14 Sep 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 30092023.pdf · uploaded 21 Oct 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 THE HUB 30092023.pdf · uploaded 30 Oct 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 THE HUB 30092023.pdf · uploaded 30 Oct 2023Source
  • 1 Disclosure of sold/ booked inventoryTHE HUB 31032022.pdf · uploaded 9 Nov 2023Source
  • 2 Disclosure of sold/ booked inventoryTHE HUB 30062022.pdf · uploaded 9 Nov 2023Source
  • 3 Disclosure of sold/ booked inventoryTHE HUB 30092022.pdf · uploaded 9 Nov 2023Source
  • 4 Disclosure of sold/ booked inventoryTHE HUB 31122022.pdf · uploaded 9 Nov 2023Source
  • 5 Disclosure of sold/ booked inventoryTHE HUB 31032023.pdf · uploaded 9 Nov 2023Source
  • 6 Disclosure of sold/ booked inventoryTHE HUB 30062023.pdf · uploaded 9 Nov 2023Source
  • 7 Disclosure of sold/ booked inventoryTHE HUB 30092023.pdf · uploaded 9 Nov 2023Source
  • 2 Declaration in FORM BFORM B - THE HUB.pdf · uploaded 12 Jan 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 31122023.pdf · uploaded 13 Jan 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 THE HUB 31122023.pdf · uploaded 23 Jan 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 THE HUB 31122023.pdf · uploaded 23 Jan 2024Source
  • 8 Disclosure of sold/ booked inventoryINVENTORY THE HUB 31122023.pdf · uploaded 25 Jan 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 31032024.pdf · uploaded 27 Apr 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 THE HUB 31032024.pdf · uploaded 27 Apr 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 THE HUB 31032024.pdf · uploaded 27 Apr 2024Source
  • 9 Disclosure of sold/ booked inventoryINVENTORY THE HUB 31032024.pdf · uploaded 15 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A THE HUB 31032024.pdf · uploaded 16 May 2024Source
  • 10 Disclosure of sold/ booked inventoryTHE HUB 30062024.pdf · uploaded 16 Jul 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 THE HUB 30062024.pdf · uploaded 17 Jul 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 THE HUB 30062024_compressed.pdf · uploaded 17 Jul 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 The Hub 300602024.pdf · uploaded 20 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)The Hub - Form 5.pdf · uploaded 7 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)The Hub - Form 5.pdf · uploaded 7 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)The Hub - Form 5.pdf · uploaded 7 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 30092024.pdf · uploaded 19 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 30092024.pdf · uploaded 19 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 30092024.pdf · uploaded 19 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryTHE HUB 30092024.pdf · uploaded 21 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryTHE HUB 30092024.pdf · uploaded 21 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryTHE HUB 30092024.pdf · uploaded 21 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3_THE_HUB_30-09-2024_compressed.pdf · uploaded 18 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3_THE_HUB_30-09-2024_compressed.pdf · uploaded 18 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3_THE_HUB_30-09-2024_compressed.pdf · uploaded 18 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 THE HUB 30092024.pdf · uploaded 27 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 THE HUB 30092024.pdf · uploaded 27 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 THE HUB 30092024.pdf · uploaded 27 Nov 2024Source
  • 1 Declaration in FORM BForm B_The Hub_10122024.pdf · uploaded 10 Dec 2024Source
  • 1 Declaration in FORM BForm B_The Hub_10122024.pdf · uploaded 10 Dec 2024Source
  • 1 Declaration in FORM BForm B_The Hub_10122024.pdf · uploaded 10 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - The Hub.pdf · uploaded 13 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 31122024.pdf · uploaded 13 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - The Hub.pdf · uploaded 13 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 31122024.pdf · uploaded 13 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE HUB 31122024.pdf · uploaded 13 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - The Hub.pdf · uploaded 13 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - The Hub 31122024.pdf · uploaded 14 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - The Hub 31122024.pdf · uploaded 14 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - The Hub 31122024.pdf · uploaded 14 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryTHE HUB 31122024.pdf · uploaded 16 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryTHE HUB 31122024.pdf · uploaded 16 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryTHE HUB 31122024.pdf · uploaded 16 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 AS The Hub.pdf · uploaded 21 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)The Hub FORM 2.pdf · uploaded 21 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 The HUb.pdf · uploaded 22 Apr 2025Source
  • Form 1Form 1 The HUb.pdf · uploaded 14 Jun 2025Source
  • Form 2The Hub FORM 2.pdf · uploaded 14 Jun 2025Source
  • Form 3Form 3 the hub.pdf · uploaded 14 Jun 2025Source
  • Disclosure of Sold and Booked InventoryTHE HUB 31032025.pdf · uploaded 14 Jun 2025Source
  • Form 2A (FY 2024-2025)FORM 2A THE HUB.pdf · uploaded 27 Jun 2025Source
  • Form 5 (FY 2024-2025)FORM 5- THE HUB.pdf · uploaded 29 Aug 2025Source
  • Form 5 (FY 2025-2026)Form 5 The Hub FY 2025-2026 sign.pdf · uploaded 21 Sep 2026Source

