Dream City

Completion due Oct 2026

Jalochi, Pune 413102 |Promoter: Tanaji Sadashiv Pansare

27 Nov 2018Registered with MahaRERAFirst of 2 registrations
31 Oct 2026Promised completionLatest across registrations
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.15381, 74.60695
Dream City is at latitude 18.15381, longitude 74.60695.

Also registered as

Dream City -A Building
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 14 Nov 2021

P52100018706

The latest completion date on record passed 4 years and 11 months ago.

Registered
27 Nov 2018
Promised
14 Nov 2021

Completion promised for 31 Oct 2026

P52100053419
Registered
31 Oct 2023
Promised
31 Oct 2026

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001870627 Nov 201814 Nov 2021—Tanaji Sadashiv PansareProject page
P5210005341931 Oct 202331 Oct 2026—Tanaji Sadashiv PansareProject page

Documents

2 documents held by Deedo

Registration certificates

  • Registration certificateP52100018706 · 9 Sep 2021ViewSource
  • Registration certificateP52100053419 · 31 Oct 2023ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Jalochi

Survey, CTS, gat or plot numbers

193/1GAT NO 193/1

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology