Nyati Equinox
Completion due Sep 2028Haveli, Maharashtra 411021 |Promoter: Mihir Homes Enterprise LLP
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 2 years and 1 month
P52100047984- Registered
- 7 Dec 2022
- Promised
- 31 Aug 2026
- Revised
- 30 Sep 2028
Completion promised for 31 May 2027
P52100054912- Registered
- 15 Feb 2024
- Promised
- 31 May 2027
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100047984 | 7 Dec 2022 | 31 Aug 2026 | 30 Sep 2028 | Mihir Homes Enterprise LLP | Project page |
| P52100054912 | 15 Feb 2024 | 31 May 2027 | — | Mihir Homes Enterprise LLP | Project page |
Documents
3 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- Regulatory order14 Oct 2025Mentioned in the order; may refer to a related project
Regulatory order: PROJECT NAME: NYATI EQUINOX I (Regulatory Case No. 411 OF 2025) dated 14 Oct, 2025.
- Regulatory order14 Oct 2025Matched by RERA number
Regulatory order: PROJECT NAME: NYATI EQUINOX I (Regulatory Case No. 411 OF 2025) dated 14 Oct, 2025.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Bavdhan Kh.
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.