Technical

  • DocumentLAYOUT.pdf · uploaded 3 Feb 2022Source
  • DocumentLAYOUT.pdf · uploaded 3 Feb 2022Source

Technical (Architect)

  • DocumentFORM 1 The Hub 300602024.pdf · uploaded 30 Sep 2024Source
  • DocumentFORM 1 THE HUB 30092024.pdf · uploaded 19 Oct 2024Source
  • DocumentFORM 1 THE HUB 30092024.pdf · uploaded 19 Oct 2024Source
  • DocumentFORM 1 THE HUB 30092024.pdf · uploaded 19 Oct 2024Source
  • DocumentFORM 1 THE HUB 31122024.pdf · uploaded 13 Jan 2025Source
  • DocumentFORM 1 THE HUB 31122024.pdf · uploaded 13 Jan 2025Source
  • DocumentFORM 1 THE HUB 31122024.pdf · uploaded 13 Jan 2025Source
  • DocumentForm 1 The HUb.pdf · uploaded 22 Apr 2025Source

Technical (Engineer)

  • DocumentFORM 2 THE HUB 30062024.pdf · uploaded 30 Sep 2024Source
  • DocumentForm 2 THE HUB 30092024.pdf · uploaded 27 Nov 2024Source
  • DocumentForm 2 THE HUB 30092024.pdf · uploaded 27 Nov 2024Source
  • DocumentForm 2 THE HUB 30092024.pdf · uploaded 27 Nov 2024Source
  • DocumentForm 2 - The Hub.pdf · uploaded 13 Jan 2025Source
  • DocumentForm 2 - The Hub.pdf · uploaded 13 Jan 2025Source
  • DocumentForm 2 - The Hub.pdf · uploaded 13 Jan 2025Source
  • DocumentThe Hub FORM 2.pdf · uploaded 21 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Kesnand, Haveli taluka

Survey, CTS, gat or plot numbers

625 PART652 PART654 PART661662 PARTS NO 626 PART

Boundaries

North
Part Of Gat No 662 Part
South
Part Gat No 654 Part
East
Adjacent Gaothan
West
Internal Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnkur Associates—
ArchitectMinal Firake—
Chartered accountantAmit Shingvi—
EngineerRajesh More—
EngineerSantosh Mohite—
Registered real estate agent360 Realtors LLP—
Registered real estate agentANAROCK Property Consultants Pvt. Ltd.—
Registered real estate agentBasil Realty & Infra Solution LLP—
Show all 41 professionalsShow fewer professionals
RoleNameRegistration no.
Registered real estate agentBharat Shankar Tawar proprietor of Sai real estate solution—
Registered real estate agentBrickfolio Solutions Private Limited—
Registered real estate agentBullmen Realty India Private Limited—
Registered real estate agentChasing Spaces Private Limited—
Registered real estate agentClearspace Prop-Tech India Private Limited—
Registered real estate agentFirstdoor Realty LLP—
Registered real estate agentFirstkey Realtors Private Limited—
Registered real estate agentHiren Natvarlal Trivedi—
Registered real estate agentHomesfy Realty Limited—
Registered real estate agentInvestoxpert Advisors Private Limited—
Registered real estate agentKamaal Khan—
Registered real estate agentKey Mansions Private Limited—
Registered real estate agentKingsFort Developers Private Limited—
Registered real estate agentKprbsk Realtors Private Limited—
Registered real estate agentKrishna Kumar Panday—
Registered real estate agentLivnest Technologies Private Limited—
Registered real estate agentMagicstone Spaces LLP—
Registered real estate agentParesh Sureshrao Mamidwar—
Registered real estate agentProIndia Realty Private Limited—
Registered real estate agentPropBiz Advisors Private Limited—
Registered real estate agentPropengine Realtech Private Limited—
Registered real estate agentPropertypistol Realty Private Limited—
Registered real estate agentPropnivesh Private Limited—
Registered real estate agentRahri Services Pvt Ltd—
Registered real estate agentRahul Kumar Singh—
Registered real estate agentRealty Assistant Private Limited—
Registered real estate agentRockwellroyal Homes Private Limited—
Registered real estate agentSantosh Pande—
Registered real estate agentSmc Real Estate Advisors Private Limited—
Registered real estate agentSpacewalk Advisors LLP—
Registered real estate agentSquare Yards Consulting Private Limited—
Registered real estate agentThee House Of Real Estate Solutions Private Limited—
Registered real estate agentWillow Stone Realty Private Limited—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology