Carnation · Collina
Kanhe · RERA P52100002704
IDBLD_02785213 floorsPromised date passed
13Sanctioned habitable floorsregistration certificate
30 Mar 2022Revised completionpromised 30 Mar 2022
21 of 66Units bookedMahaRERA project page
Floors
13 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100002704 · registered 2 Aug 2017
- Promised completion
- 30 Mar 2022
- Revised completion
- 30 Mar 2022
- Sanctioned habitable floors
- 13
- ProjectId
- 4,631
- ProjectName
- COLLINA
- TotalUnitCount
- 0
- ProjectBuildingId
- 43,722
- BuildingNameNumber
- CARNATION
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100002704
- ProjectBuildingWingsId
- 43,722
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- CARNATION
- NoOfBuildingWingFloorProposed
- 13
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 13
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2.5BHK A WING | 84 m² (904 sq.ft) | 2 | 1 |
| 2.5BHK A WING | 85 m² (914 sq.ft) | 9 | 7 |
| 2.5BHK B WING | 84 m² (904 sq.ft) | 2 | 0 |
| 2.5BHK B WING | 85 m² (914 sq.ft) | 9 | 3 |
| 2.5BHK C WING | 84 m² (904 sq.ft) | 2 | 0 |
| 2.5BHK C WING | 85 m² (914 sq.ft) | 9 | 1 |
| 2BHK C WING | 81.8 m² (881 sq.ft) | 1 | 0 |
| 3BHK A WING | 97 m² (1,044 sq.ft) | 2 | 0 |
| 3BHK A WING | 97.9 m² (1,054 sq.ft) | 9 | 4 |
| 3BHK B WING | 97 m² (1,044 sq.ft) | 2 | 1 |
Show all 13 unit typesShow fewer unit types
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 3BHK B WING | 97.9 m² (1,054 sq.ft) | 9 | 1 |
| 3BHK C WING | 97 m² (1,044 sq.ft) | 1 | 0 |
| 3BHK C WING | 97.9 m² (1,054 sq.ft) | 9 | 3 |
| Total | 66 | 21 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology