Vizion Galaxy
Completion due Dec 2026Junnar, Maharashtra 410504 |Promoter: Vizion Construction
Project summary
As registered with MahaRERA
- RERA registrations
- 3
- Phases
- 3
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Jan 2018
P52100004006The latest completion date on record passed 8 years and 9 months ago.
- Registered
- 7 Aug 2017
- Promised
- 31 Jan 2018
Completion promised for 31 May 2018
P52100005061The latest completion date on record passed 8 years and 5 months ago.
- Registered
- 9 Aug 2017
- Promised
- 31 May 2018
Completion promised for 31 Dec 2026
P52100077774- Registered
- 29 Oct 2024
- Promised
- 31 Dec 2026
3 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100004006 | 7 Aug 2017 | 31 Jan 2018 | — | Vizion Construction | Project page |
| P52100005061 | 9 Aug 2017 | 31 May 2018 | — | Vizion Construction | Project page |
| P52100077774 | 29 Oct 2024 | 31 Dec 2026 | — | Vizion Construction | Project page |
Documents
3 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Narayangaon
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.